Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...

Consider a project with the following information:

Activity Duration Predecessors
A 5 --
B 7 A
C 9 B
D 5 B
E 7 C, D
F 6 D
G 4 C
H 7 E, F, G
Activity Duration ES EF LS LF Float
A 5 0 5 0 5
B 7 5 12 5 12
C 9 12 21 12 21
D 5 12 17 16 21
E 7 21 28 21 28
F 6 17 23 22 28
G 4 21 25 24 28
H 7 28 35 28 35
Activity Duration Total Float Resource Hours Needed per Week Total Resources Required
A 5 Weeks 10
B 7 Weeks 8
C 9 Weeks 7
D 5 Weeks 8
E 7 Weeks 4
F 6 Weeks 6
G 4 Weeks 5
H 7 Weeks 8
Total

  

1. Calculate the total resources required for this project, and create a Resource Loading table, highlighting the activity float.

2. Consider that the maximum resource hours available per week are 10. Which weeks are overcommitted?

3. What options are available for you to resource-level the project? Re-create the Resource Loading table.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Float = LF - EF

Activity Duration ES EF LS LF Float
A 5 0 5 0 5 0
B 7 5 12 5 12 0
C 9 12 21 12 21 0
D 5 12 17 16 21 4
E 7 21 28 21 28 0
F 6 17 23 22 28 5
G 4 21 25 24 28 3
H 7 28 35 28 35 0
Activity Duration Total Float Resource Hours Needed per Week Total Resources Required
A 5 Weeks 0 10 50
B 7 Weeks 0 8 56
C 9 Weeks 0 7 63
D 5 Weeks 4 8 40
E 7 Weeks 0 4 28
F 6 Weeks 5 6 36
G 4 Weeks 3 5 20
H 7 Weeks 0 8 56

1.

Resource loading table with resource histogram:

2.

As it is very clear from the resource histogram, weeks starting from week-13 and up to week-23, the resources are overcommitted i.e. more than 10 per week.

3.

The project cannot be completed within 35 weeks' time if the capacity is 10 hours per week. We can use the floats to balance the load but still overshooting happens in-between. This is shown below:

So, the only alternative is to extend the project beyond 35 weeks as shown:

So, the project has to be delayed by 11 more weeks.

Add a comment
Know the answer?
Add Answer to:
Consider a project with the following information: Activity Duration Predecessors A 5 -- B 7 A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • 5.) Consider a project whose activities are listed in the table below. Activity A will have...

    5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…    Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...

  • The following data were obtained from a project to expand a warehouse: Activity Duration Predecessors Resources/cost...

    The following data were obtained from a project to expand a warehouse: Activity Duration Predecessors Resources/cost A 2 weeks -- 1 Excavator/$800 day B 3 weeks -- 1 Excavator/$800 day C 2 weeks -- 1 Concrete Mixer/$250 day D 3 weeks A 1 Crane/$1,000 day E 2 weeks C 1 High-lift/$500 day F 1 week B,D 1 Crane/$1,000 day The contractor has only one machine of each type available at the above costs, and operations cannot be split. Additional equipment...

  • 1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C...

    1. Consider the following information: Activity Predecessor Duration (weeks) A None 2 B A 4 C A 3 D A 2 E B 3 F C 6 G C, D 5 H E, F 6 I G 5 J H, I 5 Activities B and H can be shortened by a minimum of 2 time units. Which activity would you shorten to reduce the project duration of 2 weeks. Why? (be specific)

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Use a PERT network to establish the expected duration for the project described in the table...

    Use a PERT network to establish the expected duration for the project described in the table below:    (SHOW the PERT NETWORK) Activity Predecessors Duration a        m       b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400         600 D B, C 4 6 8 200                             600 E B, C 6 9 12 400 300 F C 4 6 14...

  • Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as...

    Q5: A construction project consists of activities, immediate predecessors (IPA) and duration in weeks are as shown in the following table. Draw the project network diagram, find the critical path and calculate the corresponding project completion time. Also, find the total float as well as the free float for each activity and the non- critical activities. (10 Marks) ТРА Duration (Weeks) Activity A B نما 4 с 14 D A 10 E F A BD BD с F.H 5 4...

  • Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c,...

    Activity Predecessor Duration (weeks) a none 12 b none 5 c a, b 7 d c, e 2 e b 8 f e 9 g d 5 h f,g 8 Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late delivering some key data points...

  • Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7...

    Construct an Activity-on-branch network from the precedence relationships of activities shown Activity Predecessors Duration 6 7 A A A B с D E F 1 14 5 8 9 3 5 3 B C D C, D D H F E, J F GI G, I L, N H I J K L M 12 6

  • Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...

    Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT