Question

MS.53 An office furniture manufacturer needs to calculate material requirements for one of its most popular tables. The graph

For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19?
   

For the Office Table above, what are the Planned Order Receipts in the week of 8/8?

   
For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?

   
For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?
  

0 0
Add a comment Improve this question Transcribed image text
Answer #1

or the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in the week of 9/19?

Correct answer is 65
For the Office Table above, what are the Planned Order Receipts in the week of 8/8?

Correct answer is 225


For the Table-Top Assembly above, what are the Net Requirements in the week of 9/19?

Correct answer is 270


For the Table-Top Assembly above, what are the Planned Order Releases in the week of 9/5?

Correct answer is 480

office table final assembly

Week 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26
Gross requirement 500 200 0 600 0 500 0 500 300
Scheduled receipt 0 0 0 0 0 0 0 0 0
Projected on hand Inv. 440 440 15 40 40 40 40 65 65 15
Net requirement 60 185 0 560 0 460 0 435 285
Planned order receipt 75 225 0 600 0 525 0 450 300
Planned order release 225 0 600 0 525 0 450 300 0

Table-top assembly

Week 8/1 8/8 8/15 8/22 8/29 9/5 9/12 9/19 9/26
Gross requirement 225 0 600 0 525 0 450 300 0
Scheduled receipt 80 0 0 0 0 0 0 0 0
Projected on hand Inv. 190 270 45 45 5 5 0 0 30 0
Net requirement 0 0 555 0 520 0 450 270 10
Planned order receipt 0 0 560 0 520 0 480 280 0
Planned order release 0 560 0 520 0 480 280 0 0
Add a comment
Know the answer?
Add Answer to:
For the Office Table above (the first MRP table), what is the Projected On-Hand Inventory in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...

    sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior in the department of management at ISU, recently got a job as a production planner at Honda Automotive Assembly Plant in Lincoln. Alabama. His first task on the job training is to review the master production plan shown below. (Initial inventory = 160 units, Ordering cost = $200 per order Lead time = 1 week, Holding cost = $1 per unit per week. No...

  • supply chain question, please solve it anyone.

    There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of its assemblies/components Part 1:...

  • provide step by step explanation of calculation. thanks

    Case #2 MGT2315  There are two (2) Parts to this case.  The First part (Part 1) requires you to use the information to:1.    Build a Bill of Material (BOM) form the given information2.    Determine the Master Production Schedule (MPS) and3.    Complete the MRP for all parts including the product.   The Second Part (Part 2) will require you to use an indexed BOM to 1.    Create the correct MPS from the provided information2.    create the MRP for the unit and all of...

  • Using the following table and applying the L4L lot sizing rule, what is the projected planned...

    Using the following table and applying the L4L lot sizing rule, what is the projected planned receipts for week 3? L4L Lead Time: 1 1 2 3 4 5 6 7 8 Gross Requirements 90 20 40 60 60 Scheduled Receipts 40 Projected On-Hand Inventory 50 Planned Receipts Planned Order Releases

  • OPMGT301 Homework Assignment 5: MRP You MUST show all your work, including tables for all the...

    OPMGT301 Homework Assignment 5: MRP You MUST show all your work, including tables for all the necessary parts, to get full credit. If you plan to type your answers in a word processor, you may find the following table useful (you can copy-and-paste it for convenience) End Product Week Gross Requirements from Gross Requirements from Gross Requirements Scheduled Receipts Projected On-hand Net Requirements Planned-order Receipts Planned-order Releases 12345678 Product B 12 345 Week Gross Requirements from Gross Requirements from Gross...

  • PLEASE PROVIDE STEP BY STEP CALCULATION PERFORMED IN EXCEL.

    Product XYZ is described as follows: Quantity of each assembly/component is in (brackets) XYZ are made up of assemblies A(3), B, & C(2) Assembly A contains D(2), E(2), & F(3) Assembly B contains part H(2) Assembly C contains parts G(2) & E(2) Inventory Lead- time and Lot Size Information: XYZABCDEFGHLead Time121112222Projected On Hand93125329252039160012568Lot SizeLFLLFL2010LFL10020010050Scheduled Receipts500000001000Safety Stock 105025 **Note** all scheduled receipts are in week 1 Create a product structure tree (Multilevel BOM):       (5 marks) Using Blank MRP sheets, Create a level loaded (discreet, with no remnants) plan    ...

  • One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of tw...

    One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...

  • Using this MRP record and a lead time of 3 weeks, what should the planned orders...

    Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross Requirements Scheduled receipts Projected ending Inventory Net Requirements Planned Receipts Planned Orders 400 500 300 0 C 100 100 300 OA 200 O B. 400 O C. 500 O D. 300 8a Using this MRP record and a lead time of 3 weeks, what should the planned orders be in week 1? 3 4 5 Gross...

  • Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time =...

    Complete the MRP record for a bicycle seat. MRP Record Part Name: Seat Lead time = 1 week On-hand = 40 Safety stock = 20 Order quantity: FOQ = 100 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 70 50 80 80 70 60 80 80 Scheduled receipts Available inventory Net requirements Planned order receipts Planned order releases

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT