Question

A specific product has demand during lead time of 100 units, with a standard deviation during...

A specific product has demand during lead time of 100 units, with a standard deviation during lead time of 25 units. What safety stock (approximately) provides a 95% service level?

The answer is 41. How do you arrive at this answer? (what are the calculations)

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Demand during lead time \(=100\) units

Standard deviation \(\sigma_{\mathrm{L}}=25\)

Service level, \(Z=95 \%\) and its value is \(1.64\)

$$ \begin{aligned} \text { Safety stock } &=Z \sigma_{L} \\ &=1.64 \times 25 \\ &=41 \end{aligned} $$

Add a comment
Know the answer?
Add Answer to:
A specific product has demand during lead time of 100 units, with a standard deviation during...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • A specific product has demand during lead time of 100 units, with a standard deviation during...

    A specific product has demand during lead time of 100 units, with a standard deviation during lead time of 25 units. What safety stock (approximately) provides an 85% service level? A. 133 B. 165 C. 26 D. 41 O E. 126

  • 1. A specific product has demand during lead time of 350 units, with a standard deviation...

    1. A specific product has demand during lead time of 350 units, with a standard deviation during lead time of 80 units. Management wants a 99% service level. a) What value of Z should be applied? b) How many units should be carried as safety stock? c) What is the appropriate reorder point?

  • Given this information: Expected demand during lead time = 285 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 285 units Standard deviation of lead time demand = 16 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 1 percent during lead time. (Round your answer to the nearest whole number.) ROP _____ units    b. The safety stock needed to attain a 1 percent risk of stockout during lead time. (Do...

  • Given this information: Expected demand during lead time = 295 units Standard deviation of lead time...

    Given this information: Expected demand during lead time = 295 units Standard deviation of lead time demand = 20 units Use Table. Determine each of the following, assuming that lead time demand is distributed normally: a. The ROP that will provide a risk of stockout of 2 percent during lead time. (Round your answer to the nearest whole number.) ROP             units    b. The safety stock needed to attain a 2 percent risk of stockout during lead time....

  • The demand for an electronic component is normally distributed with an average demand during lead time...

    The demand for an electronic component is normally distributed with an average demand during lead time of 4500 units and a standard deviation of 150. If a service level of 95% is desired, then the company’s safety stock for this component is approximately? A) 150 units. B) 247 units. C) 336 units. D) 740 units.

  • Daily demand for a product is 100 units, with a standard deviation of 15 units. The...

    Daily demand for a product is 100 units, with a standard deviation of 15 units. The review period is 20 days and the lead time is 10 days. At the time of review there are 50 units in stock. If 98 percent service probability is desired, how many units should be ordered? (Use Excel's NORMSINV() function to find the correct critical value for the given α-level. Do not round intermediate calculations. Round "z" value to 2 decimal places and final...

  • Daily demand for a product is 100 units, with a standard deviation of 15 units. The...

    Daily demand for a product is 100 units, with a standard deviation of 15 units. The review period is 20 days and the lead time is 10 days. At the time of review, there are 50 units in stock. If 98 percent service probability is desired, how many units should be ordered? (Use Excel's NORM.S.INV() function to find the z value. Round z value to 2 decimal places and final answer to the nearest whole number.) Ordered quantity units

  • Given this information: Lead-time demand = 620 pounds Standard deviation of lead time demand = 50...

    Given this information: Lead-time demand = 620 pounds Standard deviation of lead time demand = 50 pounds (Assume normality.) Acceptable stockout risk during lead time = 4 percent Use Table. a. What amount of safety stock is appropriate? (Round your answer to the nearest whole number.)   Safety stock units b. When should this item be reordered? (Round your answer to the nearest whole number.)   ROP units c. What risk of stockout would result from a decision not to have any...

  • Problem 11-20 Daily demand for a product is 100 units, with a standard deviation or 15...

    Problem 11-20 Daily demand for a product is 100 units, with a standard deviation or 15 unts The review peniod is 20 days and the lead time is 10 days. At the time of review there are 50 units in stock If 98 percent service probability is desired, how many units should be ordered? (Use Excet's NORMSINVO function to find the correct critical value for the given a-level. Do not round intermediate calculations. Round "r value to 2 decimal places...

  • Given this information: Daily demand =50 units , standard deviation = 6 units and lead time...

    Given this information: Daily demand =50 units , standard deviation = 6 units and lead time = 4 days. What is the safety stock to attaib 5% rish of out stock during lesd time, asssuming that the denand in distributed normally?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT