Question

Given the following BILL OF MATERIAL, the number of G's required for each A would be...

Given the following BILL OF MATERIAL, the number of G's required for each A would be _____.

(Hint: draw the product structure diagram first.)

LEVEL

ITEM

QTY

0

A

1

- 1

B

3

  - - 2

D

2

  - - - 3

G

3

- - 2

E

1

- 1

C

2

- - 2

D

3

- - - 3

G

3

- - 2

G

2

  1. 36
  2. 40
  3. 8
  4. 18
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Levello Leveer 30 C (2) Level 2 1 (2) 1G (2) Leveryl G C

For 1 unit of A, B required = 3, C required = 2, D required = 3*2+2*3 = 6+6 = 12

Hence G required = 2*2 (From parent C) + 12*3 (from parent G) = 40

Correct answer is B. 40

Add a comment
Know the answer?
Add Answer to:
Given the following BILL OF MATERIAL, the number of G's required for each A would be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Mass production systems are best scheduled with a) PERT/CPM b) sequencing rules c) linear programming d) line balancing . In the bill of material shown below, how many D's are required to mak...

    Mass production systems are best scheduled with a) PERT/CPM b) sequencing rules c) linear programming d) line balancing . In the bill of material shown below, how many D's are required to make one A? (Hint: draw the product structure diagram) Level Item Qty 2 4 2 a) 5 b) 6 c) 12 d) 14 40. The SPT sequencing rule is most useful when subcontracting is anticipated. a) b) the shop is highly congested. only small tardiness values can be...

  • Consider the end item whose bill of material file is as given in Figure 8-7 of...

    Consider the end item whose bill of material file is as given in Figure 8-7 of your textbook. Suppose that the planning horizon is 8 weeks. Week Forecas 145 Order 168 13 325 279 4 196 213 127 312 273 167 123 b) Suppose that the initial inventory level of B is 1200 and the safety stock level is 20 and a lot-for-lot (LFL) policy is appropriate. There are scheduled receipts of 279, 486 and 523 in weeks 2, 5...

  • 34. Consider the following product structure diagram, representing a bill of materials required to assemble some...

    34. Consider the following product structure diagram, representing a bill of materials required to assemble some finished good A: 009G CCDD (Items A through FF have been sketched as circles for convenience, but represent the same information as a product structure diagram sketched with squares, or any other shapes.) Please answer the following questions, based on this information a. Who is the parent of item N? b. Who are the children of item B? C. List all raw material items...

  • Draw a Product Structure Diagram from the bill of material for a Xavier Skateboard as shown...

    Draw a Product Structure Diagram from the bill of material for a Xavier Skateboard as shown below. Assuming a 10% profit Margin, how should the Xavier be priced? Show your costs per item and total cost Level Item Quantity Unit Cost Total Cost 0 1 2 3 0 Skateboard 1 1 Deck 1 $54.90 1 Grip Tape 1 4.95 1 Wheel Assembly 2 2 Wheels 2 8.95 2 Bearings 4 4.95 2 Truck 1 33.90 1 Nuts & Bolts 4...

  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • As the production planner for Xiangling Hu Products, Inc., you have been given a bill of...

    As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 1 shaft. There is no inventory on hand. a) Design a product structure noting the quantities for each item and show the low-level coding....

  • Show work on excel QM to do this thanks Consider the bill of material for Product...

    Show work on excel QM to do this thanks Consider the bill of material for Product "T'h: To make one unit of"T, it needs one unit of"x" and two units of"M. To make one unit of K, it requires 4 units (Corrected) of ". The gross requirements for J are 200 units in week 6 and 250 units in week 8. Use the data given in the following table, develop the MRP tables for each item for an 8-week planning...

  • Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and...

    Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...

  • Draw the missing major organic product(s), starting material(s), or reagents for each of the following reactions...

    Draw the missing major organic product(s), starting material(s), or reagents for each of the following reactions (DO NOT WRITE +EN AS A PRODUCT (ie draw everything out!)! And remember stereo and regiochemistry.) Assume reagents are in excess unless otherwise indicated. **To make things simple, I indicated what is needed for each section! Please don't just put the answers, but explanations as well on why. Thanks! a) draw the starting material for this reaction. b) draw the product for this reaction....

  • The bill of materials and the data from the inventory records for product A are shown in the figu...

    The bill of materials and the data from the inventory records for product A are shown in the figure to the right. Assume that the MPS start quantities for A are 100 units in weeks 1, 2, and 7. Derive an MRP plan for the components going into product A using the data in the table below Item Data Category L4L 2 weeks 100 (week 2) 350 L4L 1 week None 215 Lot-sizing rule Lead time Scheduled receipts Beginning inventory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT