The beginning workforce is 335 employees. The monthly output per employee is 400 units. The cost...

The beginning workforce is 335 employees. The monthly output per employee is 400 units. The cost to hire and lay off a worker are ​$1,000 and ​$2,000​, respectively. The cost to carry an item in inventory for one month is estimated at ​$11​, and the stockout cost is ​$30 per unit. Show the production​ schedule, the inventory​ levels, and the changes in workforce from period to period. Compute the​ plan's cost.

Construct the chase sales and operations plan

​(enter your responses as whole numbers​).

Month

1

2

3

4

5

6

Total

Demand

32,000

49,600

36,800

25,600

20,800

23,200

188,000

Production

nothing

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost of the plan excluding regular time production cost = inventory cost+stock out cost + hiring cost + firing cost
=0+0+1000*50+2000*327
=$704000

Formula

Add a comment
Know the answer?
Add Answer to:
The beginning workforce is 335 employees. The monthly output per employee is 400 units. The cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company believes that its demand for the next six months is as follows ota ont eman The output per worker per month is 100 units. The per worker hiring and lay off costs are $1,500 and $3,500, resp...

    A company believes that its demand for the next six months is as follows ota ont eman The output per worker per month is 100 units. The per worker hiring and lay off costs are $1,500 and $3,500, respectively. There is no beginning inventory, and the starting workforce is 135. It cost the company $25 to carry an item in inventory each month, and the stockout costs is estimated to be $25 per unit. Develop a level sales and operations...

  • Check my wa will have 400 mowers in inventory at the beginning of the month and...

    Check my wa will have 400 mowers in inventory at the beginning of the month and desires to maintain at least that number at the end of each month. Assume hiring and layoff/firing, if necessary, occur at the beginning of the quarter. Below is other critical data: Production cost per unit = $230 Inventory carrying cost per month per unit = $50 (based on ending month inventory) Hiring cost per worker = $420 Firing cost per worker = $540 Beginning...

  • Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1...

    Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1 2 3 4 Demand 500 800 1,000 1,400 Month 5 6 7 8 Demand 2,000 3,000 2,700 1,500 Month 9 10 11 12 Demand 1,400 1,500 2,000 1,200 An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular-time wages per month. Undertime is paid at the same rate as regular time. In accordance with...

  • . An Excel spreadsheet containing data tables is available 2. All data in this problem set are fictitious. 3. Please round the number of required workers/agents up to the next highest integer in all p...

    . An Excel spreadsheet containing data tables is available 2. All data in this problem set are fictitious. 3. Please round the number of required workers/agents up to the next highest integer in all problems. Problem 1 PrintEverything is a leading 3D-printer manufacturer. Their products are quite popular recently. The following table provides the demand forecast for their most popular 3D-printer. Month Demand Forecast (Number of 3D-Printers) OCT-15 5760 NOV-15 3697 DEC-15 5587 JAN-16 4815 FEB-16 6325 MAR-16 6145 APR-16...

  • How do I calculate the one time adjustment of workforce to support the level production plan?...

    How do I calculate the one time adjustment of workforce to support the level production plan? Problem information: Month: 1 2 3 4 5 6 7 8 9 10 11 12 Demand: 500 800 1000 1400 2000 3000 2700 1500 1400 1500 2000 1200 Management at the Kerby Corporation has determined the following aggregated demand schedule in Units. An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular time wages...

  • How would you modify the workforce to reduce cost? What would be the cost of the...

    How would you modify the workforce to reduce cost? What would be the cost of the 46-worker production plan? Assume the following costs: • Holding Cost (per unit per month): $8.50 • Hiring Cost per worker: $800 • Firing Cost per worker: $1,250 • Payroll Cost: $75/worker/day Shortage Cost: $50 unit short/month • Assume that the work force at end of Dec was 40. • How many did you have to hire? Starting inver Ending invent 200 100 K= 0.342105263...

  • Manufacturers Inc. (MI) currently has a labor force of 10, which can produce 600 units per...

    Manufacturers Inc. (MI) currently has a labor force of 10, which can produce 600 units per period. The labor cost is now $5000 per period per employee. The company has a long-standing rule that does not allow it to make use of any overtime. In addition, the product cannot be subcontracted, due to the specialized nature of the machinery that MI uses to produce it. As a result, MI can only increase/decrease production by hiring or laying off employees. The...

  • Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company...

    Refrigeration Corp. needs an aggregate plan for January through June for its refrigerator production. The company has developed the following​ data: a) Plan​ A: Vary the workforce so that production meets the forecasted demand​ (maintain inventory at 250​ units). Bell had eight employees on staff in December.​ Part-time labor is available. Complete the following table ​(enter your responses as whole​ numbers). Costs Holding cost ​$8/ refrigerator/ month Subcontracting ​$80/ refrigerator ​Regular-time labor ​$12/ hour Overtime labor ​$18/ hour for hours...

  • Plan B: Vary the workforce to produce the prior month's demand. The firm produced 1,300 units...

    Plan B: Vary the workforce to produce the prior month's demand. The firm produced 1,300 units in June. The cost of hiring additional workers is $35 per unit produced. The cost of layoffs is $60 per unit cut back. (Enter all responses as whole numbers.) Note: Both hiring and layoff costs are incurred in the month of the change (i.e., going from production of 1,300 in July to 1200 in August requires a layoff (and related costs) of 100 units...

  • a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost...

    a) the total cost of hiring=$ (enter your response as a whole number) b)the total cost of layoffs=$?(enter your response as a whole number) c)the total inventory carrying cost =$?(enter your response as a whole number) d)the total stockout cost$?(enter your response as a whole number) e) the total cost, excluding normal time labor cost, is =$ ?(enter your response as a whole number) The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT