1] Given -
a) Material cost for producing concrete = 1000 LE/
b) Concrete Produced per day by crew = 60
c) Number of carpenters required = 8
d) Number of Laborers Required = 3
e) Wages of Carpenter = 20 LE/hour
f) Wages of Laborer = 15 LE/hour
g) Number of working hours per day = 8
h) Overtime rate = 1.5 x Normal time rate
i) New productivity on overtime day = 0.9 times the normal time day productivity
2] To Find -
a) Total cost and Total Duration for executing an underground RC
tank work that requires 800
of concrete.
b) The new cost of the owner want to reduce the activity duration to 10 days
3] Solution -
A)
i)
Let us assume an efficiency rate of 0.83.
So, the concrete produced per day by crew = (0.83 x 60)
/day
As the concrete to be done is 800

ii)



As the total duration is 16 days and wages of Carpenter are 20 LE/hour and 15 LE/hour with 8 working hours per day.




Thus the total duration of concreting is 16 days and total cost of concreting is 826240 LE
B]
To complete the activity in 10 days the working hours of workers needs to be increased to match the new per day requirement of concrete production

For 60
the working hours was 8 per day, so for 96.4
with reduced productivity to 0.9,

Thus a total of 10 days will require 14 hours per day of working hours, this will change the manpower cost but the material cost will remain same, the new manpower cost with 1.5 times the old rates is as below




Thus for the total duration 10 days and total cost of concreting is 843050 LE
Question 5 a- Calculate the Duration and Total Cost of executing an underground RC tank that...
A crew of six carpenters and three laborers will be used to build the formwork for a concrete structure. Work is scheduled for 11 hr/day on Monday through Friday and 8 hr on Saturday. Overtime at a rate of one and one-half will be paid for all hours over 8 hr/day during the week and double-time for all Saturday work. The base wage, taxes, and insurance rates are given in the table. Calculate the hourly, weekly, and monthly cost for...
For a building you need to calculate duration of installing brick with the following information: Total brick area=1861 SF Expected crew is four(4) brick masons and two (2) laborers Productivity rate per brick mason =400 brick/day Brick quantities per square foot of wall surface area= 7.4/SF Productivity rate per brick mason =400 brick/day
cost estimation
PROB #2: LearningCurve An activity to produce 100 units was planned for 40 working days of 8 hours each, for one 5 person crew at KD 10 per hour per person. Because of owner required acceleration, the contractor worked with 2 crews of 5 people each for 10 hour per day. The contractor had to pay KD 15 per hour per person for the overtime hours above 8 hr day. For this work, LP 85% ( for learning...