Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions.
A thorough answer will probably require 300 to 500 words for each question.
Feel free to use text bullets, tables, or graphics to summarize your points.
Questions
Q1: Make or Buy decision – Describe the make or buy decision in the case study and the pros and cons associated with each option. What would you have done? Why?
Q2: Risk – What were the key risks in this project? How were they mitigated? What additional actions would you have taken as project manager to mitigate these risks?
Q3: Earned Value – At the Alpha Review in November, how far along was the project? How could you have salami sliced the project differently to recognize revenue earlier? Feel free to include graphics or sketches with your answer to illustrate the situation as you see it.
Q4: Requirements Analysis – How would you evaluate the establishment of the requirements and schedule for the project? What problems can you see and how would you address these if you were the project manager?
Q5: Team Management – What problems emerged with the team? How would you have persuaded or coerced team members to complete their sections earlier? How would you control for quality?
Case Study
Online Training Module – Antiterrorism Awareness
Overview
It was 3:00 p.m. on Friday, May 5, 2017 when Mr. Hassan Adedayo hung up from his conversation with his long-time U.S. Department of Defense client. They were both relieved they had finally initiated this new project to provide antiterrorism training modules for DoD dependents. As Mr. Adedayo considered the many challenges ahead for the team, he reflected on the nine-month long struggle with this client to hammer out the scope and requirements and finally win approval for this project.
Although Mr. Adedayo had served as project manager for years, he
was preoccupied by the risks he had taken on by involving other
sections of his company in this project. They had earned their role
as a trusted advisor to this client by delivering high quality work
for their DoD client, Ms. Rebecca Allen, over the past ten years.
But the work that earned their reputation was performed by a team
of hand-picked, high-caliber professionals who reported directly to
Mr. Adedayo. Now, he would have to depend on other teams, with
their own leaders and managers. Did he do the right thing by
essentially “subcontracting to other groups within his own company,
Gargantuan Computing Services (GCS)?
Or, should he have turned to the small business community and hired
vendors who were “chomping at the bit” for this work, but over whom
he would presumably have less control? Did they work hard enough at
defining the requirements and the scope of the project? Or was that
a lurking risk that would explode on them later.
And finally, the risk that probably caused the most concern, was how he could ensure the professionals from the other parts of the company would share his team’s commitment to quality and deliver on schedule. Then he remembered that the team owed this project to Collin Eng’s conversation with the client, six months prior.
Initial Conversation
Mr. Collin Eng had accompanied the Safe Schools team on a
regular client visit in November 2016.
Mr. Eng explained to the client that his team of web developers
could solve her challenge by building a web site to accompany the
new online training module. “That would keep it evergreen”
explained Eng.
Ms. Allen liked that idea and adopted the word “evergreen.” She had a very bad previous experience when her office hired a least price, technically acceptable contractor to develop the original training video. Technology had moved on since then, and now they needed a module that would be interactive and present well on projectors around the world. Their 83,000 students were located on military bases in Japan, Korea, Germany, Belgium, Italy, Spain, Turkey, Bahrain, and various other parts of the world, including the Southeastern United States.
Mr. Adedayo had explained that because Gargantuan Computing Services served several similar government clients, they could tap into the company’s Multi-Media Center of Excellence and access experts who wrote scripts and developed videos for other federal agencies. The Safe Schools team would provide the subject matter expertise, but GCS people who produced professional quality films all the time would coordinate the actors and produce the videos for the course module.
When Ms. Allen visited the GCS studio and facilities in Cherry Hill, New Jersey, she came away impressed. She started working on the procurement paperwork to issue a contract modification on the existing GCS fixed price contract.
Requirements
The needs assessment with stakeholders had been underway for years. Counselors, principals and educators, from elementary schools, middle schools, and high schools had suggested they needed an updated training module for years. “Students are ignoring vital security messages, because the actors’ clothes had gone out of fashion,” remarked one counselor in Germany.
The team also needed to ensure the training was delivered in an age-appropriate manner to students of different maturity levels – from elementary students – 5th graders and 6th graders, up through seniors in high school. Finally, the Statement of Work that resulted from a months long requirements definition process wound up stating: provide instruction on what to do if kidnapped by terrorists, but do not make it scary.
Intra-Company Coordination
Mr. Adedayo deeply respected his supervisor, a GCS director named Darius Inglimo, who explained to him the advantage of working with teams from within the same company. “The company recognizes all the revenue, plus we own all the materials developed and learn from the process,” Inglimo explained. “If you hired a small business from outside the company, they would own the intellectual property and could compete with us for future business with this client.”
“Yes,” agreed Adedayo, “but my contract with this client is fixed-priced, and the Intra-Company agreements are time and materials. If our colleagues go over budget, we cannot ask the client to pay more money. That is not their problem.”
Mr. Inglimo acknowledged the risk and suggested they consult his business analyst, Ms. Palistha Khan. Ms. Khan had an answer: Management Reserve and Contingency Reserve.
“We have to create a budget that allows for some overrun. We will build that into the project within the narrow variances tolerated by the contract and the relevant regulations,” she answered. She showed Adedayo how to do that in his rough spreadsheet that he was using to plan schedule and budget. “And although you’re the project manager, and it’s not my area of expertise, I suggest you do the same thing, with the schedule,” she added.
They collected cost estimates from both of the intra-company teams: the web developers and the Multi-Media Center of Excellence. Mr. Adedayo had a tough time contacting the person identified as the project manager for the Web developers, but he finally visited her in person and found she worked three floors above him on the sixth floor of his own building. Turned out there was a perfectly logical explanation for the delay – Ms. Amina Talbert was in love! And she shared that she was preparing to fly to Guatemala to meet her betrothed and formalize their new life together.
Three months into the project
By August of 2017, Mr. Adedayo was glad that they had built the extra time into the schedule and included additional funding in the budget. But the project did not seem to be making progress, and time was slipping away.
They had begun by trading scripts and ideas with the Multi-Media Center of Excellence. The editor from the Safe Schools content team had to suggest basic features such as a “narrative arc” and some conflict between characters to keep the video interesting. They were beginning to wonder when the center would reveal it’s “excellence,” when the center announced they had hired child actors from the New York and New Jersey area and would commence filming in their studio using “B-roll” footage as a backdrop.
Meanwhile, Mr. Adedayo could not convince the website developers to do anything. They were busy on other projects and kept “slow-rolling” him each time he asked. Mr. Adedayo could not elicit a reply to his emails from Ms. Talbert and finally learned from Mr. Eng that she had left the company and moved to Guatemala. He was astounded. This was a multimillion dollar group within Gargantuan Computer Services, but it seemed like there was no adult supervision.
Only much later would Mr. Adedayo learn that the group felt that
they did all the work to help market the client and then only
received a sliver of the project funding. They expected to earn 33%
of the project funding because they felt they were contributing 1/3
of the work. In reality, the budget allocation called for 12% of
project funding to go to that group because the majority of the
work was performed by two technical experts. Meanwhile at the
multi-media center of excellence more than
20 people were performing several tasks such as creating scripts,
directing, acting, managing actors, and using green screen
technology to make it look like the child actors were in Italy,
Japan, and Turkey.
Turned out the delay with the web developers did not significantly delay the project. In October 2017, when they finally received the graphic artwork that would determine the branding from the multi-media center, the web developers surged and produced an excellent, interactive website with downloadable tools and interactive features – beyond what the client expected. But they also charged hourly rates and worked right past the funding ceiling established in the intra-company work order. According to the terms of the work order, Mr. Adedayo’s group had to reimburse that team at the agreed upon rates, and they just kept billing. Now that they were finally working and turned “on,” there seemed to be no way to turn them “off.”
Mr. Adedayo occasionally had to visit them in person and participate in meetings to keep them interested in the project because the client liked what they were delivering and requested changes that were clearly within scope, enhanced the offering, but required more time. Unfortunately, the web development experts were once again becoming more deeply involved in other projects.
Alpha Review
Finally, in November 2017, Mr. Muhammad Sarawary, the leader of the Multi-Media Center of Excellence road the Excella Express train down from Philadelphia and joined Mr. Adedayo for a visit to their client. Ms. Allen and her colleagues had been coached since the start of the project that if they had concerns, the earlier they mentioned them, the easier it would be to incorporate changes into the modules.
Ms. Allen and her team of government security experts had understood and complied with that ground rule. For example, government subject matter experts had suggested very specific wording for sections of the script so that it would comply with government regulations and doctrine.
As improbable as it sounded, the team managed to make government criteria for Force Protection Condition (FPCON) Bravo, FPCON Charlie, and FPCON Delta tumble out of teenagers’ mouths in a convincing manner. The Multi-Media Center almost succeeded in creating interesting videos using a mix of quiz show games, skits, and b-roll footage from overseas scenes.
Now, during the technical review of the final product known as the Alpha Review, Ms. Allen did notice some substantial flaws that needed to be addressed. Mr. Sarwary said just the wrong thing. Instead of sounding deferential and diplomatically explaining what could and could not be done, he was just a bit too abrupt.
Mr. Adedayo missed it during the meeting, but his loyal editor caught a micro expression cross the client’s face and mentioned it to Mr. Adedayo the following day. Mr. Adedayo called the client the immediately and managed to limit damage to the relationship. But he fixed the communication flaw by banning Mr. Sarwary from future client meetings and mandating that he, Mr. Adedayo, would present the deliverables. Mr. Adedayo also authorized expenditure of additional contingency reserves so the additional work could be completed. But the client relationship damage was done and Mr. Sarwary was not invited to future meetings.
Meanwhile, the clock kept ticking. A project that was supposed to be completed by January 2018 began spilling into February 2018. Mr. Sarwary left the company! The entire Multi-Media Center of Excellence was disbanded.
Mr. Adedayo was forced to work with loyal employees who continued to help finish the project simply out of loyalty to GCS and because they liked the cause – teaching students how to protect themselves and what to do in a crisis. At one point, to make the delivery of the modules happen on schedule, Mr. Adedayo drove North from Virginia while the last responsive member of the Multi-Media Center drove South from New Jersey to hand off the modules in Delaware. It worked and kept the project on schedule.
Bravo Review
By Bravo Review, Mr. Adedayo and his GCS team were holding their breath as Ms. Allen and her colleagues reviewed the final version of the modules. A few more minor requests to the Web site were not only doable, they were great suggestions, and enhanced the usability of the training and contributed to deeper involvement among students.
Observations
Mr. Inglimo called Mr. Adedayo and told him to gather his team. As part of GCS’s commitment to quality standards specified in the International Organization for Standardization (ISO) 9000 quality certification series, GCS teams conducted thorough lessons learned reviews regarding every project.
Director Inglimo also noted that although the project was profitable overall, and had a respectable ROI, the funding had been delayed so long due to the Fixed Priced arrangement, that interest costs had forced the business analyst to report the project “in the red” for months, meaning it showed negative profitability each time it was reviewed internally by company leaders. In the future, they would have to use Earned Value Management and “salami slice” projects into phases so they could receive some payment from the client as milestones were achieved at the end of each of the phases. That was the approach needed to make projects “pay as they go” on fixed priced contracts.
Mr. Adedayo mapped out the agenda for the lessons learned review and considered what the team had learned.
Would they have been better off hiring outside vendors?
They did eventually deliver the project, and the client requested future business with the team, but was the risk justified?
Despite hammering out requirements with the client for months, in the end, it seemed that they needed to keep making adjustments until clients were personally satisfied, before the clients would provide a final written approval to authorize payment.
Finally, how could one predict that one project manager would leave for Guatemala, and another would leave the company and the company would disband the entire Multi-Media Center of Excellence team. What would they do if the client needed future projects that required similar capabilities?
Answer 2) Project Risk is one of those exciting topics that everyone has an opinion about. Risk management is about maximizing your chances of project success by identifying risks early on and planning how to manage them. The following examples of risks will get you started down the path of risk identification.
Executive Support
1. Executives fail to support project
The project team may lack the authority to achieve project
objectives. In such cases, executive management support is
fundamental to project success. When this doesn't materialize the
project fails.
2. Executives become disengaged with project
Executive management disregards project communications and
meetings.
3. Conflict between executive stakeholders disrupts
project
Members of executive management are combative to the project or
there is a disagreement over project issues at the executive
level.
4. Executive turnover disrupts project
A key executive leaves the company, the resulting disruption
becomes a project issue.
Scope
5. Scope is ill defined
The general risk of an error or omission in scope definition.
6. Scope creep inflates scope
Uncontrolled changes and continuous growth of scope.
7. Gold plating inflates scope
The project team add their own product features that aren't in
requirements or change requests.
8. Estimates are inaccurate
Inaccurate estimates is a common project risk.
9. Dependencies are inaccurate
Dependencies dramatically impact the project schedule and
costs.
10. Activities are missing from scope
Required activities are missing from scope definition.
Cost Management
11. Cost forecasts are inaccurate
Inaccurate cost estimates and forecasts.
12. Exchange rate variability
When costs are incurred in foreign currencies exchange rates can
have a dramatic impact.
Change Management
13. Change management overload
A large number of change requests dramatically raises the
complexity of the project and distracts key resources.
14. Stakeholder conflict over proposed
changes
Change requests may be the source of stakeholder conflict.
15. Perceptions that a project failed because of
changes
Large numbers of high priority change requests may lead to the
perception that the project has failed. When the schedule and
budget are continually extended — stakeholders may feel the project
missed its original targets.
16. Lack of a change management system
Identify any lack of critical tools as a risk.
17. Lack of a change management process
Change management at the organizational or departmental level is
critical to project success. Otherwise, the project will have
limited visibility into changes that impact the project.
18. Lack of a change control board
A change control board is essential to managing change for large
projects.
19. Inaccurate change priorities
When non-essential changes are prioritized impacting critical
schedules.
20. Low quality of change requests
Change requests that are low quality (e.g. ambiguous).
21. Change request conflicts with
requirements
Change requests that make no sense in the context of the
requirements.
Stakeholders
22. Stakeholders become disengaged
When stakeholders ignore project communications.
23. Stakeholders have inaccurate
expectations
Stakeholders develop inaccurate expectations (believe that the
project will achieve something not in the requirements, plan,
etc).
24. Stakeholder turnover
Stakeholder turnover can lead to project disruptions.
25. Stakeholders fail to support project
When stakeholders have a negative attitude towards the project and
wish to see it fail.
26. Stakeholder conflict
Disagreement between stakeholders over project issues.
27. Process inputs are low quality
Inputs from stakeholders that are low quality (e.g. business case,
requirements, change requests).
Procurement
28. No response to RFP
The risk that there is limited response to an RFP. This occurs when
the RFP terms are unacceptable to vendors or if your firm has a bad
reputation amongst vendors.
29. Low quality responses to RFP
Half hearted responses to your RFP that are unusable.
30. Failure to negotiation a reasonable price for
contracts
Inability to negotiate a reasonable price for contracts. This
occurs when the requirements or contract terms make vendors
nervous.
Together these 5 risk management process steps combine to deliver a simple and effective risk management process.
Answer 4) Project requirements are conditions or tasks that must be completed to ensure the success or completion of the project. They provide a clear picture of the work that needs to be done. They're meant to align the project's resources with the objectives of the organization.
Typically, requirements gathering (or “requirements elicitation”) refers specifically to the practice of defining software requirements, but really every project has requirements, from a new customer support platform to a remodeled kitchen. At its core, this is the process of understanding what you’re supposed to be building, and why you’re building it.
This process often involves a set of activities including:
Requirements elicitation: getting business requirements from relevant stakeholders to understand user needs;
Requirements documentation: codifying that information in the form of user stories and feature specifications so they are accessible to the project team;
Requirements understanding: making sure everyone’s on the same page about what the heck you’re all trying to build.
Depending on your project methodology, you may do this step at the beginning during a Discovery phase, you may do it during the project within each sprint or build cycle, or you may skip it altogether and hope for the best. That last option is a simple way to sabotage your project and guarantee a lot of late nights and awkward status meetings.
Below is a five-step guide to conducting your own business requirements analysis.
1. Identify Key Stakeholders
Identify the key people who will be affected by the project. Start by clarifying exactly who the project's sponsor is. This may be an internal or external client. Either way, it is essential that you know who has the final say on what will be included in the project's scope, and what won't.
Then, identify who will use the solution, product, or service. These are your end-users. Your project is intended to meet their needs, so you must consider their inputs.
. 2) Capture Stakeholder Requirements
Ask each of these key stakeholders, or groups of stakeholders, for their requirements from the new product or service. What do they want and expect from this project?
You can use several methods to understand and capture these requirements. Here, we give you four techniques:
Technique 1: Using stakeholder interviews
Talk with each stakeholder or end-user individually. This allows you to understand each person's specific views and needs.
Technique 2: Using joint interviews or focus groups
Conduct group workshops. This helps you understand how information flows between different divisions or departments, and ensure that hand-overs will be managed smoothly
3) Categorize Requirements - To make analysis easier, consider grouping the requirements into these four categories:Functional Requirements – These define how a product/service/solution should function from the end-user's perspective. They describe the features and functions with which the end-user will interact directly.Operational Requirements – These define operations that must be carried out in the background to keep the product or process functioning over a period of time.Technical Requirements – These define the technical issues that must be considered to successfully implement the process or create the product.
4. Interpret and Record Requirements
Once you have gathered and categorized all of the requirements, determine which requirements are achievable, and how the system or product can deliver them.
To interpret the requirements, do the following:
Once everything is analyzed, present your key results and a detailed report of the business needs. This should be a written document.
Circulate this document among the key stakeholders, end-users, and development teams, with a realistic deadline for feedback. This can help resolve any remaining stakeholder conflicts, and can form part of a "contract" or agreement between you and the stakeholders.
5. Sign Off
Finally, make sure you get the signed agreement of key stakeholders, or representatives of key stakeholder groups, saying that the requirements as presented precisely reflect their needs. This formal commitment will play an important part in ensuring that the project does not suffer from scope creep later on.
Select two of the discussion questions and analyze the case study using project management principles. Apply...
select one theory of ethics to apply to the case study ("Evaluating a Case Study: Developing a Practical Ethical Viewpoint"). Based on your selected ethical theory, what are the main ethical concerns? Utilitarianism Deontology Ethical Intuitionism Virtue Ethics Ethical Non-Cognitivism Ethical Contractarianism Describe how each ethical theory might approach this situation. Which one is most consonant to your own worldview, and why? Case Study: You are on the executive committee of the XYZ organization of health care professionals. Each year...
Apollo Tech Solutions Case Study Part Two The deadline for submitting proposals was 8 April 2012 and Arnott was looking forward to receiving three submissions from the consulting firms. He cleared his diary and arranged the meetings for the following two weeks. Ferguson & Co and EuroComms Solutions came back immediately with dates to present their initial proposals to him; however, ITL seemed very reluctant to agree to time. Finally, Arnott was contacted by the Senior Partner in their Strategy...
Scenario: You are in charge of allocating a $10,000 bonus to a team that has recently met an important deadline. The team was in charge of designing a web-based product for a client. The project lasted a year. There were five people in the team. Instructions: Your job is to determine each person’s share from the bonus. Team Members: • Devin: Project manager. Devin was instrumental in securing the client, coordinating everyone’s effort, and managing relationships with the client. He...
Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong Police (HKP) was responsible for the public safety and internal security of Hong Kong. She came under the umbrella of the Security Bureau of the Government of Hong Kong. It had more than 34,000 employees, of these, over 26,000 were disciplinary staff. This was the largest department within the hierarchy of the Government of Hong Kong. The organization structure of HKP was rather complicated....
CASE STUDY – THE RELUCTANT PROJECT TEAM JJ Okocha started a new job 6 months ago. His new position was project manager. At first, he had starts in his eyes about becoming the best project manager that his company had ever seen. Now he is not sure if project management is worth the effort. He made an appointment to see Phil Davies the director of project management. JJ Okocha: “Phil I am a little unhappy with the way things are...
CASE STUDY – THE RELUCTANT PROJECT TEAM JJ Okocha started a new job 6 months ago. His new position was project manager. At first, he had starts in his eyes about becoming the best project manager that his company had ever seen. Now he is not sure if project management is worth the effort. He made an appointment to see Phil Davies the director of project management. JJ Okocha: “Phil I am a little unhappy with the way things are...
answer discussion quesyions and case study questions
DISCUSSION QUESTIONS 1. Discuss what is meant by the term “power." 2. Explain the difference between potential and kinetic power 3. Describe the different sources of power. 4. Explain what is meant by a manager's power base and the way ers develop it. 5. Describe organizational politics and the resulting political behavi 6. Discuss what is meant by upward influence and the various influ tactics categories associated with it. od the ways manag....
Read the following case study and answer the question that follows. Article: A TALE OF TWO PROJECTS [20 MARKS] A business tale of what it takes to turn around troubled projects. The year is 2015 and times are good. The business environment is vibrant and the econo my is strong. Large businesses are committing large amounts of capital and resources to implement new strategies, establish new capabilities, and open new markets. It was no different at PintCo, where Jack works...
Read the following case study and answer the question that follows. Article: A TALE OF TWO PROJECTS [20 MARKS] A business tale of what it takes to turn around troubled projects. The year is 2015 and times are good. The business environment is vibrant and the econo my is strong. Large businesses are committing large amounts of capital and resources to implement new strategies, establish new capabilities, and open new markets. It was no different at PintCo, where Jack works...
How do the four principles apply to this case? Make sure to address each principle individually. The Case of Mr. Perry and his Pacemaker Mr. Perry (not his real name) was 83 years old and had several medical problems. He had spent the past several months in and out of hospitals and rehab. Prior to that, he lived independently in a small Midwestern town. Widowed many years ago, he subsequently enjoyed the company of a lovely lady friend who lived...