Pickle Company has contracted to build for the city of Charleston a new school. The estimated cost is $6,000,000 and the contract price is $9,000,000. The school took three years to complete as follows:
2020 2021 2022
Costs to Date $1.500,000 $4,000,000 $6,200,000
Costs to Complete $4,500,000 $2,200,000 $0
Amounts Billed to Date $1,300,000 $5,800,000 $9,000,000
Collections to Date $1,300,000 $4,300,000 $9,000,000
a) Determine using the percentage of completion method the gross profit to be recognized for:
2020 2021 2022
b) Determine using the completed contract method the gross profit to be recognized for:
2020 2021 2022
We need at least 10 more requests to produce the answer.
0 / 10 have requested this problem solution
The more requests, the faster the answer.
Pickle Company has contracted to build for the city of Charleston a new school. The estimated cost is $6,000,000 and the contract price is $9,000,000. The school took three years to complete as follows:
brady construction company contracted to build an apartment for a
price of $6,000,000.
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred (As of the End During Year of the Year) Situation 2021 2022...
(Long-Term Contract with Interim Loss) On May 1, 2020, Jackson Construction Company contracted to construct a factory building for a total contract price of $9,600,000. The building was completed by May 31, 2022. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2020, 2021, and 2022 are given below. 2020 2021 2022 Contract costs incurred during the year $3,400,000 $2,400,000 $2,900,000 Estimated costs to complete the contract at 12/31 4,600,000 3,100,000 -0-...
Bramble Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $606,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $902,000. The following data pertain to the construction period.
2020 2021 2022 Costs to date $272,700 $466,620 $618,000 Estimated
costs to complete 333,300 139,380 –0– Progress billings to date
273,000 546,000 902,000 Cash collected to date...
Pronghorn Construction Company has entered into a contract
beginning January 1, 2020, to build a parking complex. It has been
estimated that the complex will cost $596,000 and will take 3 years
to construct. The complex will be billed to the purchasing company
at $894,000. The following data pertain to the construction
period.
2020
2021
2022
Costs to date
$274,160
$417,200
$607,000
Estimated costs to complete
321,840
178,800
–0–
Progress billings to date
272,000
550,000
894,000
Cash collected to date...
Ivanhoe Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $599,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $905,000. The following data pertain to the construction period 2020 2021 2022 Costs to date $257,570 $413,310 $609,000 Estimated costs to complete 341,430 185,690 –0– Progress billings to date 270,000 551,000 905,000 Cash collected to date...
Waterway Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $275,080 $412,620 $607,000 Estimated costs to complete 322,920 185,380 –0– Progress billings to date 272,000 545,000 897,000 Cash collected to date...
Grouper Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $266,640 339,360 270,000 240,000 $412,080 193,920 545,000 495,000 2022 $617,000...
Pearl Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $606,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 2021 2022 $272,700 $466,620 $618,000 333,300 139,380 -0- 273,000 546,000 902,000...
During 2020, Riverbed Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2022 2020 2021 Costs incurred to date $404,000 $830,680 $1,069,000 Estimated costs to complete -0 606,000 262,320 Billings to date 300,000 906,000 1,600,000 Collections to date 272,000 810,000 1,416,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 Gross profit recognized in...
Bonita Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $596,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $902,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2020 $256,280 339,720 270,000 240,000 2021 $429,120 166,880 555,000 505,000 2022 $606,000...