Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--‐paced line flow). Each worker must perform at least one task. Time to Complete Task (seconds): Task 1: 26 Task 2: 25 Task 3: 15 Task 4: 24 Task 5: 15 Task 6: 20 Task 7: 47 Task 8: 15 Task 9: 20 Task 10:25 Task 11: 15 Task 12: 20 The current conveyor--paced assembly-‐line configuration assigns the workers in the following way: • Worker 1: Tasks1, 2, 3 • Worker 2: Tasks 4, 5, 6 • Worker 3: Tasks 7, 8, 9 • Worker 4: Tasks 10, 11, 12 Assume a demand rate of 21 units per minute. What would be the target manpower?
Total task time = sum of all task times =
Total Task Time = 26+25+15+24+15+20+47+15+20+25+15+20
Total Task time = 267 seconds
Desired output = 21 units per minutes
Cycle time or takt time = Available time / desired output = 60/21 = 2.857143 seconds per unit.
Target manpower = Total task time / cycle time =
Target Manpower = 267 / 2.857143 = 93.45
Target Manpower = 94
Consider the following tasks that must be assigned to four workers on a conveyor--paced assembly line (i.e., a machine--...
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There is unlimited demand. Time to Complete Task (seconds) Task 1 20 Task 2 20 Task 3 10 Task 4 15 Task 5 10 Task 6 15 Task 7 40 Task 8 10 Task 9 15 Task 10 20 Task 11 10 Task 12 15 The current conveyor-paced assembly-line configuration assigns...
1. Consider the following table providing the needed tasks to completing a successful project. The first column provides the name of the task, the second column states the time to complete that task and the third column tells when a task can begin. Task Time to Condition to start task complete #1 #2 #3 #4 #5 #6 #7 #8 #9 #10 #11 #12 #13 #14 #15 #16 #17 #18 #19 7 days None 5 days 8 daysNone 4 days 3...
The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 18 — B 10 A C 25 B D 15 B E 14 C F 17 D G 12 E, F H 20 G The workday is 6.25 hours long. Demand for completed product is 750 per day. a. Find the cycle time required to meet the desired output rate. (Round your answer to 1 decimal place.) b. What is the theoretical...
Question 2 (10 points)
If four workers (1 worker for each task) were assigned to the
four task assembly line shown below, what would be the efficiency
of the worker doing Task B?
Question 2 options:
43%
Unable to calculate
100%
71%
Question 3 (10 points)
The facility layout that would be used to construct a
hydroelectric dam, is an example of a
Question 3 options:
process layout
fixed-position layout
product layout
cellular layout
Question 4 (10 points)
The facility...
Question 30 (3.03 points) What would happen to productivity if the following four-task assembly line went from having 4 workers (one for each task) to 4 workers doing all four tasks? A Four-Task Assembly Line B minutes minutes minutes minutes O Productivity would stay the same O Productivity would decrease due to having extra workers O Productivity would increase from 1 unit in 7 minutes to 1 unit in 3 minutes Productivity would increase from 1 unit in 7 minutes...
The White Tooth Device Company is a manufacturer of high-end electric toothbrushes. For each toothbrush, there are a sequence of assembly steps performed by five workers. Each worker does two tasks. Workers are paid $15 per hour. Worker Task Time (seconds) A T1 40 A T2 25 B T3 20 B T4 15 C T5 10 C T6 15 D T7 10 D T8 20 E T9 25 E T10 35 Instruction: Round "cost of direct labor" and "average labor...
PowerToys Inc. produces a small remote-controlled toy truck on a conveyor belt with nine stations. Each station has, under the current process layout, one worker assigned to it. Stations and processing times are summarized in the following table: Station Task Processing Times (seconds) 1 Mount battery units 70 2 Insert remote control receiver 80 3 Insert chip 90 4 Mount front axle 60 5 Mount back axle 65 6 Install electric motor 50 7 Connect motor to battery unit 75...
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3, and 6 minutes, and the cycle time is 8 minutes?
Installing a muffler at Barut Garage, Inc. involves a five work tasks. Azra has timed workers performing these tasks seven times, with the results (in minutes) shown in the following table. No Tasks 1 2 3 4 5 6 7 PR 1 Select correct mufflers 5 4 6 3 4 5 5 120 2 Remove old muffler 8 8 8 6 8 7 6 85 3 Install new muffler 15 13 15 14 12 15 13 85 4 Inspect the...
Information regarding tasks in an assembly line run for an 8-hour shift each day is provided: Task Proceeding Task (s) Tme (min) A - 5 B - 3 C - 2 D A 1 E B 4 F C 6 G D,E 7 H G 5 I F,G 6 J H,1 4 K I 3 a)What is the theoretical minimum number of stations for a shift output of 40 units? B)if the line is balanced according to the desired cycle...