A company makes 4 products P1, P2, P3 and P4. The raw materials (A, B, C) and the labor hours needed to produce each product is given the table. Also the profit per each of these products is given.
|
A |
B |
C |
Labor hours |
Profit per each |
|
|
P1 |
4 |
0 |
1 |
3 |
$24 |
|
P2 |
0 |
4 |
0 |
1 |
$28 |
|
P3 |
2 |
2 |
2 |
2 |
$20 |
|
P4 |
3 |
1 |
1 |
1 |
$25 |
During next week, the company has:
2800 units of A,
3000 units of B,
1000 units of C
1800 hours of labor available.
The firm operates to achieve maximum profit.
a) Define the variables and formulate the LP.
b) Solve it on Excel and report maximum profit and how much of each products should be produced?
c) Is there any C left over? If so, how much? If not, what is its shadow price (dual value)? Explain what this value means to management.
d) Is there any B left over? If so, how much? If not, what is its shadow price (dual value)? Explain what this value means to management.
e) Interpret the meaning of the lower bound to Labor. That is, explain how the solution would change if the amount of labor fell below that lower value.
f) What is the meaning of reduced cost for each product?
g) Interpret the meaning of the allowable increase and decreases for the objective coefficients.
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
A company makes 4 products P1, P2, P3 and P4. The raw materials (A, B, C)...
Let P1 = number of Product 1 to be produced P2 = number of Product 2 to be produced P3 = number of Product 3 to be produced P4 = number of Product 4 to be produced Maximize 15P1 + 20P2 + 24P3 + 15P4 Total profit Subject to 8P1 + 12P2 + 10P3 + 8P4 ≤ 3000 Material requirement constraint 4P1 + 3P2 + 2P3 + 3P4 ≤ 1000 Labor hours constraint P2 > 120 Minimum quantity needed for...
A company produces and sells 4 types of products – P1, P2, P3, and P4. The table below summarizes the relevant data. Three types of raw materials – RM1, RM2, and RM3 are required for the manufacturing process. The availability and cost per unit for each raw material are specified under the columns Available and Cost per unit, respectively. The company is contractually obligated to produce at least a minimum quantity for each product; these are specified in the row...
A system has four resource types (A, B, C, D) and four processes {P1, P2, P3, P4 }.The maximum demands for each process is P1(4,3,2,2), P2(1,2,3,4), P3(1,1,5,0) and P4(3,2,1,5). The current allocation is: P1(1,2,2,1), P2(1,0,3,3) and P3(1,1,1,0) and P4(2,1,0,3). available resource is P1(3,1,1,2) (a) Is this state a safe state? Explain your all answer by identifying a successful future sequence of processes that makes the state safe.
4. The below table shows four different processors P1, P2, P3, and P4 executing the same program with clock rates and average CPls as shown below. Answer the following showing all the steps. Processor Clock rate CP 1.0 GHz 4.0 GHz 3.0 GHz 2.0 GHz P1 3.0 P2 2.0 P3 1.5 P4 2.5 a. Which processor has the best performance in terms of execution time? (8 Points) b. If the program has 5000 instructions, what is the time spent on...
TB MC Qu. 25-104 Rosie's Company has three products... Rosie's Company has three products, P1, P2, and P3. The maximum Rosie's can sell is 65,000 units of P1, 24,000 units of P2, and 12,000 units of P3. Rosie's has limited production capacity of 9,000 hours. It can produce 12 units of P1, 6 units of P2, and 3 units of P3 per hour. Contribution margin per unit is $5 for the P1, $15 for the P2, and $25 for the...
Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows: Department Product 1 Product 2 Product 3 A 1.95 3.45 2.45 B 2.90 1.90 3.40 C 0.70 0.70 0.70 During the next production period, the labor-hours available are 540 in department A, 440 in department B, and 140 in department C. The profit contributions per unit are $34 for product 1, $37 for product 2,...
Suppose there are 4 processes P1, P2, P3 and P4 getting to ready queue in various arrival times and with various bursts times as detailed in the table below. Using Shortest-remaining-time-first scheduling approach, find waiting time for each process and the average waiting time and provide detailed steps taken to find the answer. Using time quantum of milliseconds. Process Arrival time (ms) Burst Time (ms) P1 0 8 P2 2 3 P3 6 2 P4 9 7 Explain Peterson’s solution...
B A P1 P2 P3 P4 obotex-fc- a External forces on a bracket are as shown in the figure, If P1 = 20 kN,P2 = -10 kN, P3 =P4 = 15 kN, and 'x' = 0.45m. Which of the following expressions can correctly evaluate the reaction at B? Select one: O A. RB = (20a - 20(a+b) - 150 - 13.5) / (a+b) O B. RB = (20b + 150 + 13.5) / (a+b) X C. RB = (20a +...
A company has three production plants P1, P2, P3. In each of these plants, three A, B, C products are manufactured. Suppose that from an input unit it is known that: The first plant produces 4 units of A; 2 of B and 4 of C; the second plant produces 5 units of A; 4 of B and 2 of C; the third plant produces 2 units of A; 4 of B and 5 of C. The claims to the...
Need the process that how we get P2 P1 P4 P3 and waiting time
please
1. Draw a Gantt chart below similar to the ones from lecture that illustrates the execution of the processes using the shortest-job-first CPU scheduling algorithm. Process Arrival Burst | Time Time P. 7 ms 2 ms | P2 Oms 8 ms 11 ms 5 ms P4 4 ms 9 ms P2 P2 P4 P3 oms 8 10 19 24 | Using the chart you drew,...