Question

On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to...

On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to that order.

Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00

Calculate the manufacturing cycle time.

A. 500 Hours

B. 507 Hours

C. 502 Hours

D. 505 Hours.

THE ANSWER IS NOT C.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Manufacturing cycle time

A. 500 Hours

Explanation:

Manufacturing cycle time = Beginning of manufacturing cycle upto packaging

Add a comment
Know the answer?
Add Answer to:
On January 4th, Stevens Manufacturing received an order for 30 uniforms. The following information pertained to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT