Question

A manual assembly line is to be designed to make a small consumer product. The work...

  1. A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and precedence constraints are given in the table below. The workers will operate the line for 400 min per day and must produce 300 products per day. A mechanized belt, moving at a speed of 1.25 m/min, will transport the products between stations. Because of the variability in the time required to perform the assembly operations, it has been determined that the tolerance time should be 1.5 times the cycle time of the line. (a) Determine the ideal minimum number of workers on the line. (b) Use the Largest Candidate Rule to balance the line. (c) Compute the balance delay for your solution in part (b).

Element

Time Te (min)

Preceded by

1

0.4

-

2

0.7

1

3

0.5

1

4

0.8

2

5

1.0

2,3

6

0.2

3

7

0.3

4

8

0.9

4,9

9

0.3

5,6

10

0.5

7,8

  1. Solve Problem 1 using the Kilbridge and Wester method.

  1. Solve Problem 1 using Ranked Proportional Weights Method

  1. Work content time is 54 min for a product assembled on a manual production line. Each product is built on a base part that is launched onto the beginning of the line each cycle. The line uses an overhead conveyor that moves at 1.2 m/min. There are 27 workstations on the line, one-third of which have two workers; the rest have one worker each. Repositioning time per worker is 9 sec, and uptime efficiency is 95%. (a) What would be the hourly production rate if the line were perfectly balanced? (b) If the actual production rate is 33 units/hr, what is the balance efficiency of the line? (c) To compensate for service time variability, it has been decided that the tolerance time should be 40% greater than the cycle time. To achieve this, what station length should be used on the line? (d) Determine the elapsed time that each base part spends on the production line?

Hint:

(a) Find no. of workers; for perfect balance Eb = 1, find Tc, using uptime efficiency, find Rp

(b) Using actual Rp find balance efficiency

(c) Tolerance time = station length/ conveyor speed, find new station length

(d) Calculate elapsed time

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
A manual assembly line is to be designed to make a small consumer product. The work...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate...

    9. A new product is to be assembled on a 100% manual assembly line. The line is designed to produce 120,000 units/yr. Work content time for the product is 39.5 min. The assembly line will operate 50 wklyr, 5 shifts/wk, 8 hr/shift. Expected line efficiency is 96%. There will be one worker per station. Determine (a) average hourly production rate, (b) cycle time, and (c) ideal minimum number of workstations.(6 pts) 9. A new product is to be assembled on...

  • t nc automated stations, and (e) labor efficiency on the line. 4.6 A manual assembly line...

    t nc automated stations, and (e) labor efficiency on the line. 4.6 A manual assembly line is being designed for a product whose annual demand is 100,000 units The line will operate 50 wk/yr, 5 shifts/wk, and 8 hr/shift. Work units will be attached to a con- moving conveyor. Work content time is 42.0 min.Assume line efficiency is 0.95, bal- is 0.93 or slightly less, repositioning time is 6 sec, and manning level is 1.4 Determine (a) average hourly production...

  • 4.22 The table below lists the work elements in minutes to be performed on assembly line...

    4.22 The table below lists the work elements in minutes to be performed on assembly line with precedence requirements. Annual demand is 60000 units. The line will operate on shift (2000 hr/yr). Line efficiency is expected 95% and repositioning time is 6 sec. The table below defines the precedence relationships and element times for a new model toy. (a) Construct the precedence diagram for this job. (b) If the ideal cycle time = 1.1 min. repositioning time = 0.1 min,...

  • A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The...

    A rider lawn mower is produced on a manual assembly line. Work content time=49.5 min. The line has 25 workstations with a manning level = 1.2. Available shift time per day = 8 hr, but equipment downtime during the shift reduces actual production time to 7.5 hr on average. This results in an average daily production of 244 units/day. Repositioning time per worker = 5% of cycle time. Determine (a) line efficiency, (b) balancing efficiency, and (c) repositioning time.

  • A product whose annual demand = 75,000 units is produced on a manual assembly line. The...

    A product whose annual demand = 75,000 units is produced on a manual assembly line. The line operates 50 wk/year, 5 shifts/wk, and 7.5 hr/shift. Work content time = 48.9 min. Line efficiency = 0.97, balancing efficiency = 0.93, and repositioning time = 8 sec. Determine (a) Hourly production rate, (b) Number of workers needed, and (c) Number of workstations if the manning level is 1.333. [15 pts] – Note: must show computational details and circle your final answers inual...

  • In an assembly line, the uniform time that each piece of work spends at a workstation...

    In an assembly line, the uniform time that each piece of work spends at a workstation before moving to the next station is called: a. Assembly line timing b. Active production time Assembly line balance d. Workstation activity time e workstation cycle time

  • Francis Johnson's plant needs to design an efficient assembly line to make a new product. The...

    Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....

  • The operations manager of an instruments company is balancing an assembly line. The company needs to...

    The operations manager of an instruments company is balancing an assembly line. The company needs to build 96 instruments per 24-hour day. The assembly line activities are: a. Draw the precedence diagram. b. If the daily (24-hour) production rate is 96 units, what is the greatest possible cycle time? c. If the cycle time after allowances is given as 10 minutes, what is the daily (24-hour) production rate? d. With a 10-minute cycle time, what is the theoretical minimum number...

  • Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new...

    Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 24 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 1.0 1.0 2.5 1.5 A, B, C 1.5...

  • Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line...

    Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand. Time to Complete Task (seconds) Task 1 20 Task 2 20 Task 3 10 Task 4 15 Task 5 10 Task 6 15 Task 7 40 Task 8 10 Task 9 15 Task 10 20 Task 11 10 Task 12 15 The current conveyor-paced assembly-line configuration assigns...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT