1. The activities needed for a new project your company is undertaking are listed in the following table.
ACTIVITY IMMEDIATE
PREDECESSOR(S)
A ----
B ----
C A
D A, B
E B
F C, D, E
G D, E
H F
I F, G
J G
The activity times were determined for the project, and were as
below.
ACTIVITY ACTIVITY TIME (days)
A 11
B 9
C 7
D 12
E 8
F 9
G 10
H 6
I 7
J 9
a. Construct the project network diagram using Activity-on-Node
(AON) approach.
b. Determine the earliest start (ES) time, earliest finish (EF)
time, latest finish (LF) time, and latest
start (LS) time for all project activities.
c. Determine slack times for all project activities.
d. Identify the critical path(s) in the project network.
e. How long will it take to complete the entire project?
2. A project network is shown below, with three time estimates (Optimistic Time-Most Likely TimePessimistic Time (in weeks)) for each activity in the network. a. Compute the expected time for each activity in the project network. b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. c. Identify the critical path. What is the expected project completion time? d. Compute the variance of each activity on the critical path. e. Determine the project variance and project standard deviation. Use the PERT analysis results in (c) and (e) to answer questions (f), (g), (h), and (i) below: f. What is the probability that the project can be completed within 40 weeks of its start? g. What is the probability that the project can be completed within 31.5 weeks of its start? h. Determine the project deadline that gives this project a 96% chance of on-time completion. i. Determine the project deadline that gives this project a 13% chance of on-time completion. 0-0-0 10-16-19 11-14-17 4-8-12 9-15-18 0-0-0 Start A B H C End 1-4-10 E 5-10-18 G
1. 
2. Activity sequence seems to have some issuein the last line. Unable to understand how the activities are related to any other activities. kIndly re-post
1. The activities needed for a new project your company is undertaking are listed in the...
Mauritius Pharmaceuticals Ltd was undertaking a project for reviewing the packaging of its saline drips. The activities and the duration of each activity are shown in the table below. Activity Completion time (weeks) ACTIVITY Completion time (weeks) A 6 B 9 C 8 D 5 E 10 F 6 G 14 H 11 I 9 The immediate precedence relationships are: Activities D and E follow activity B. Activities A and D follow activity C. Activities G and...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 7 7 N/A B none 3 2 $500 C A 5 3 $1000 D A, B 6 4 $2000 E C, D 4 3 $1250 F D 3 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...
also needs daves latest start and latest finish:
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for e activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) C, E D, F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES...
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day А 6 B 3 с 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)
The table below defines the activities and the normal time duration for each activities within a small project. You can decrease (crash) the durations at an additional expense. Table 1 summarizes the time-cost information for the activities to complete the project. Table 1: The time-cost information for the activities Activity Normal Completion Time (weeks) Immediate Predecessor Crash Time (weeks) Normal cost for activities Crash cost for activities/week A 2 - 1 1200 400 B 3 - 1 1400 500 C...
Given is a CPM project network diagram as shown below.
Activity
Start
A
B
C
D
E
F
G
H
End
day
0
5
6
9
6
9
8
5
4
0
a) The Project Completion time = days.
b) The Earliest Start time, ES, of Activity G = days.
c) The Latest Finish time, LF, of Acitivity C = days..
d) The critical activities are = (ex. Fill in answer as: ABCD)
End Start
QUESTION 5 Given is a CPM project network diagram as shown below. А F Start E H End B D G Start A B C D E F G H End Activity day 0 6 زر 8 7 4 9 4 6 0 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in...
QUESTION 5 Given is a CPM project network diagram as shown below. A F Start H End B D G B Activity days Start 0 A 2 H D 3 E 4 F 2 G 3 6 8 End 0 2 a) The Project Completion time days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity C- days. d) The critical activities are (ex. Fill in answer as: ABCD)
please show answers clearly
12 points Save Answer QUESTION 5 Given is a CPM project network diagram as shown below. F А H End E Start G B D E F Activity day Start 0 A 5 B 6 Ula G 5 H 4 End 0 ON 9 8 days. a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days.. c) The Latest Finish time, LF, of Acitivity C = d) The critical...