Part 2: Project Scope Management
Congratulations! You have been selected as the project manager
for the Green Computing Research Project. The company’s CIO, Ben,
is the project sponsor, and Ito is the program manager for the
larger Environmental Technologies Program that this project is part
of. Now you need to put together your project team and get to work
on this high-visibility project. You will work with Ben to handpick
your team. Ben had already worked with the HR department to
advertise these openings internally as well as outside the company.
Ben had also used his personal contacts to let people know about
this important project. In addition, you are encouraged to use
outside consultants and other resources, as appropriate. Initial
estimates suggest that about $300,000 budgeted for this project
will go to internal staffing and the rest to outside sources. The
main products you’ll produce will be a series of research reports
one for each green computing
technology listed earlier plus one final report including all data
plus formal project proposals for
at least four recommendations for implementing some of these
technologies. Ben also suggested that the team come up with at
least 20 different project ideas and then recommend the top four
based on extensive analysis. Ben thought some type of decision
support model would make sense to help collect and analyze the
project ideas. You are expected to tap into resources available
from the Environmental Technologies Program, but you will need to
include some of those resources in your project budget. Ben
mentioned that he knew there had already been some research done on
increasing the use of telecommuting. Ben also showed you examples
of what he considered to be good research reports. You notice that
his examples are very professional, with a lot of charts and
references, and most are 20 30 pages long, single-spaced. Ben has
also shown you examples of good formal project proposals for We Are
Big, Inc., and you are surprised to see how detailed they are, as
well. They often reference other research and include a detailed
business case.
Tasks
Work Breakdown Structure Template for Project Name
Prepared by: Date:
1.1 Subcategory
1.2 Subcategory
1.2.1 Sub-subcategory
1.2.2 Sub-subcategory
1.3 Subcategory
1.4 Subcategory
2.1 Subcategory
2.2 Subcategory
2.2.1 Sub-subcategory
2.2.2 Sub-subcategory
2.3 Subcategory
2.4 Subcategory
3.2.1 Sub-subcategory
3.2.2 Sub-subcategory
Part 2: Project Scope Management Congratulations! You have been selected as the project manager for the...
Create a Work break down structure (WBS) for the following project case. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks. ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should include 40...
Create a Work break down structure (WBS) for the following project case. The WBS should be organized by either “phase” or “project management process groups.” Break down the work to Level 3. The case description is simple. Thus, go beyond the case description and be creative to include additional detailed tasks. ---------------[Case] ----------------------- Project for building a new, state-of-the-art multimedia classroom for your organization within the next five months and the budget is $200,000. The classroom should include 40 high-end...
(TCO 2) You are a project manager for a new hardware/software project. You just received the project charter and established your scope statement. Within the scope statement, you defined some of the key components to meet the overall project objective. Establishing requirements will be critical to define and get approved. The hardware will be new for your company, so you will need to ensure the vendor is selected and the hardware is appropriately installed into your environment. The supporting software...
HU, Closed book, 13. Scope management for a project begins with: (53M) A) A work package. B) An organization breakdown structure. C) A statement of goals. D) A configuration statement. 14. A graphical display of costs against project schedule is called a(n): (5SS) A) S-curves. B) Gantt chart C) Project schedule chart D) Budget in phases 15. The lowest level in work breakdown structure contains the: (50V) A) Atoms. B) Activities. C) Finite elements D) Work packages. E) Sub-Task or...
I have this assignment that I need help with, I turned it in but I got a bad grade for it, could someone please help me take an overview of it or take a look at it. but I want to change the project to Fundraising for kids in need all over the world. Because there is an assignment that I did in the past that is connected to it. Develop a work breakdown structure (WBS) for the project. Break...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Question 1 (1 point) The project scope statement and resource calendars are inputs to which Project Time Management process? Question 1 options: Sequence Activities Estimate Activity Resources Develop Schedule Control Schedule Question 2 (1 point) Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area? Question 2 options: Project Time Management Project Cost Management Project Scope Management Project Human Resource Management Question 3 (1 point) Units of measure, level of precision, level of accuracy, control thresholds,...
A) We require you to describe how you would use project management tools to develop and implement a project plan. Discuss at least 3 tools from below: project management software Gantt and bar charts critical path method (CPM) Program Evaluation Review Technique charts (PERT) cost schedule control system life cycle cost analysis logistics support analysis spreadsheets technical resources B) Whilst completing your project plan, ensure you include the following: deliverables work breakdown budget and allocation of resources timelines risk management...
!!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...
You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths are your organizational and leadership skills....