Question 2. (30%)
The following table provides the information necessary to construct project network and calculate a total project cost. In case of activity crash, the information includes crash cost for each activity.
|
Activity |
Immediate predecessor(s) |
Activity time (weeks) |
Normal cost (x1000$) |
Additional cost for crashing one week (x1000$) |
|
|
Normal |
After maximum crash |
||||
|
A |
- |
16 |
12 |
2,000 |
300 |
|
B |
- |
14 |
9 |
1,000 |
160 |
|
C |
A |
8 |
6 |
500 |
100 |
|
D |
A |
5 |
4 |
600 |
700 |
|
E |
B |
4 |
2 |
1,500 |
750 |
|
F |
C |
6 |
4 |
800 |
400 |
|
G |
D, E |
15 |
14 |
5,000 |
600 |
|
H |
F, G |
10 |
9 |
3,000 |
500 |
Crash the project network the maximum amount possible and make sure that the new crush adds minimum cost every time. Show the changes in total project duration and the total project cost for every crush.


Question 2. (30%) The following table provides the information necessary to construct project network and calculate...
1) Based on the given information regarding the activities for
the project, the project length= ___ weeks.
2) The total cost required for completing this project on normal
time= $____
3) For reducing the duration of the project by one week, the
activity that should be crashed first is activity ___.
4) The cost of the project based on the first activity selected
for crashing will increase by $___.
5) The maximum weeks by which the project can be reduced...
Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 narl Case Study A Table 1 below contains activities associated with a...
Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...
2. A student has developed a project and is interested in accelerating the schedule. Below network diagram (Activity on Arrow) and table show all information needed. Partial crashing is available. Show your work for crashing. Accelerated Duration Cost Present Duration Cost $100 4 $50 5 $250 2 $200 3 a h 3 $100 $350 C d 3 $100 cannot accelerate 6 $100 $150 e f 7 $300 5 $600 a) Without any crashing (acceleration), how long is the project expected...
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noquera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: To Cost Normal Time (weeks) Crash Time Normal with Activity (weeks) Cost Crashing Immediate Predecessor(s) $2.700 A $2,000 7 $2,300 S3,100 3 $500 $500 S2,300 $2,580 A E 5900 $1.275 F F $3.400 2 S4,800 C G $1,500 $2.100 D, E a) Based on...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
hi need answers for this urgently thanks
Question 2 (20 Marks) a) Given the following project details, identify the project's critical path; Activity Predecessor A B Duration (Man Days) 5 10 12 8 6 15 D Ε F B, C GE CD G H 20 18 30 5 I,J к F, L M (10 Marks) Continued... b) Given the information below, identify how much it would cost for each day you crash the schedule. Determine the total cost for crashing...
What is the minimum cost of crashing the following project that
Roger Solano manages at Slippery Rock University by 4 days?
Please show work and calculations.
NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300 400 C 4 3 500 600 5 3 900 1,200 A 5 1,000 1,600 C LO LO C Ln LLI
NORMAL CRASH TIME ACTIVITY (DAYS) (DAYS) TIME NORMAL CRASH COST IMMEDIATE COST PREDECESSOR(S) 900 $1,000 B 300...
Non wission er absurd submisen Problem [10 points The following table provides the informationery a project to appet crash data Activity Cost data is cost per week ez. A week is the cost of crashing for ce week Cath the propetas much as po. Mas lowance for crash 55.000/werk Activity Activity Activity Activity Time (weeks) Costis Predecessor Normal Crash Normal Crash 16 2000 4400 14 1.000 1.800 500 700 5 600 1.300 4 2 1.500 6 4 800 1000 10...
Below is a four-activity project network presented in activity-on-node form, along with information on crashing opportunities for each activity: Crash Cost Per Activity Normal Minimum Possible Time Time Complete the following tabulation of crashing cost vs. project length: Step ProjectIncremental Crashing Cost/Da Total Crashing Cost Activities to Crash Length 16
Below is a four-activity project network presented in activity-on-node form, along with information on crashing opportunities for each activity: Crash Cost Per Activity Normal Minimum Possible Time Time Complete the...