Question

A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturin

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans-1

If this was the only unfished job then WIP Inventory as on 1st January would have been :

Amount 6000 Cost Component Opening Direct Material Opening Direct Labour Opening O/H 7000 4900 17900

Ans-2

Last Year rate = 4900/7000 = 70% of Labour Cost

Current Year rate = (8500+3400)/(10000 + 4000) = 11900/14000 = 85%

Ans-3

DEBIT CREDIT 9500 Date DETAILS 31-Jan Work in Process Inventory Raw Material Inventory (Raw materials consumed on job in curr

Add a comment
Know the answer?
Add Answer to:
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing | Overhead Date Beg. bal. Jan. 1 6,700 7,000 4,900 7,000 10,000 7,500 2,800 4,000 21,000 3,000 15,400 16,500 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,900 + 2,000) $16,500 21,000 15,400 $52,900 $26.45 (a) On the basis of the foregoing data, answer the following questions. (1) What was...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...

  • Question 5 --/1 View Policies Current Attempt in Progress A job order cost sheet for Ryan...

    Question 5 --/1 View Policies Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,700 7,000 4,900 7,000 10,000 8,500 2,200 4,000 3,400 16,800 14,900 21,000 Cost of completed job: Direct materials $14,900 Direct labor 21,000 Manufacturing overhead 16,800 Total cost $52,700 Unit cost ($52,700 + 2,000) $26.35 (a) On the basis of the foregoing data, answer...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job:    Direct materials $13,900    Direct labor 20,000    Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....

  • help please nelurumenda Ajob order cost sheet for Ryan Company is shown below. Job No.92 For...

    help please nelurumenda Ajob order cost sheet for Ryan Company is shown below. Job No.92 For 2,000 Units oport Direct Materials Date Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 7,000 6,400 7.000 se 10,000 500 2,800 4,000 21,000 16,200 3,000 15,400 Cost of completed job: Direct materials $16,200 Direct labor 21,000 Manufacturing overhead 15,400 Total cost $52,600 Unit cost ($52,600 + 2,000) $26,30 Unit cost ($52,600 2,000) $26.30 (a) On the basis of the foregoing data, answer the following...

  • Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct...

    Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct Labor Date For 2,000 Units Manufacturing Overhead 4.900 5,500 Beg. bal. Jan. 1 8 7.000 7.000 9,000 7,200 12 25 27 2.900 4,000 20,000 3.200 15,300 15,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($50,700 2.000) $15,400 20,000 15,300 $50.700 $25.35 (a) On the basis of the foregoing data, answer the following questions. (1) What was the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT