Question

Question 2 (10 points) If four workers (1 worker for each task) were assigned to the...

Question 2 (10 points)

If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task B?

Question 2 options:

43%

Unable to calculate

100%

71%

Question 3 (10 points)

The facility layout that would be used to construct a hydroelectric dam, is an example of a

Question 3 options:

process layout

fixed-position layout

product layout

cellular layout

Question 4 (10 points)

The facility layout that would be used to construct an apartment complex, is an example of a

Question 4 options:

process layout

cellular layout

product layout

fixed-position layout

Question 5 (10 points)

Facility layout studies are necessary when

Question 5 options:

a new facility is constructed

there is a significant change in demand or throughput volume

different processes, equipment, and/or technology are installed.

all of the above

Question 6 (10 points)

A new custom car shop has just opened. The will provide the following services: custom paint, custom electronics, custom wheels, and custom lighting. What type of facility layout meets their needs the best?

Question 6 options:

product layout

process layout

fixed-position layout

cellular layout

Question 7 (10 points)

What would happen to productivity if the following four-task assembly line went from having 4 workers (one for each task) to 4 workers doing all four tasks?

Question 7 options:

Productivity would increase from 1 unit in 7 minutes to 4 units in 18 minutes.

Productivity would decrease due to having extra workers

Productivity would increase from 1 unit in 7 minutes to 1 unit in 3 minutes

Productivity would stay the same

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 2: 100%

Explanation: in this 4 worker assembly line, the bottleneck worker is at Task B (because Task B takes the most time)

Hence, the cycle time of the assembly line is 7 mins, and

Efficiency= task time/cycle time= 7 mins/7 mins= 1 that is 100%

Add a comment
Know the answer?
Add Answer to:
Question 2 (10 points) If four workers (1 worker for each task) were assigned to the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • If four workers (1 worker for each task) were assigned to the four task assembly line...

    If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task C? A Four-Task Assembly Line minutes minutes minutes 71% Unable to calculate 100% 43%

  • If four workers (1 worker for each task) were assigned to the four task assembly line...

    If four workers (1 worker for each task) were assigned to the four task assembly line shown below, what would be the efficiency of the worker doing Task C? A Four-Task Assembly Line 5 minutes minutes minutes minutes 71% Unable to calculate 24 100% 43%

  • Question 30 (3.03 points) What would happen to productivity if the following four-task assembly line went...

    Question 30 (3.03 points) What would happen to productivity if the following four-task assembly line went from having 4 workers (one for each task) to 4 workers doing all four tasks? A Four-Task Assembly Line B minutes minutes minutes minutes O Productivity would stay the same O Productivity would decrease due to having extra workers O Productivity would increase from 1 unit in 7 minutes to 1 unit in 3 minutes Productivity would increase from 1 unit in 7 minutes...

  • Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--...

    Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--‐paced line flow). Each worker must perform at least one task. Time to Complete Task (seconds): Task 1: 26 Task 2: 25 Task 3: 15 Task 4: 24 Task 5: 15 Task 6: 20 Task 7: 47 Task 8: 15 Task 9: 20 Task 10:25 Task 11: 15 Task 12: 20 The current conveyor--paced assembly-‐line configuration assigns the workers in the following...

  • Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line...

    Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand. Time to Complete Task (seconds) Task 1 20 Task 2 20 Task 3 10 Task 4 15 Task 5 10 Task 6 15 Task 7 40 Task 8 10 Task 9 15 Task 10 20 Task 11 10 Task 12 15 The current conveyor-paced assembly-line configuration assigns...

  • 2, (3 points) 10% of the population are low-productivity workers and 90% of the popula- tion are high-productivity workers. The present value of lifetime productivity for low- productivity workers is...

    2, (3 points) 10% of the population are low-productivity workers and 90% of the popula- tion are high-productivity workers. The present value of lifetime productivity for low- productivity workers is $150,000 and the present value of lifetime productivity for high- productivity workers is $200,000. It costs $30,000 for a low-productivity worker to go to school. (a) (1 point) Calculate how much the employer would pay in a pooling equilibrium? (b) (1 point) In a separating equilibrium, the firm is requiring...

  • Question 2 Explain four rules that could be used to design a product for assembly and discuss how they will provide...

    Question 2 Explain four rules that could be used to design a product for assembly and discuss how they will provide benefit, use sketches to illustrate your answer.. [8 marks] Table Q2 itemises the precedence and timing information that is required to complete the assembly of a product. Through the application of a Largest Candidate Rule procedure, devise an assembly task grouping to achieve an assembly rate of 30 per hour. What is the utilisation for each assembly station [8...

  • answer asap plz will thumb up Question 9 (10 points) There are basically 4 layout types...

    answer asap plz will thumb up Question 9 (10 points) There are basically 4 layout types used in organizing the work flow for manufacturing processes. They are: Fixed-Product Layout, Flowline/Product Layout, Cellular/Group Technology Layout, and Process/Functional/Job Shop Layout. A flowline/product layout has which of the following characteristics? a) Sometimes can be the preferred layout when high levels of precision are in order O b) The line for each part is organized in a way that facilitates the corresponding production flow....

  • Question 10 (4 points) The following table shows the total output, number of workers employed, variable...

    Question 10 (4 points) The following table shows the total output, number of workers employed, variable costs, and fixed costs of a firm Number of Workers 0 1 2 3 Total Output (units) 0 25 Variable Costs () 0 10 Fixed Costs (5) 150 150 150 SS 86 110 150 5 130 6 145 7 155 160 Suppose the only variable input that the firm uses is labor. What is the wage paid to a worker in the firm? O...

  • Exhibit 6-1 Production of pizza data Workers Pizzas 0   0 1   4 2 10 3 15...

    Exhibit 6-1 Production of pizza data Workers Pizzas 0   0 1   4 2 10 3 15 4 18 5 19 Exhibit 6-1 shows the change in the short-run production of pizzas as more workers are hired. The table shows the marginal product of the labor input is decreasing with the hiring of the third worker. A possible reason for this diminishing marginal product is: a. increased division of labor as additional workers are hired. b. increases in plant size. c....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT