Question

A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturin(a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory(b) Prepare summary entries at January 31 to record the current years transactions pertaining to Job No. 92. (Credit account

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
1
Balance in Work in Process on January 1 17000 =5100+7000+4900
2
Overhead rate:
Last year 70% =4900/7000
Current year 75% =6000/8000
b
Account Titles and Explanation Debit Credit
Work in process inventory 9800 =7000+2800
      Raw materials inventory 9800
(To record raw materials used)
Work in process inventory 13000 =8000+5000
      Factory labor 13000
(To record factory labor used)
Work in process inventory 9750 =6000+3750
    Manufacturing overhead 9750
(To record manufacturing overhead)
Finished goods inventory 49550
      Work in process inventory 49550
(To record job completed)
Add a comment
Know the answer?
Add Answer to:
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job:    Direct materials $13,900    Direct labor 20,000    Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,300 6,000 4,200 8 6,000 12 7,000 5,600 25 2,500 27 4,000 3,200 13,800 17,000 13,000 Cost of completed job:    Direct materials $13,800    Direct labor 17,000    Manufacturing overhead 13,000 Total cost $43,800 Unit cost ($43,800 ÷ 2,000) $21.90 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job...

    Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing | Overhead Date Beg. bal. Jan. 1 6,700 7,000 4,900 7,000 10,000 7,500 2,800 4,000 21,000 3,000 15,400 16,500 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,900 + 2,000) $16,500 21,000 15,400 $52,900 $26.45 (a) On the basis of the foregoing data, answer the following questions. (1) What was...

  • Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct...

    Ajob order cost sheet for Sunland Company is shown below. Job No. 92 Direct Materials Direct Labor Date For 2,000 Units Manufacturing Overhead 4.900 5,500 Beg. bal. Jan. 1 8 7.000 7.000 9,000 7,200 12 25 27 2.900 4,000 20,000 3.200 15,300 15,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($50,700 2.000) $15,400 20,000 15,300 $50.700 $25.35 (a) On the basis of the foregoing data, answer the following questions. (1) What was the...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT