Question

A project has the following cash flows : C0                           C1         &n

A project has the following cash flows :

C0                           C1                           C2

+6,750                   +4,500                   -18,000

  1. calculate the discount rate at which the NPV = 0.

  1. 15.5%
  2. 20.5%
  3. 33.3%
  4. 50.0%
0 0
Add a comment Improve this question Transcribed image text
Answer #1

А в YEAR 1 cash flows $6,750.00 $4,500.00 -$18,000.00 33.3% IRR(B3:35) IRR 9 IRR is the rate at which NPV = 0

Add a comment
Know the answer?
Add Answer to:
A project has the following cash flows : C0                           C1         &n
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40...

    A project has the following forecasted cash flows: Cash flows C0 C1 C2 C3 (100) 40 60 50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...

  • A project has the following forecasted cash flows: Cash flows C0         C1    C2     C3 (100)     40    ...

    A project has the following forecasted cash flows: Cash flows C0         C1    C2     C3 (100)     40     60   50 The estimated project beta is 1.5. The market return r m is 16%, and the risk-free rate r f is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). b. What are the certainty-equivalent cash flows in each year? c. What is the ratio of the certainty-equivalent cash flow to...

  • Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...

    Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 11% A −36,500 26,200 26,200 +$8,368 B −56,500 39,500 39,500 +11,145 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.) b. Which project does the IRR rule suggest is best? Project A Project B c. Which project is really best?

  • Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...

    Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.)

  • Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...

    Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.)

  • cash flows project C0 C1 C2 C3 C4 C5 A -1,000 1,000 0 0 0 0 B -2,000 1,000 1,000 1,000 0 0 C -3,000 1,...

    cash flows project C0 C1 C2 C3 C4 C5 A -1,000 1,000 0 0 0 0 B -2,000 1,000 1,000 1,000 0 0 C -3,000 1,000 1,000 0 1000 1,000 a) If the opportunity cost of capital is 11 percent, which projects have a positive NPV? b) Calculate the payback period for each project. c) Which project(s) would a firm using the payback rule accept if the cutoff period is three years?

  • You have the chance to participate in a project that produces the following cash flows: Cash...

    You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 –5,000 4,000 –11,000 a. The internal rate of return is 13%. If the opportunity cost of capital is 10%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your final answer to the nearest whole number.) NPV: ________

  • Consider the following projects: Cash Flows ($) Project C0 C1 D –11,200 22,400 E –21,200 37,100...

    Consider the following projects: Cash Flows ($) Project C0 C1 D –11,200 22,400 E –21,200 37,100 Assume that the projects are mutually exclusive and that the opportunity cost of capital is 12%. a. Calculate the profitability index for each project. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project Profitability Index D E b-1. Calculate the profitability-index using the incremental cash flows. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Profitability-index            ...

  • 1. You have the chance to participate in a project that produces the following cash flows:...

    1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV            $ __________. 2. Consider the following projects: Cash Flows...

  • Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the...

    Marielle Machinery Works forecasts the following cash flows on a project under consideration. It uses the internal rate of return rule to accept or reject projects. C0: -$10,900 C1: 0 C2: +$8,400 C3: +9,400 a. What is the project’s IRR?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT