Question 2: You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic Cable (KRFOC) project. You are preparing your cost estimate for the project and your Project Engineer (PE) tells you it will take 425 hours to complete the design effort. Your Finance Manager (FM) tells you that engineering labor is $125 an hour. Fortunately for you, unfortunately for them, you are a graduate of yur university, specializing in project management in general and advanced project management techniques in particular.
Upon questioning, your PE admits that the 425 hours is just a guess, that under the best circumstances, meaning you quit bugging him with inane questions, it may take only 375 hours. However, it could take as long as 700 hours (if you do not leave him alone to do his job). He stands by his estimate that it will normally take 425 hours. Hint: this is a triangular distribution.
Thinking back to your school days, you wonder if all engineers cost $125 per hour. Upon questioning, your FM admits that this is an average cost, that some are higher, some are lower. You direct him to give you the distribution of all engineer labor rates. With a lot of help, he replies that the labor rate is normally distributed with a mean of $125 and a standard deviation (he is still not sure what that is) of $25.
Please answer the following two questions:
Solution :
The two major factors for estimate of labour charges are working hours and wage rate.In addition to this Fringe benefits/Insurance & Taxes, wage premiums are also considered.
As per manhours ,it belongs to triangular distribution hence calculating (P + O + ML ) / 3, we get
Manhours = (375+425+700)/3 = 500hrs
The cost is given as mean value of 125$/hr.Hence,
The cost estimate considering 5% of additional value from actual as follows :
Cost = Manhours x wage rate x additional percentage
= (500x125)*1.05
= 65,625$
Note : The additional cost due to wage benefits/Tax/Levis etc can be considered in addition as per govt regulations.
Question 2: You have just been assigned as Project Manager (PM) to the Kuraiz-Reconda Fiber Optic...
Question No. 2: a) Imagine you have been hired by Enormous Oil, Inc (EOI). They ask you to evaluate a project. After getting estimates from the engineers you determine that the project will have an initial capital cost of $10 million to implement and yield 100,000 barrels of oil per year. Based on this information ALONE do you have enough information to recommend investing in the project. If not, please describe the information that you lack regarding the viability of...
You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational and leadership skills....
Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the Green Computing Research Project. The company’s CIO, Ben, is the project sponsor, and Ito is the program manager for the larger Environmental Technologies Program that this project is part of. Now you need to put together your project team and get to work on this high-visibility project. You will work with Ben to handpick your team. Ben had already worked with the HR department...
Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000 ft of pipe was installed....
You have been asked to price out a project for a customer based on a firm-fixed price. Table below shows the numbers that you arrived at in determining the bid amount for the project that should be submitted. As you know, before a bid is submitted to a potential customer, the bid must be reviewed by a committee of senior managers that can question the validity of the numbers as well as look for “hidden” costs that may have been...
You have just been assigned to a new manager who believes you have exceptional budgeting skills. Since you began your job last summer, you have been showing management your latest spreadsheets and how you use your new-found knowledge of Managerial Accounting to make sound business decisions. Your new manager is responsible for the nationwide distribution of designer shaving kit sets (SKS) and, through multiple franchise agreements, sales have grown very rapidly, and the timing is right for you to join...
Assume the following: You are a contractor and have just been awarded a Greenfield Project. A budget has been established to install 20,000ft of pipe at an estimated 15,000 man hours and an estimated billable cost of $700,000. The original schedule planned for 4,000ft of pipe to be installed per day by a 300-man crew working a 10-hour shift (anticipated). The job was scheduled to start in Monday and finish on Friday. On Monday 2,000ft of pipe was installed. On...
Human Resources You have been a department manager at Metro Hospital for 15 months. Today you received a memo from the Human Resources department indicating that one of the employees whom you supervise, Ramon Olivarez, has come to them to file a grievance against one of your actions. In accordance with company policy, you are asked to provide a written response within a week. A copy of Ramon’s grievance is attached to the memo and reads as follows: “My manager...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Consider the proposal. Should SCF accept or reject ACL’s request? If you were the project manager, which option would you select? What risks are involved with your choice and with ACL’s request? Shell Case Fabricators BACKGROUND Shell Case Fabricators (SCF) designs and builds shell casings that enclose electronic products such as calculators, cell phones, modems. Typically the cases are plastic or plastic compounds. SCF has six different production lines that cover different types of product. For example, the largest high...