Mars Corporation uses the completed-contract method. At the end
of the first year of a $9,000,000 contract, the following
information is available:
| Costs to date: | $2,000,000 |
| Estimated costs to complete | 6,000,000 |
| Progress billings during the year | 1,800,000 |
| Cash collected during the year | 1,500,000 |
In the first year, Mars should recognize gross profit of
Answer:
First method:
Mars should recognize the gross profit, the method should be used completed contract method
Calculations are as:
Formula:
Gross profit= contact price-total estimated cost
Total estimate cost= cost to date+estimated cost to complete
Total estimated cost=2000,000+6000,000
=8000,000
Gross profit = 9000,000-800,000
=1000,000(completed contact method)
Second method:
Mars should recognize the gross profit, the method should be use percentage of completion method
Calculations are as:
Formula:
(Cost to date/Total estimated cost)*(contract price-total estimated cost)
Total estimate cost=cost to date+estimated cost to complete
Total estimated cost=2000,000+6000,000=8000,000
Gross profit=(2000,000/8000,000)*(9000,000-8000,000)
=0.25*1000,000
=250000( method used percentage completion method)
Mars Corporation uses the completed-contract method. At the end of the first year of a $9,000,000...
Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of$ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are 4. non-refundable. 2020 2021 2022 Costs to date $360,000 $900,000 $390,000 Estimated costs to complete 1,260,000 380,000 Progress billings during the 305,000 765,000 1,200,000 year Cash collected during the year 280,000 760,000 2,000,000...
question 1
4. Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable. 2022 2021 2020 $390,000 $ 900,000 $360,000 Costs to date 380,000 1,260,000 Estimated costs to complete 420 Doo -1,200,000 765,000 305,000 Progress billings during the year 2,000,000 760,000...
Black Sea Construction Company has a contract to construct a $6,000,000 oil rig at an estimated cost of $5,300,000. The contract is to start in July 2017, and the oil rig is to be completed in October 2019. The following data pertain to the construction period. 2017 2018 2019 Costs to date $1,325,000 $3,720,000 $6,300,000 Estimated costs to complete 3,975,000 2,480,000 — Progress billings during the year 1,200,000 3,200,000 1,600,000 Cash collected during the year 1,000,000 2,340,000 2,660,000 What amount...
grand construction company was awarded a contact to construct
an interchange at the junction of u.s 94 and highway 30 at atotoal
contract price of 8000000$. the estimated total cost to complete
the project were 6000000$.
Cooper Construction Company had a contract starting April 2012, to construct a $9,000,000 building that is expected to be completed in September 2014, at an estimated cost of $8,250,000. At the end of 2012, the costs to date were $3,795,000 and the estimated total...
C) Compute the amount of gross profit to be recognized
each year, assuming the completed-contract method is
used.
During 2017, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2017 $434,300 575,700 301,000 271,000 2018 $859,560 242,440 897,000 817,000 2019 $1,073,000 -0- 1,610,000 1,428,000 Prepare all necessary journal entries for 2018. (Credit...
During year 1, Fox Co. started a construction job with a contract price of $1,500,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year 2: Year 1 Year 2 Cost incurred to date $350,000 $1,100,000 Estimated cost to complete 650,000 0 Billings to date 300,000 1,100,000 Collections to date 100,000 1,000,000 What amount of gross profit should Fox recognize for this job for...
Pickle Company has contracted to build for the city of Charleston a new school. The estimated cost is $6,000,000 and the contract price is $9,000,000. The school took three years to complete as follows: 2020 2021 2022Costs to Date $1.500,000 $4,000,000 $6,200,000Costs to Complete $4,500,000 $2,200,000 $0Amounts Billed to Date $1,300,000 $5,800,000 $9,000,000 Collections to Date $1,300,000 $4,300,000 $9,000,000 a) Determine using the percentage of completion method the gross profit to be recognized for: 2020 2021 2022b) Determine using...
In 2020, Dixon Construction Company was awarded a contract to construct an interchange on Highway 30 at a total contract price of $15,000,000. Construction is expected to take two years to complete. The estimated total costs of the project are $12,000,000. Dixon uses the percentage-of-completion method to account for long-term contracts. During the first year cost of construction totaled $7,200,000 and the total estimated costs for the project are unchanged. a) Prepare the entry to record 2020 construction costs of...
Bigelow Contractors signed a contract to construct a storage facility for RGN manufacturing, Inc. The fixed-fee contract specifies that the facility is to be completed in three years. Bigelow uses the percentage-of-completion method (cost-to-cost approach) to account for its construction transactions. Information related to this contract is summarized in the following table. Contract price $ 2,000,000 2018 2019 2020 Actual construction costs incurred during the year $ 900,000 $ 300,000 $ 600,000 Construction costs incurred in prior years 0 900,000...
Ex. 18-127-Percentage-of-completion and completed-contract methods. On February 1, 2012, Marsh Contractors agreed to construct a building at a contract price of $5,400,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2014. Information relating to the costs and billings for this contract is as follows: 2014 2012 $1,500,000 2,500,000 2,200,000 2,000,000 2013 $4,600,000 $2,640,000 1,760,000 4,000,000 3,500,000 Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date -0-...