1. As the indirect labor are associated on the basis of activity based costing, and the product development cost is allocated on the basis of Number of engineering changes,
Activity rate for product development cost = Total product development Cost /Total Number of engineering changes
Total Number of engineering changes = 13 + 5 + 26 = 44
Therefore, Activity rate for product development cost = $770,800/44 = $17,518 per engineering change
Option a is the correct answer.
2. To calculate the overhead costs for producing 11,700 units, we will need to calculate overhead cost per hour for both the departments.
Overhead cost per hour for fabrication department = Total Overhead Cost / Total No of Direct labour hours
Therefore, Overhead cost per hour for fabrication department = $732,480 / 381,500 = $1.92 per hour
Overhead cost per unit of lamp in fabrication department = Overhead cost per hour * No of Hours per unit
Therefore, Overhead cost per unit of lamp in fabrication department = $1.92 * 4 = $7.68
Overhead cost per hour for assembly department = Total Overhead Cost / Total No of Direct labour hours
Therefore, Overhead cost per hour for assembly department = $559,504 / 74,800 = $7.48 per hour
Overhead cost per unit of lamp in assembly department = Overhead cost per hour * No of Hours per unit
Therefore, Overhead cost per unit of lamp in assembly department = $7.48 * 7 = $52.36
Hence, total overhead cost per unit of lamp = Overhead Cost in Fabrication department + Overhead Cost in Assembly department
Hence, total overhead cost per unit of lamp = $7.68 + $52.36 = $60.04 per unit.
Therefore, total factory overhead cost allocated to produce 11,700 units = 11,700 * $60.04 = $702,468
Hence, option d is the correct answer.
Calculator Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $374,100 Number of purchase orders Scheduling $208,600 Number of production orders Materials handling $478,000 Number of moves Product development $798,000 Number of engineering changes Production $1,461,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $355,800 Number of purchase orders Scheduling $219,600 Number of production orders Materials handling $486,900 Number of moves Product development $756,500 Number of engineering changes Production $1,495,300 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $345,800 Number of purchase orders Scheduling $231,000 Number of production orders Materials handling $490,100 Number of moves Product development $785,000 Number of engineering changes Production $1,537,000 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $352,000 Number of purchase orders Scheduling $213,200 Number of production orders Materials handling $454,500 Number of moves Product development $725,300 Number of engineering changes Production $1,401,500 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Activity Cost Activity Base $366,100 Number of purchase orders 244,900 Number of production orders 414,000 Number of moves 720,800 Number of engineering changes 1,584,700 Machine hours Production Number of Engineering Changes Number ol...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $329,900 Number of purchase orders Scheduling 223,700 Number of production orders Materials handling 426,300 Number of moves Product development 762,500 Number of engineering changes Production 1,434,200 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $316,400 Number of purchase orders Scheduling $205,600 Number of production orders Materials handling $499,400 Number of moves Product development $710,900 Number of engineering changes Production $1,565,900 Machine hours Number of Purchase Orders Number of...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Activity Cost Activity Base Procurement $384,800 Number of purchase orders Scheduling $227,600 Number of production orders Materials handling $472,700 Number of moves...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below. Procurement Scheduling Materials handling Product development Production Activity Cost Activity Base $347,800 Number of purchase orders 205,800 Number of production orders 491,900 Number of moves 779,400 Number of engineering changes 1,418,700 Machine hours Number of Engineering Machine Changes Hours...
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools The budgeted activity cost and activity base data by product are provided below Activity Cost Activity Base Number of purchase orders Number of production orders Number of moves Procurement333,500 Scheduling $245,900 Materials handling Product development Production ,513,200 $424,700 $743,700 Number of engineering changes Machine hours Number Number of Number Number of Number...