Question

A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

A job order cost sheet for Ryan Company is shown below.

Job No. 92

For 2,000 Units


Date

Direct
Materials

Direct
Labor

Manufacturing
Overhead

Beg. bal. Jan. 1 5,300 6,000 4,200
8 6,000
12 7,000 5,600
25 2,500
27 4,000 3,200
13,800 17,000 13,000
Cost of completed job:
   Direct materials $13,800
   Direct labor 17,000
   Manufacturing overhead 13,000
Total cost $43,800
Unit cost ($43,800 ÷ 2,000) $21.90


(a) On the basis of the foregoing data, answer the following questions.

(1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job?

Balance in Work in Process Inventory on January 1 $enter a dollar amount


(2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (Round answers to 0 decimal places, e.g. 55%.)

Last year Current year
Overhead rate

enter percentages rounded to 0 decimal places

%

enter percentages rounded to 0 decimal places

%


(b) Prepare summary entries at January 31 to record the current year’s transactions pertaining to Job No. 92. (Credit account titles are automatically indented when amount is entered. Do not indent manually.)

Date

Account Titles and Explanation

Debit

Credit

Jan. 31

enter an account title to record raw materials used on January 31

enter a debit amount

enter a credit amount

enter an account title to record raw materials used on January 31

enter a debit amount

enter a credit amount

(To record raw materials used)

31

enter an account title to record factory labor used

enter a debit amount

enter a credit amount

enter an account title to record factory labor used

enter a debit amount

enter a credit amount

(To record factory labor used)

31

enter an account title to record manufacturing overhead

enter a debit amount

enter a credit amount

enter an account title to record manufacturing overhead

enter a debit amount

enter a credit amount

(To record manufacturing overhead)

31

enter an account title to record job completed

enter a debit amount

enter a credit amount

enter an account title to record job completed

enter a debit amount

enter a credit amount

(To record job completed)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution - 1 Calculation of Begining WIP

Particulars Amount
Direct Materials $15,300
Add- Direct Labour $6,000
Add- Manufaturing Overhead $4,200
Cost of Begining Work In Progress $25,500

Balence In WIP Inventory on january 1 $ 25,500

Solution-2 Calculation Of Total Manufacturing Cost for the Current Year

Particulars Manufacturing Cost Labour coat
Incurred On January 12 $5,600 $7,000
Add- Incurred on January 27 $3,200 $4,000
Total Cost $8,800 $11,000

Calculation of Overhead rate

Particulars Working

Last Year

Current Year
Manufacturing Overhead Cost (1) $4,200 $8,800
Labour Cost (2) $6,000 $11,000
Overhead Rate (3)=[(1)/(2)]*100 70% 80%

Sol (b)- Journal Entreis at January31 To job no.92

Account Titles and Explanation Debit Credit
Work in process inventory $8,500 (6000+2500)
      Raw materials inventory $8,500
(To record raw materials used)
Work in process inventory $11,000 (7,000+4,000)
      Factory labor $11,000
(To record factory labor used)
Work in process inventory $8,800 (5,600+3,200)
    Manufacturing overhead $8,800
(To record manufacturing overhead)
Finished goods inventory 43,800
      Work in process inventory 43,800
(To record job completed)
Add a comment
Know the answer?
Add Answer to:
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...

  • MENT RESOURCES Exercise 15-03 A job order cost sheet for Ryan Company is shown below. se...

    MENT RESOURCES Exercise 15-03 A job order cost sheet for Ryan Company is shown below. se 15-03 m 15-01A m 15-04A For 2,000 Units Job No. 92 Manufacturing Overhead Direct Labor Direct Materials Date Score Beg. bal. Jan. 1 Results by Study we 4,200 5.300 6,000 6,000 5,600 7,000 12 2,500 25 3,200 13,000 4,000 27 17,000 13,800 Cost of completed job: $13,800 Direct materials 17,000 Direct labor 13,000 Manufacturing overhead $43,800 Total cost $21.90 Unit cost (S43,800 - 2,000)...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job:    Direct materials $13,900    Direct labor 20,000    Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job...

    Current Attempt in Progress A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials 6,300 7,000 Direct Labor 7,000 For 2,000 Units Manufacturing Overhead 4,900 Date Beg. bal. Jan. 1 8 12 25 27 9,000 7,200 3,000 4,000 20,000 3,200 15,300 16,300 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($51,600 + 2,000) $16,300 20,000 15,300 $51,600 $25.80 (a) On the basis of the foregoing data, answer the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT