Case Study 12: Hong Kong Police’s Project Management B
Chuah
Background
In the 1990’s, Hong Kong Police (HKP) was responsible for the
public safety and internal security of Hong Kong. She came under
the umbrella of the Security Bureau of the Government of Hong Kong.
It had more than 34,000 employees, of these, over 26,000 were
disciplinary staff. This was the largest department within the
hierarchy of the Government of Hong Kong.
The organization structure of HKP was rather complicated. It
consisted of functional units as well as regional hierarchical
structure. Besides, matrix structure also existed in some units,
especially within the regional front line offices.
In order to provide fast response, security and confidentiality to
the front line operations, a group of Telecommunications Engineers
and Technicians were recruited specifically to meet these
requirements. These Telecommunications Engineers and Technicians
were grouped under the Information Systems Wing of HKP, which was
under the command of Assistant Police Commissioner.
All the communications equipment for the operations of HKP were the
responsibility of the Telecommunications Engineers of the
Information Systems Wing. These Telecommunications Engineers are
divided into three Divisions; namely Systems Engineering and
Research Division, Project Management Division and Maintenance
Division. The acquisition of new communications facilities followed
a project life cycle approach and project management process.
Unlike in most other organizations, the project manager would often
be changed from one project stage to another.
A Telecommunications Engineer of the Systems Engineering and
Research Division would be the project manager during the project
formation stage. He would liaise with user group(s) to define the
operational and functional requirements, carry out product and
system research in the market, seek project funding from
government, and produce a design report including appropriate
technical specifications and other essential documents, such as
operational and functional requirements, for subsequent tendering
to be managed by the Project Management Division.
After the completion of the design report, normally another
Telecommunications Engineer of the Project Management Division
would be appointed to take over the role of managing the project
implementation. His duties were to first prepare the tender
document which included appropriate contract documents and
schedules together with the system’s technical specifications. He
would then liaise with the Government Supplies Department about the
tendering exercise. Following that, he would undertake the
selection of appropriate contractor and supervise the subsequent
project implementation. After the implementation work, the
completed system would be under the care of the Telecommunications
Engineers in the Maintenance Division for the rest of the system
operational life.
The Radio Communication System Project
This project took place in the early 1990’s before the 1997
changeover of sovereignty. In order to fight against terrorist and
organized crime, the Special Duties Unit (SDU) was established in
the HKP. Though all the team members of the SDU were volunteers
from HKP, they must undergo extensive physical tests before
becoming its official member.
To meet the great challenges of the operation, these SDU members
have to go through very demanding physical and technical training
programmes. After several large scale exercises, it was decided
that in order to improve and ensure effective operations of SDU, a
reliable radio communication system was needed. This
state-of-the-art radio communication system must be able to support
regular voice communication and also short bursts of data
transmission for critical front-line operations.
Project Design
For this radio communication system project, a Telecommunications
Engineer of the Systems Engineering and Research Division, was made
the Design Engineer. He had the project manager's role during the
project formation stage and was responsible for the system’s
functional requirement specification and design; product and market
research; costing and funding application. With the strong support
of the end user, i.e. the SDU, the government approved the required
funding smoothly. The SDU wished to have the system ready for
operations as soon as possible and pushed the design team very hard
to finalize the system specifications.
To meet this tight schedule, the Design Engineer carried out a
short market survey and product research and justified, based
mainly on his own expertise and experience, decided that the needed
radio communication system could be built from off-the-shelf
equipment with some minor modifications by the contractor. The
Design Engineer completed the design report, which contained the
operational requirements, functional and the technical
specifications, for the Project Management Division to follow
up.
Project Implementation
The leading role for this phase of the project was handed over to a
Telecommunications Engineer of the Project Management Division. He
was the Project Engineer in charge of the project implementation,
being responsible for preparing the tender document; evaluating the
tender returns and recommending the selected contractor;
supervising the radio communication system installation and
commissioning work; and the overall contract management of the
project.
After this Project Engineer had reviewed the design report received
from the Design Engineer at the project hand-over, he felt that the
design was very primitive and might not meet the full operational
and functional requirements of SDU. He had also great concerns
about many of the assumptions made in the system design and
stipulated requirements which might lead to no tender return. After
some discussion and exchange of ideas with the Design Engineer, the
Project Engineer's concerns remained as they could not resolve many
of their differences. The Project Engineer basically wished to have
all the technical constraints explicitly detailed in the technical
specifications, whilst the Design Engineer wanted to let the
tenderers more room to consider. Moreover, the attitude of the
Design Engineer was that his duties had been discharged and the
Project Engineer who was now the project manager, should have the
responsibility and power to make changes as he saw fit.
However, the Project Engineer decided not to change anything,
simply added the necessary contractual conditions and schedules to
the tender document. He made such decision because the project had
a committed completion date and time was running out. Besides, he
did not want to make any changes in the system design without the
Design Engineer's agreement and endorsement. The tender process
followed the Government’s procurement regulations. The tender was
finally awarded to a lowest tenderer, who was not in the original
list of potential contractors of the Design Engineer. Though the
Project Engineer had some reservation about awarding the contract
to this tenderer, he could not substantiate his objection because
this tenderer’s submission had apparently complied with all the
requirements stipulated in the tender.
Project Acceptance
The delivery of the equipment, installation and commissioning of
the radio communication system went smoothly. The system was put
into service on schedule and was in its warranty period. To protect
the Government’s interest, it was a normal practice in the
procurement of a system over five million dollars, ten per cent of
the contract sum (termed the retention money), would only be
released to the contractor after the satisfactory completion of the
warranty period. This period was normally one year after the system
was put into service.
During the system warranty period, many missed or false burst of
data transmission problems surfaced intermittently. These problems
were recorded and the contractor was asked to investigate and solve
them. The SDU was very disappointed with the reliability as well as
unavailability of the system because the system had to be taken to
the contractor's factory for fault diagnosis and rectification much
of the time. At the expiration of the warranty period, the SDU
refused to accept the radio communications system.
Though the intermittent fault was not rectified during the system
warranty period, the contractor still asked the Government to pay
the retention money. The Project Engineer refused to endorse the
payment request. Instead, the Project Engineer demanded the
extension of the system warranty period for another year as it did
not satisfy the contractual specifications. Shortly, the contractor
sent in another bill claiming for an extra amount of money to cover
the effort of rectifying the additional “unreasonable” faults. The
contractor claimed that the equipment was deployed in an
unfavourable environment and condition, which was not specified in
the tender document.
Project Termination
The argument about the contract terms went on for almost a year
among the contractor, the Government Supplies Department, the
Department of Justice and the HKP. Meantime, there was still no
proper solution to the system problem.
At about the same time, a special Anti-Smuggling Task Force was
established to combat the increase in smuggling activities through
the waters between Shenzhen and Hong Kong. In order to support the
task force’s operations effectively, a radio communication system
was required urgently. The task force’s requirement was mainly
voice radio transmission system and the operational environment of
this task force was more suited to the installed radio
communication system than that of the SDU. With the senior
management's approval, the SDU’s radio communication system was
thus redeployed for this Anti-Smuggling Task Force.
An agreement was finally reached among the contractor, Government
Supplies Department and HKP that the contractor had completed its
system warranty obligation and retention money was released.
Post-project notes
Another project was subsequently initiated to re-design a radio
communication system to meet the operational and functional
requirements of the SDU. The follow-up study revealed that it was
very difficult to use a single radio communication system to
support both voice and short burst data transmission effectively.
In view of the number of equipment that the front line officers
needed to carry, the SDU agreed to amend its operational
requirements to use encrypted voice transmission instead of short
burst data transmission in their operations, so as to relax the
technical constraints. Another radio communication system that met
the SDU’s operational needs was later successfully installed.
Answer the following questions based on the given
assumptions -
Assume that you are an experienced project engineer recently
recruited into the HKP’s Project Management Division. The senior
management of HKP is not happy about the way the radio
communication system project has been handled and as part of the
post-project appraisal, has asked you to review this case
thoroughly.
You are asked to:
c. Identify the problems encountered in this radio communication
project.
d. Explain the root causes of these problems.
c. Recommend ways of improvement.
Key problems identified in article :
Root causes :
Recommended Solution :
Case Study 12: Hong Kong Police’s Project Management B Chuah Background In the 1990’s, Hong Kong...
20. The docum ent named "Available Information" is part of the: a. Instruction to bidders b. Contract documents c. Specifications d. Procurement requirements e. All of the above 21. Contractual clauses in the conditions of the contract: a. Have priority over Division 01 b. Are superseded by Division 01 Are expanded upon by the provisions of Division 01 d. Are independent and Division 01 provisions have no effect 22. Under the AIA A201, who provides property insurance covering the a....
Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question. Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...
Continual Technology Training (CTT) is a technology learning centre founded by Dr. Alan Hong. CTT provides short technical courses catered to adults working in Singapore’s science and technology sectors. The courses conducted, such as Artificial Intelligence and Machine Learning, equip learners with the latest technical knowledge that they can apply in their work. CTT started three years ago at Happy World Plaza with one classroom and Dr. Hong was the only trainer. Recently, with the promotion of life-long learning by...
Project Background In a recent regular quarterly meeting in June, several members of the Board of Directors of Crystal Fashion Group (CFG) have a big concern on the future business position and outlook of the company in view of the long-term trade dispute between USA and China. Also, the rising costs of manufacturing in China are eroding off the profit margin and undercut CFG’s competitiveness in the market. Seeing that quite a number of fellow fashion/ garment manufacturers have already...
Case Study JONES AND SHEPHARD ACCOUNTANTS, INC. By 1990, Jones and Shephard Accountants, Inc. (J&S) was a midsized company and ranked 38th in size by the American Association of Accountants. In order to compete with the larger firms, J&S formed an Information Services Division designed primarily for studies and analyses. By 1995, the Information Services Division (ISD) had fifteen employees. In 1997, the ISD purchased three largecomputers. With this increased capacity, J&S expanded its services to help satisfy the needs...
KM THE BOYGUES TELECOM WAY The case underneath presents the approach of the Knowledge Management adopted by a well-known French company. The Bouygues Telecom way With more than six million customers and a network covering 98 per cent of France, Bouygues Telecom, created in 1994 as a subsidiary of the Bouygues global industrial group (turnover : 19 billion euros in 2000), has established itself as one of the most dynamic and innovative players in the French mobile telephony market. But...
its
a case study on the course strategic management...i need
answers...its urgent
No SIM 12:22 PM @ 82% 7 < BTECH ASSIGNMENT JANUARY 2 ASSIGNMENT DATE OF SUBMISSION: 07/02/2020 QUESTION 1 a) CASE STUDY 1 Joe Smith is the stores and purchasing manager for the Cocoa Research Institute Hotel and Golfing Complex located at one of Ghana's research centres at Tafo in the Eastern Region. Joe receives purchase requisitions from other departmental heads in the organization. When he took the...
How can we assess whether a project is a success or a
failure?
This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...
Hi, Kindly assist with my project management assignment below using the attached case study Question 1 Update the project charter for the remainder of the project in response to Adams’ memo (lines 241 through 246). Question 2 Prepare a plan for the remainder of the project in response to Adams’ memo (lines 241 through 246). Your answers to the above will be assessed in terms of the level of communication displayed, the insights and inferences drawn, and your ability to...
QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...