Describe and compute the takt time based on the information below. Operating Time: The plant worked...

Describe and compute the takt time based on the information below.
Operating Time:
The plant worked one shift of eight hours, with two 15 minute breaks and one 15 minute stand up department meeting.
Customer Demand:
Part A Quantity 40, Part B Quantity 20, Part C Quantity 50, and Part D Quantity 30
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Takt time means that maximum time needed to produce one unit of product inorder to meet the customer demand .

Takt time =

Given that one shift of eight hours = 60min /hr * 8 hour

= 480 mints /shift

Break = 2*15mint /shift

= 30 mint /shift

Meeting = 15 mint /shift

Net operating time = 480 -30 -15

= 480 - 45

= 435 mints /shift

Takt time = 435 / quantity

Part A

Takt time = 435/40

=10.875 minute /unit

Part B

Takt time = 435 /20

= 21.75 minute/ unit

Part C

Takt time = 435/ 50

= 8.7 minute / unit

Part D

Takt time = 435/30

= 14.5 minute / unit

Add a comment
Know the answer?
Add Answer to:
Describe and compute the takt time based on the information below. Operating Time: The plant worked...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT