Question

Compute the MIRR statistic for Project lif the appropriate cost of capital is 12 percent. (Do not round intermediate calculat

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We use the formula:
A=P(1+r/100)^n
where
A=future value
P=present value
r=rate of interest
n=time period.

Future value of inflows=5480*(1.12)^3+4330*(1.12)^2+1670*(1.12)+2150

=$17150.9574

MIRR=[Future value of inflows/Present value of outflows]^(1/time period)-1

=[17150.9574/11300]^(1/4)-1

=10.99%(Approx)

Hence since MIRR is less than cost of capital;project must be rejected.

Add a comment
Know the answer?
Add Answer to:
Compute the MIRR statistic for Project lif the appropriate cost of capital is 12 percent. (Do...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent....

    Compute the MIRR statistic for Project J if the appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$1,100 $380 $1,530 −$530 $330 −$110 Should the project be accepted or rejected? accepted rejected

  • Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent....

    Compute the MIRR static for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project I Time: Cash flow: $11,000 $5,330 $4,180 $1,520 $2,000 MIRR % Should the project be accepted or rejected? accepted rejected

  • Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do...

    Compute the IRR statistic for Project F. The appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project F Time: 0 1 2 3 4 Cash flow: −$10,300 $3,950 $4,780 $2,120 $2,750 Should the project be accepted or rejected? rejected accepted

  • Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent....

    Compute the PI statistic for Project Q if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)      Project Q   Time: 0 1 2 3 4   Cash flow –$11,600 $3,650 $4,480 $1,820 $2,450      PI       Should the project be accepted or rejected? Rejected Accepted

  • Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....

    Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amounts should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: Cash flow: 0 $8,000 1 $3,350 2 $4,180 3 $1,520 4 $300 NPV Should the project be accepted or rejected? O accepted O rejected

  • Compute the PI statistic for Project Zer the appropriate cost of capital is 6 percent (Do...

    Compute the PI statistic for Project Zer the appropriate cost of capital is 6 percent (Do not round intermediate calculations and round your final answer to 2 decimal places.) 23 Protect a Time: Cash flow: $1,800 $510 $640 $819 5160 5 260 PI Should the project be accepted or rejected? rejected accepted < Prey 5 of 7 !! Nept> to search ORHOM

  • Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12...

    Compute the discounted payback statistic for Project D if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is four years. (Do not round intermediate calculations and round your final answer to 2 decimal places. If the project does not pay back, then enter a "O" (zero).) Project D Time: Cash flow: 0 -$11,600 1 $3,410 $4,300 34 $1,640 $0 $1,120 Discounted payback period 0 years Should the project be accepted or rejected? accepted rejected...

  • Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent....

    Compute the PI statistic for Project Z if the appropriate cost of capital is 7 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Z Time: 0 1 2 3 4 5 Cash flow: −$2,300 $610 $740 $910 $560 $360 Should the project be accepted or rejected? accepted rejected

  • Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....

    Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: Cash flow: -$1,300 $470 $1,780 $580 $420 -$160 NPV Should the project be accepted or rejected? rejected accepted

  • Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do...

    Compute the IRR statistic for Project E. The appropriate cost of capital is 9 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project E Time: 0 1 2 3 4 5 Cash flow −$1,800 $670 $720 $680 $460 $260 IRR? Should the project be accepted or rejected?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT