Suppose the manager of a construction supply

Suppose the manager of a construction supply house determined from historical records that the lead time demand for sand averages 49 tons. In addition, suppose the manager determined that demand during lead time could be described by a normal distribution that has a mean of 49 tons and a standard deviation of 6 tons. If the manager is willing to accept a service risk of no more than 3 percent:

What value of z is appropriate?
How much safety stock should be held?
What reorder point should be used?


0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:


a) Lead time demand = 49

Standard deviation = 6

Acceptable stock-out risk = 3%

Hence, service level = 100 - 3% = 97%

1.88 (the value of z is given, by using the normal table, 97% fill-rate = 1.88 z-score)

b) Safety Stock is given by:

Safety Stock = Standard Deviation x Z

Therefore:

Safety Stock = 6 x 1.88

= 11.28 tons

c) ROP = Lead time demand + Safety Stock

Therefore:

ROP = 49 + 11.28

= 60.28 tons


answered by: Subrahmanyam golla
Add a comment
Know the answer?
Add Answer to:
Suppose the manager of a construction supply
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Rich Hotel distributes a mean of 1,000 bath towels per day to guests at the pool...

    Rich Hotel distributes a mean of 1,000 bath towels per day to guests at the pool and in their rooms. This demand is normally distributed with a standard deviation of 100 towels per day, based on occupancy. The laundry firm that has the linens contract requires a 2-day lead time. The hotel expects a 98% service level to satisfy high guest expectations. a. What is the safety stock needed to meet this service level? b. What is the ROP? c....

  • IM.61 Demand for Etched Impressions Wood products averages 40 units per day with a standard deviation...

    IM.61 Demand for Etched Impressions Wood products averages 40 units per day with a standard deviation of daily demand being 4. Lead time is 3 days. This IBC company strives for a 93% service level. What is the Z-value for the company's desired service level? (Display your answer to two decimal places.) What is the standard deviation of demand during the lead-time period? (Display your answer to two decimal places.) How many units of wood should Etched Impressions carry for...

  • Mr. Smith runs a world-food wholesale store in Nottingham. One of the items he orders from the Far East is Sriracha hot sauce. Every pack costs £10 and requires a six-month lead time for replenishment...

    Mr. Smith runs a world-food wholesale store in Nottingham. One of the items he orders from the Far East is Sriracha hot sauce. Every pack costs £10 and requires a six-month lead time for replenishment. Mr. Smith uses a 20% annual interest rate to compute holding costs. Estimated ordering cost is £50. During the six-month replenishment lead time, Mr. Smith estimates that he sells an average of 100 packs of sauce, but there is substantial variation from one six-month period...

  • Problem 2 A local service station is open 365 days per year. Sales of 10W40 premium...

    Problem 2 A local service station is open 365 days per year. Sales of 10W40 premium engine oil averages . Inventory holding cost are $0.50 per can per year. Ordering cost are $10 per order. Lead time to deliver the order is 2 weeks. Backorders are not practical as the customer will chose another service station if the desired number of oil cans is not available immediately. 20 cans per day a. Based on these data chose the appropriate inventory...

  • You are the inventory manager for a large retail store. You face uncertain demand from customers...

    You are the inventory manager for a large retail store. You face uncertain demand from customers and you buy products from an external sup- plier. Suppose you follow a “fixed-order quantity model”. What is the effect of increased lead time, decreased variability, increased ordering costs and decreased service level on the reorder point and on the order quantity? Write your answer in the table below by saying either Decreases (D), Increases (I), Stays the same (S), or, No answer -...

  • 1. Basic EOQ Question: The inventory manager of ABC, Ltd., wants to order flour for its...

    1. Basic EOQ Question: The inventory manager of ABC, Ltd., wants to order flour for its bakery in a cost effective manner. The bakery uses an average of 12,000 bags a year. Preparing an order and receiving a shipment of flour involves a cost of $40 per order. Annual carrying costs are $37.50 per bag. REQUIRED: A. Determine the economic order quanity. B. What is the average number of bags on hand? C How many orders will there be per...

  • Please kindly explain all the formulas and also how to find z value from service level...

    Please kindly explain all the formulas and also how to find z value from service level in steps Question 5: (5 Points) A local company uses an average of 650 items a day. The daily usage has a standard deviation of 23. The manager is willing to accept no more than a 1% chance of a stock out. The lead-time is 14 days. (Assuming the distribution of usage is normal). What is the re-order point? Question 6: (5 Points) A...

  • Based on available​ information, lead time demand for PC jump drives averages 5151 units​ (normally distributed),...

    Based on available​ information, lead time demand for PC jump drives averages 5151 units​ (normally distributed), with a standard deviation of 66 drives. Management wants aa 9090​% service level. Refer to the standard normal table LOADING... for​ z-values. ​a) What value of Z should be​ applied? ▼ 2.06 1.65 1.04 1.28 ​b) How many drives should be carried as safety​ stock? nothing units ​(round your response to the nearest whole​ number). ​c) What is the appropriate reorder​ point? nothing units...

  • Question 8 (2 points) You are the operations manager of a firm that uses the continuous...

    Question 8 (2 points) You are the operations manager of a firm that uses the continuous review inventory control system. Suppose the firm operates 252 days a year and has the following characteristics for its primary item: Demand - 25,000 units/year Ordering cost - $38/order Holding cost - $2/unit/year Lead time - 4 days Standard deviation in daily demand - 5 units Service level - 95% (z-1.65) What is the reorder point? (Please round your calculations to the nearest whole...

  • Based on available​ information, lead time demand for PC jump drives averages 53 units​ (normally distributed),...

    Based on available​ information, lead time demand for PC jump drives averages 53 units​ (normally distributed), with a standard deviation of 5 drives. Management wants a 95​% service level. Refer to the standard normal table for​ z-values. ​a) What value of Z should be​ applied? (1.04/1.28/2.06/1.65) ​b) How many drives should be carried as safety​ stock? __________ units ​(round your response to the nearest whole​ number). ​c) What is the appropriate reorder​ point? __________ units ​(round your response to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT