The following info is available for drawing a PERT network using AOA.
*(More than one answer may be selected)*
|
Activity |
Immediate Predecessors |
Activity Duration (days) |
|
A |
-- |
10 |
|
B |
-- |
13 |
|
C |
A |
12 |
|
D |
B |
15 |
|
E |
A |
13 |
|
F |
C |
16 |
|
G |
D,E |
10 |
|
H |
G,F |
5 |
| a. |
the critical path includes: B, D, G, and H. |
|
| b. |
the slack on activity G is not 11 days. |
|
| c. |
there is one critical path. |
|
| d. |
the total duration to complete the project is 40 days. |
|
| e. |
the critical path includes: A, C, F, and H. |
|
| f. |
the slack on activity D is 5 days. |
|
| g. |
the slack on activity H is less than 1 day. |
|
| h. |
the slack on activity C is not 5 days. |
|
| i. |
the slack on activity E is more than 5 day. |
|
| j. |
the total duration to complete the project is more than 40 days. |

The following info is available for drawing a PERT network using AOA. *(More than one answer...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Problem 5: For the given activity network, if there are 35 days required to complete the project, find the following Complete the network by filling in ES, LS, EF and LF Earliest start for activities D, E, F, H, G, L, M ill. Earliest finish for activities D, E, F, H,G,L,M Latest start for activities D, E, F, H, G, LM V. Latest finish activities D, E, F.H.GLM vi. Slack/Float time for each activities D, E, F, H, G, LM...
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project: Activity Activity Time (days) Immediate Predecessor(s) A 3 − B 4 A C 5 B D 7 C E 6 C F 2 C G 4 F H 4 D, E, G Determine the project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 23 day(s). (Enter your response as a whole number.) c. What is...
For the activities given in the table: Draw the AOA network diagram Find the critical activities Find the critical path Find the project completion time Time (days) Predecessors Activity Description Initial Paperwork A 3 Build Body B A 3 C Build Frame A 2 Finish Body 3 D E Finish Frame C Final Paperwork B,C 3 G Mount Body to Frame D,E 6 Install Skirt on Frame C 2 H A FLO
For the activities given in the table: Draw...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
b. Determine the project’s critical path and duration.(this is
number b wuestion) please answer this two b and c questions
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...
Q1. a) Draw a project network using (AOA) method, b) and calculate (EST, EFT, LFT, LST) for each activity, c) and define the critical path. Activity Symbol A B C Predecessor Activity D E F G Duration (Weeks) Nil Nil Nil 5 9 4 B 7 AC C 8 7 D F
Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?
A construction company has a project proposal, which takes 10 activities as follows: Activity Predecessors Activity Duration Time (In DAYS ) Early Start (ES) (In DAYS ) Early Finish (EF) (In DAYS ) Late Start (LS) (In DAYS ) Late Finish (LF) (In DAYS ) SLACK (In DAYS ) A - 14 B - 13 C A 11 D A 15 E B 14 F B 11 G D, E 13 H F 15 J C 12 K G,H 11...
Network Diagrams & PERT Question:
We are remodeling the da Vinci Lounge in the Spencer Engineering
Building.
A. Identify the critical path
B. Identify the slack for each element
C. Identify the most and least sensitive element
D. Identify the predicted project duration (TE)
E. Z is the number of standard deviations from the mean found in
the statistical table below, and
defined by the relationship:
Z = (Ts - TE) / SQRT(Σσte2 ) where only critical path σte are...