Eighty units of end item E are needed at the beginning of week 6. Twocases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, and one in week 4. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 100 units of J now on hand. Lead times are two weeks each for E and B, and one week for J. 3Part 2: Eighty units of end item E are needed at the beginning of week 6. Twocases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, and one in week 4. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 100 units of J now on hand. Lead times are two weeks each for E and B, and one week for J.
Prepare a material requirements plan for component J
GIVE THIS ANSWER A THUMBS UP
Your rating is highly appreciated and benefits me. Thank you!
MRP for Component J
|
Master Schedule |
Week |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
||
|
Quantity |
80 |
|||||||||
|
E LT = 2 wks. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
|||
|
Gross requirements |
80 |
|||||||||
|
Scheduled receipts |
||||||||||
|
Projected on hand |
||||||||||
|
Net requirements |
80 |
|||||||||
|
Planned-order receipts |
80 |
|||||||||
|
Planned-order releases |
80 |
|||||||||
|
B(2) LT = 2 wks. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
|||
|
Gross requirements |
160 |
|||||||||
|
Scheduled receipts |
||||||||||
|
Projected on hand |
60 |
60 |
60 |
60 |
60 |
20 |
20 |
|||
|
Net requirements |
100 |
|||||||||
|
Planned-order receipts |
120 |
|||||||||
|
Planned-order releases |
120 |
|||||||||
|
J(4) & J(3) LT = 1 wk. |
Beg. Inv. |
1 |
2 |
3 |
4 |
5 |
6 |
|
|
Gross requirements |
480 |
240 |
||||||
|
Scheduled receipts |
30 |
30 |
30 |
|||||
|
Projected on hand |
20 |
20 |
20 |
50 |
80 |
50 |
50 |
|
|
Net requirements |
460 |
160 |
||||||
|
Planned-order receipts |
480 |
180 |
||||||
|
Planned-order releases |
480 |
180 |
Eighty units of end item E are needed at the beginning of week 6. Twocases (30...
Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed at the beginning of week 8 B(2) D(3) D(2) F(2) Prepare a material requirements plan for component D. D can only be ordered in whole cases (50 units per case). One case of D is automatically received every other week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units...
QUESTION 16 The following is a list of components required to produce one unit of end item E: E: 2 B's, 3 Js Eighty units of end item E are needed at the beginning of week 6. 30 units of F are scheduled to arrve in week 2. There are 60 units of B and 20 units of F now on hand. Lead times are two weeks for E and B, and one week for F. Prepare a material requirements...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. ts Direct C End rded B(2), 3(3) G(2), B(2) H(4), B(2) 12 21 32 103 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) 405 0 Additional units b. An order for the end item is scheduled to be shipped...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand on Hand Iten End Direct Components L(2), C(1), K(3) B(2), (3) G(2), B(2) H(4), B(2) a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan.) Additional units C b. An order for the end item is scheduled to be shipped at...
One unit of A is made of one unit of B and one unit of C. B is
made of four units of C and one unit each of E and F. C is made of
two units of D and one unit of E. E is made of three units of F.
Item C has a lead time of one week; Items A, B, E, and F have
two-week lead times; and Item D has a lead time of...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand L12), c(1),x(3) B(2), 33) G(2), 8(2) H(4), B(2) 13 16 21 29 a. f 43 unts of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) Additional units b. An order for the end item is scheduled to be shipped at the start of week...
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F G H LT (wk) 2 2 1 1 1 2 1 2 Amount on hand 0 11 8 26 12 30 7 0 A. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)...