Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand.
| Time to Complete Task (seconds) | |
| Task 1 | 20 |
| Task 2 | 20 |
| Task 3 | 10 |
| Task 4 | 15 |
| Task 5 | 10 |
| Task 6 | 15 |
| Task 7 | 40 |
| Task 8 | 10 |
| Task 9 | 15 |
| Task 10 | 20 |
| Task 11 | 10 |
| Task 12 | 15 |
The current conveyor-paced assembly-line configuration assigns the workers in the following way:
e. Assume the firm has hired a fifth worker. The task
assignments for the five workers are shown below. What is the
capacity of this line now? (Round your final answer to two
decimal places.)
| Worker | Task(s) | |||
| 1 | 1,2 | |||
| 2 | 3,4,5 | |||
| 3 | 6,7 | |||
| 4 | 8,9 | |||
| 5 | 10,11,12 | |||
f. Again, assume the firm has hired a fifth worker. The task assignments for the five workers are shown below. What is the capacity of this line now? (Round your final answer to two decimal places.)
| Worker | Task(s) | |||
| 1 | 1,2 | |||
| 2 | 3,4,6 | |||
| 3 | 5,8,10 | |||
| 4 | 7 | |||
| 5 | 9,11,12 | |||
g. Now assume the firm is using eight workers. The task assignments for the eight workers are shown below. What is the capacity of this line now? (Round your final answer to two decimal places.)
| Worker | Task(s) |
| 1 | 1 |
| 2 | 2,3 |
| 3 | 4,5 |
| 4 | 6 |
| 5 | 7 |
| 6 | 8,9 |
| 7 | 10,11 |
| 8 | 12 |
The capacities are computed in 'units per hour' as nothing was mentioned. The numbers will be different if they want you to enter it in 'units per minute' or 'per second'. Please make a note of this.
(e)
| Worker | Task(s) | Processing time per unit (P) | No. of workers (N) | Capacity in units per hr. = 3600*N/P |
| 1 | 1,2 | 20+20=40 | 1 | 90.00 |
| 2 | 3,4,5 | 10+15+10=35 | 1 | 102.86 |
| 3 | 6,7 | 15+40=55 | 1 | 65.45 |
| 4 | 8,9 | 10+15=25 | 1 | 144.00 |
| 5 | 10,11,12 | 20+10+15=45 | 1 | 80.00 |
So,
the capacity is Min(90, 102.86, 65.45, 144,80) = 65.45 units per hour
(f)
| Worker | Task(s) | Processing time per unit (P) | No. of workers (N) | Capacity in units per hr. = 3600*N/P |
| 1 | 1,2 | 20+20=40 | 1 | 90 |
| 2 | 3,4,6 | 10+15+15=40 | 1 | 90 |
| 3 | 5,8,10 | 10+10+20=40 | 1 | 90 |
| 4 | 7 | 40 | 1 | 90 |
| 5 | 9,11,12 | 15+10+15=40 | 1 | 90 |
So,
the capacity is 90 units per hour
(g)
| Worker | Task(s) | Processing time per unit (P) | No. of workers (N) | Capacity in units per hr. = 3600*N/P |
| 1 | 1 | 20 | 1 | 180 |
| 2 | 2,3 | 20+10=30 | 1 | 120 |
| 3 | 4,5 | 15+10=25 | 1 | 144 |
| 4 | 6 | 15 | 1 | 240 |
| 5 | 7 | 40 | 1 | 90 |
| 6 | 8,9 | 10+15=25 | 1 | 144 |
| 7 | 10,11 | 20+10=30 | 1 | 120 |
| 8 | 12 | 15 | 1 | 240 |
So,
the capacity is Min(180, 120, ..., 240) = 90 units per hour
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line...
Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--‐paced line flow). Each worker must perform at least one task. Time to Complete Task (seconds): Task 1: 26 Task 2: 25 Task 3: 15 Task 4: 24 Task 5: 15 Task 6: 20 Task 7: 47 Task 8: 15 Task 9: 20 Task 10:25 Task 11: 15 Task 12: 20 The current conveyor--paced assembly-‐line configuration assigns the workers in the following...
If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task C? A Four-Task Assembly Line 5 minutes minutes minutes minutes 71% Unable to calculate 24 100% 43%
If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task C? A Four-Task Assembly Line minutes minutes minutes 71% Unable to calculate 100% 43%
PowerToys Inc. produces a small remote-controlled toy truck on a conveyor belt with nine stations. Each station has, under the current process layout, one worker assigned to it. Stations and processing times are summarized in the following table: Station Task Processing Times (seconds) 1 Mount battery units 70 2 Insert remote control receiver 80 3 Insert chip 90 4 Mount front axle 60 5 Mount back axle 65 6 Install electric motor 50 7 Connect motor to battery unit 75...
Question 2 (10 points)
If four workers (1 worker for each task) were assigned to the
four task assembly line shown below, what would be the efficiency
of the worker doing Task B?
Question 2 options:
43%
Unable to calculate
100%
71%
Question 3 (10 points)
The facility layout that would be used to construct a
hydroelectric dam, is an example of a
Question 3 options:
process layout
fixed-position layout
product layout
cellular layout
Question 4 (10 points)
The facility...
Question 30 (3.03 points) What would happen to productivity if the following four-task assembly line went from having 4 workers (one for each task) to 4 workers doing all four tasks? A Four-Task Assembly Line B minutes minutes minutes minutes O Productivity would stay the same O Productivity would decrease due to having extra workers O Productivity would increase from 1 unit in 7 minutes to 1 unit in 3 minutes Productivity would increase from 1 unit in 7 minutes...
consider a labor market experiment involving four buyers (firms) and four sellers (workers). Each firm seeks to hire a single worker and each worker can work for a single firm. Each firm has a maximum revenue they can earn per worker hired. Each worker has a cost of working, which represents the value of his or her leisure time. Suppose the revenues from hiring a worker are $23, $15 and $21 and $17 for firms 1, 2, 3 and 4,...
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...
The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequence of assembly steps performed by five workers. Each worker does two tasks. Workers are paid $15 per hour. Worker Task Time (seconds) A T1 40 A T2 25 B T3 20 B T4 15 C T5 10 C T6 15 D T7 10 D T8 20 E T9 25 E T10 35 Instruction: Round "cost of direct labor" and "average labor...
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table. No Tasks 1 2 3 4 5 6 7 PR 1 Select correct mufflers 5 4 6 3 4 5 5 120 2 Remove old muffler 8 8 8 6 8 7 6 85 3 Install new muffler 15 13 15 14 12 15 13 85 4 Inspect the...