Hamilton steel company operates two 10-hours shifts each day. In the past, 600 steel valves were produced by the end of each day. The use of new production line has increased the productivity of the company by 25%. What is the new productivity of producing valves (expressed as valves per hour)?
Note:
1- Only round your final answer to 2 decimal places. Enter your
final answer with 2 decimal places.
2- Only enter the productivity value (without the unit of measure).
For instance, if the productivity is 32.43 valves per hour, only
enter 32.43.
Solution:
Number of working hours = (2 x 10-hours shifts each day) = 20 hours
Total production = 600 steel valves
Productivity is calculated as,
Productivity = Total production / Number of working hours
Productivity = 600 steel valves / 20 hours
Productivity = 30 valves per hour
Now, the productivity of the company is increased by 25%,
New total production = 600 + (25% of 600)
New total production = 750 steel valves
New Productivity = New Total production / Number of working hours
New Productivity = 750 steel valves / 20 hours
New Productivity = 37.50 valves per hour
New Productivity = 37.50
Hamilton steel company operates two 10-hours shifts each day. In the past, 600 steel valves were...
Lake Charles Seafood makes 550 wooden packing boxes for fresh seafood per day, working in two 10-hour shifts. Due to increased demand plant managers have decided to operate three 8-hour shifts per day instead. The plant is now able to produce 750 boxes per day a) Before the change in work rules, the company's productivity per day boxes/hour (round your response to two decimal places) After the change, the new productivity level per day boxes/hour (round your response to two...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.05 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Day 39 Units Produced...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Skaff...
Please answer the following question correctly:
Problem 2-4 A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 7 workers, who together produced an average of 100 carts per hour. Workers receive $15 per hour, and machine cost was $40 per hour. With the new equipment, it was possible to transfer...
A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 5 workers, who together produced an average of 80 carts per hour. Workers receive $17 per hour, and machine cost was $40 per hour. With the new equipment, it was possible to transfer one of the workers to another department, and...
1.
2.
A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 6 workers, who together produced an average of 90 carts per hour. Workers receive $16 per hour, and machine cost was $30 per hour. With the new equipment, it was possible to transfer one of the workers to another...
A company that makes shopping carts for supermarkets and other stores recently purchased some new equipment that reduces the labor content of the jobs needed to produce the shopping carts. Prior to buying the new equipment, the company used 5 workers, who together produced an average of 70 carts per hour. Workers receive $19 per hour, and machine cost was $40 per hour. With the new equipment, it was possible to transfer one of the workers to another department, and...
A company operates three machines during three shifts each day. From production records, the data in the table below were collected. At the .05 level of significance test to determine if the number of breakdowns is independent of the shift. Shift Machine A 46 11 13 B 37 10 11 3 20 15 16 What is the Expected Count for Shift = 2 and Machine = A? A. 33.374 B. 11.665 C. 12.961 D. 40.279
Help Seve A company that makes shopping carts for supermarkets and other stores recenty purchased some new equipment that reduces the labor content of the Jobs needed to produce the shopping carts. Prior to buying the new equipment, the company who together produced an average of 60 carts per hour. Workers new equipment, t was possible to transfer one of the workers to another department, and equipment cost increased by $11 per hour whille output Increased by 5 carts per...