a)
| Part : | Period | ||||||
| Lot for lot strategy | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
| Gross requirements | 90 | 160 | 170 | 130 | 0 | 110 | |
| Scheduled receipts | |||||||
| Projected available (beg.) | 160 | 160 | 70 | 0 | 0 | 0 | 0 |
| Inv. On hand (End of period) | 70 | 0 | 0 | 0 | 0 | 0 | |
| Net requirements | 90 | 170 | 130 | 0 | 110 | ||
| Planned order receipts | 90 | 170 | 130 | 0 | 110 | ||
| Planned order releases | 90 | 170 | 130 | 0 | 110 | ||
| Lead time | 1 wk | Lot size | lot for lot |
Holding cost = 70*1 = 70
Ordering cost = 4*200 = 800 [As there has been 4 orders]
Total cost = 70+800 = 870
b)
| Part : | Period | ||||||
| EOQ lot sizing (EOQ=200) | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
| Gross requirements | 90 | 160 | 170 | 130 | 0 | 110 | |
| Scheduled receipts | |||||||
| Projected available (beg.) | 160 | 160 | 70 | 110 | 140 | 10 | 10 |
| Inv. On hand (End of period) | 70 | 110 | 140 | 10 | 10 | 100 | |
| Net requirements | 90 | 60 | 100 | ||||
| Planned order receipts | 200 | 200 | 200 | ||||
| Planned order releases | 200 | 200 | 200 | ||||
| Lead time | 1 wk | Lot size | 200 |
Holding cost = (70+110+140+10+10+100)*1 = 440
Ordering cost = 3*200 = 600
Total cost = 440+600 = 1040
c)
| Part : | Period | ||||||
| POQ lot sizing | 0 | 1 | 2 | 3 | 4 | 5 | 6 |
| Gross requirements | 90 | 160 | 170 | 130 | 0 | 110 | |
| Scheduled receipts | |||||||
| Projected available (beg.) | 160 | 160 | 70 | 240 | 70 | 70 | 70 |
| Inv. On hand (End of period) | 70 | 240 | 70 | 70 | 70 | 70 | |
| Net requirements | 90 | 60 | 40 | ||||
| Planned order receipts | 330 | 130 | 110 | ||||
| Planned order releases | 330 | 130 | 110 | ||||
| Lead time | 1 wk | Lot size | POQ |
Holding cost = (70+240+70+70+70+70) = 590
Ordering cost = 3*200 = 600
Total cost = 590+600 = 1190
d) Lot sizing is best as it costs least
sement 5. [Lot Sizing in Material Requirement System (MRP) (10 pts) Type: C Michael Jordan, senior...
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
please answer the question asap.
24. Given 150 units of on hand inverntory, a lead time of one period, an ordering cost of $400, and a holding cost of S$2 per unit per period, determine the lowest cost lot sizing technique among Lot for Lot, and EOQ Use the gross requirements as given in the tables. Calculate here: Lot for Lot Period # 250 350 200 406 450 Gross 170 165 Requirement On Hand Inventory Requirements order receipts order release...
Using the following table and applying the L4L lot sizing rule, what is the projected planned receipts for week 3? L4L Lead Time: 1 1 2 3 4 5 6 7 8 Gross Requirements 90 20 40 60 60 Scheduled Receipts 40 Projected On-Hand Inventory 50 Planned Receipts Planned Order Releases
One unit of A is made of two units of B and one unit of C. B is made of three units of D and one unit of F. C is composed of three units of B, one unit of D, and four units of E. D is made of one unit of E. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
For the Office Table above (the first MRP
table), what is the Projected On-Hand Inventory in
the week of 9/19?
For the Office Table above, what are the
Planned Order Receipts in the week of 8/8?
For the Table-Top Assembly above, what are the
Net Requirements in the week of 9/19?
For the Table-Top Assembly above, what are the
Planned Order Releases in the week of 9/5?
We were unable to transcribe this imageMS.53 An office...
One unit of A is made of one unit of B and one unit of C. B is made of four units of C and one unit each of E and F. C is made of two units of D and one unit of E. E is made of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two-week lead times; and Item D has a lead time of...
Problem 14-5 To simplify data handling to include the receipt of orders that have actually been placed in previous periods, the following six-level scheme can be used. (A number of different techniques are used in practice, but the important issue is to keep track of what is on hand, what is expected to arrive, what is needed, and what size orders should be placed.) One unit of A is made of three units of B, one unit of C, and...
Fill in the following question marks (?) to complete thr MRP
Chart.
E l T able Chart Text Shape Media Comment Share Sheet3 Sheet4 Sheets W X Y Z AA AB AC AD AE AF AG Dibing Rule Lat for Lot 7 40 16 - t ei A Leadtine 2 weeks PD 1 2 3 4 5 6 163425 0 0 0 0 0 72 259 0 0 0 0 25 25 50 40 LO 25 25 50 40 25...