A manual arc-welding cell uses a welder and a fitter. The cell operates 2000 hr/yr. The welder is paid $30/hr and the fitter is paid $25.00/hr. Both rates include applicable overheads. The cycle time to complete one welded assembly is 15.4 min. Of this time, the arc-on time is 25%, and the fitter’s participation in the cycle is 30% of the cycle time.
A robotic arc-welding cell is being considered to replace this manual cell. The new cell would have one robot, one fitter, and two workstations, so that while the robot is working at the first station, the fitter is unloading the other station and loading it with new components. The fitter’s rate would remain at $25.00/hr. For the new cell, the production rate would be eight welded assemblies per hour. The arc-on time would increase to almost 52%, and the fitter’s participation in the cycle would be about 62%. The installed cost of the robot and workstations is $158,000.
Power and other utilities to operate the robot and arc welding equipment will be $3.80/hr, and annual maintenance costs are $3500. Given a 3-year service life, 15% rate of return, and no salvage value,
(a) determine the annual quantity of welded assemblies that would have to be produced to reach the breakeven point for the two methods.
A manual arc-welding cell uses a welder and a fitter. The cell operates 2000 hr/yr. The...
Chapter 29 Welding Processes-Fundamentals of Modern Manufacturing 6th 29.2 (SI units) In the previous problem, a proposal has been made to install an industrial robot to replace the welder. The cell would consist of the robot, two welding fixtures, and the fitter who loads and unloads the parts. With two fixtures, the fitter and robot would work simultaneously, the robot welding at one fixture while the fitter unloads and loads at the other. At the end of each work cycle,...
9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts)
9. A new product is to be assembled on...
A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and precedence constraints are given in the table below. The workers will operate the line for 400 min per day and must produce 300 products per day. A mechanized belt, moving at a speed of 1.25 m/min, will transport the products between stations. Because of the variability in the time required to perform the assembly operations, it has been determined that...
The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. a) The bottleneck time of the system is 6 minutos per unit (onitor your response as a whole number). b) Station 3 is the bottleneck station c) The throughout time is 13 minutes (onter your response as a whole number). d) If the firm operates 8 hours per...
Question 1 A turning operation is carried out on aluminum. Based on the specific energy values in Table 20.2, determine material removal rate and cutting power in the operation under the following sets of cutting conditions: (a) Cutting speed 5.6 m/s, feed 0.25 mm/rev, and depth of cut 2.0 mm; and (b) cutting speed- 1.3 m/s, feed 0.75 mm/rev, and depth 4.0 mm. Question 2 Consider a turning operation performed on steel whose hardness 225 HB at a cutting speed...