Question

Your firm is implementing a new energy efficiency project. The initial cost will be $235.000. and the useful life of the need
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.

Mean value of savings = (37000 + 4 * 29000 + 18000) / 6 = 28500

NPW of the project = -235000 + 28500 * (P/A,10%,8)

= -235000 + 28500 *5.334926

= -82954.61

b.

Expected value of savings = 0.2* 37000 + 0.55* 29000 + 0.25 *18000 = 27850

NPW of the project = -235000 + 27850 * (P/A,10%,8)

= -235000 + 27850 *5.334926

= -86422.31

Add a comment
Know the answer?
Add Answer to:
Your firm is implementing a new energy efficiency project. The initial cost will be $235.000. and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Installing new machinery will cost $170,000. The installation will result in following annual saving: (a) Optimistic...

    Installing new machinery will cost $170,000. The installation will result in following annual saving: (a) Optimistic scenario: $22,000 annual saving with 22% probability, (b) Most likely scenario: $12,000 annual saving with 48% probability, and (c) Pessimistic scenario: $4,000 annual saving with 30% probability. The interest rate can be 5% or 8% (equally likely) and the machinery should have a useful life of 40 years. i. What is the present worth for each estimated value? What is the expected present worth?...

  • An improved design of a computerized piece of continuous quality measuring equipment used to control the thickness of rolled sheet products is being developed. It is estimated to sell for $125,000 mor...

    An improved design of a computerized piece of continuous quality measuring equipment used to control the thickness of rolled sheet products is being developed. It is estimated to sell for $125,000 more than the current design. Based on present test data, however, the typical user has the following probabilities of achieving different performance results and cost savings (relative to the current unit) in the first year of operation (assume these annual cost savings would escalate 5% per year thereafter; a...

  • A new equipment costing $100K is required to manufacture a product that has an uncertain market...

    A new equipment costing $100K is required to manufacture a product that has an uncertain market potential. The marketing department has come up with the following market potential.                         Pessimistic       Most likely       Optimistic                                                  Estimate           Estimate Probability        0.3                   0.5                   0.2 Annual sales     $25K                $50K                $65K The product may be on the market for 3 or 4 or 5 years with probabilities of 0.15, 0.5 and 0.35, respectively. a. If MARR is 8%, prepare a joint probability distribution table and compute...

  • New equipment used to control the thickness of fibre cement sheet cladding is being developed. It...

    New equipment used to control the thickness of fibre cement sheet cladding is being developed. It is estimated to sell for $130,000 more than the current design Based on present product data, the typical installer has the following probabilities of achieving different performance results and cost savings (relative to the current unit) in the first year of operation (assume these annual cost savings would be escalated 5% per year thereafter; a five-year analysis period is appropriate for this situation; the...

  • A project your firm is considering for implementation has these estimated costs and revenues: an investment...

    A project your firm is considering for implementation has these estimated costs and revenues: an investment cost of $57,673, maintenance costs that start at $5,000 at end-of-year (FOY) one and increase by $1,000 for each of the next four years, and then remain constant for the following five years; savings of $23,331 per year (EOY 1-10); and finally a resale value of $29,564 at EOY 10. If the project has a 10-year life and the firm's MARR is 10% per...

  • please show work and box answers 5. (15 points) A project is estimated in the face of a MARR = 15% as follows: Opti...

    please show work and box answers 5. (15 points) A project is estimated in the face of a MARR = 15% as follows: Optimistic Most likely Pessimistic Investment $45,000 $50,000 $55,000 Service life 6 years 5 years 4 years Salvage value $15.000 $12,000 $10,000 Net annual return $16,000 $13,000 $10,000 Find the annual equivalent amount for each possible outcome

  • The RW, Inc. is proposing an investment in energy-saving equipment. The new equipment requires a $9...

    The RW, Inc. is proposing an investment in energy-saving equipment. The new equipment requires a $9 million investment. The attraction of the new equipment is that it would create an operating cost savings by cutting manufacturing costs. Currently, these costs are $8 per unit. However, as the following table shows, there is some uncertainty both about future sales and about the performance of the new machinery: Pessimistic Expected Optimistic Sales (Millions of Cost with new Economic life of new 0.4...

  • A project has a life of 10 years and no salvage value. Your firm uses an...

    A project has a life of 10 years and no salvage value. Your firm uses an MARR of 8% to evaluate projects. The project has uncertain costs and revenue as shown in the table below: Net Revenue $32,000 0.15 $43,000 0.55 $53,0000.30 Probability Initial Cost Probability $130,000 0.25 240,000 0.60 $340,000 0.15 Determine the expected value of the EUAW for the project. Express your answer in $ to the nearest $100.

  • Intro Consider a project with a 4-year life. The initial cost to set up the project...

    Intro Consider a project with a 4-year life. The initial cost to set up the project is $100,000. This amount is to be linearly depreciated to zero over the life of the project and there is no salvage value. The required return is 15% and the tax rate is 34%. You've collected the following estimates: Base case Pessimistic Optimistic Unit sales per year (Q) 7,000 5,000 9,000 Price per unit (P) 50 4 0 Variable cost per unit (VC) 20...

  • u it Cost Ul Capital is 6%. Calculate the percentage increase in the net present worth...

    u it Cost Ul Capital is 6%. Calculate the percentage increase in the net present worth of the project if the annual revenues are increased by 1%. Answer: Question 13 Not yet answered Points out of 3.75 P Flag question (NOTE: ENTER YOUR ANSWER WITHOUT THE S AND COMMA, ROUNDED TO THE NEAREST DOLLAR, for instance as 10023, not as $10,022.78. Insert the negative sign in front of your answer if it is negative. Do not round intermediate calculations!) Supersmart...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT