Question

The plant works one eight hours shift each day. Each day there are two 15-minute breaks and a ove hrour meeting The p...

The plant works one eight hours shift each day. Each day there are two 15-minute breaks and a ove hrour meeting

The part has a cycle time of 26 minutes. The customer needs 30 parts per day

parts are delivered in a box of 15 parts each.

how many people are need for this cell ?

1

2

3

4

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ei?ht hours in a dat Plant And Thare, are toe iS- munutes breaks ard emi ra ^zcle Time of past ih 26 minuts, That mans all op

Add a comment
Know the answer?
Add Answer to:
The plant works one eight hours shift each day. Each day there are two 15-minute breaks and a ove hrour meeting The p...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The production facility run on one 7.5 hour shift. There is a 15 minute meeting planned at the beginning of the shift an...

    The production facility run on one 7.5 hour shift. There is a 15 minute meeting planned at the beginning of the shift and 30 total minutes of setup time each day. 15 minutes of unscheduled equipment failure usually occurs. 380 good parts and 20 defective parts were produced with a standard cycle time of 60 parts per hour. What is the Overall Equipment Effectiveness (OEE)? A) 93.51% B) 78.56% C) 85.17% D) 72.34%

  • The work shift at the ABC Company runs fr lunch from 11:30 to 12:15 p.m. that does not count as part of the work shift (workers are not paid for this time). The company provides two 12-minute res...

    The work shift at the ABC Company runs fr lunch from 11:30 to 12:15 p.m. that does not count as part of the work shift (workers are not paid for this time). The company provides two 12-minute rest breaks during working hours (paid time), one in the morning and one in the afternoon. The com m. to 4:15 p.m. with a 45 minute break for pany also allows 25 minute day for personal needs (paid time). In addition, a work...

  • The city of Lakewood has one magistrate who performs civil marriage ceremonies. She works eight hours...

    The city of Lakewood has one magistrate who performs civil marriage ceremonies. She works eight hours on regular business days. On average, couples arrive every 15 minutes to be married. The ceremony, including information processing, usually takes about 10 minutes. The city estimates that the time that people spend waiting to be married costs them $10 per hour in goodwill and prospective campaign donations. There are two ways that they are considering to reduce this waiting cost: a. Install a...

  • Big Al gives his worker's a one hour lunch and two fifteen minute breaks each day....

    Big Al gives his worker's a one hour lunch and two fifteen minute breaks each day. He believes that a cold soda machine would be appreciated by his workers, and an appreciated worker is a good worker. He has priced a machine at a national member only warehouse for $2,050. The machine should be usable for 3 years, after which it would be inefficient, obsolete and would have to be disposed of at the dump. Big Al believes that 14...

  • The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for...

    The owner of a small mill-working plant that builds cabinets is developing his aggregate plan for the next year. The relevant cost data and forecast for the next 4 quarters is provided below. The company currently has 20 employees and works one 8 hour shift each day with 2 paid 15 minute breaks. Assume each quarter has 65 working days, and that it currently has no units in stock. Use this information and the information from the table to answer...

  • Question Help The table below provides the parameters for a new current state vake stream map...

    Question Help The table below provides the parameters for a new current state vake stream map for the family traine e Jensen Bearings infirm described in the chapter. This table depicts the value stream atter Kline Steel agrees to condaily orders for steel sheels and also agrees to deliver on a daily basis Calculate each component of the new value stream's reduced lead me Jensen Bearings operates 5 days per week Click the icon to view the data from the...

  • Buildit is a construction company specialized in public works (roads, bridges, pipelines, tunnels, railroads, etc.). Within...

    Buildit is a construction company specialized in public works (roads, bridges, pipelines, tunnels, railroads, etc.). Within Buildit, it often occurs that engineers working at a construction site (called “site engineers”) need a special type of equipment, such as a truck, an excavator, a bulldozer, a water pump, etc. Buildit has some heavy equipment available in its depot, but very often, it hires equipment when needed from specialized heavy equipment suppliers. A piece of heavy equipment is called a “plant” in...

  • This is a two part question for two different case. I am currently focusing on case...

    This is a two part question for two different case. I am currently focusing on case 5 Case 4: Time for some Maintenance on Maintenance? (consider: Chapters 6 & 7) Date: February 19, 2012; 9:00 AM It was a Sunday morning, and Patrick decided to make a quick visit to the plant. He knew that several people were working overtime that day, and the plant would be running at full speed—and that is was important for the hourly employees to...

  • Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes...

    Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 271 and Part 342. Part 271 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 342 was added. Part 342 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after the addition of the...

  • Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes...

    Scenario Cartech Manufacturing is engaged in the production of replacement parts for automobiles. One plant specializes in the production of two parts: Part 271 and Part 342. Part 271 produces the highest volume of activity, and for many years it was the only part produced by the plant. Five years ago, Part 342 was added. Part 342 was more difficult to manufacture and required special tooling and setups. Profits increased for the first three years after the addition of the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT