2. Joe Malay received the following report on the Division's
operation for the month of August: Direct labor rate variance =
$25,000 unfavorable; Direct labor efficiency variance = $70,000
(?). The standard calls for 3 direct labor hours per unit of output
at $28 per labor hour (SP). The standard direct labor hours for the
units manufactured (SQ) is 20 percent more than the total direct
labor hours actually worked (AQ) in August.
What was the average direct labor hourly rate (AP) the Division
paid in August?
Select one:
a. $24.00
b. $26.00
c. $28.00
d. $30.00
e. $31.25
3James Webb is the general manager of the Industrial Product Division, and his performance is measured using the residual income (RI) method. Webb is reviewing the followed forecasted information for his division for the coming year:
|
Category |
Amount (thousands) |
|
Current assets (e.g., inventory) |
$1,800 |
|
Revenue |
30,000 |
|
Plant and equipment (net book value) |
17,200 |
If the imputed interest charge (i.e., divisional cost of capital)
is 15% and Webb wants to achieve an RI target of $2 million, what
will costs have to be in order to achieve the
target?
Select one:
a. $9,000,000
b. $10,800,000
c. $23,620,000
d. $25,150,000
e. $25,690,000
2. Solution: The correct option is “d” i.e $ 30 (Refer Note below)
Note:
Since given that the standard direct labor hours for the units manufactured (SQ) is 20 percent more than the total direct labor hours actually worked (AQ) in August, the labor efficiency variance is favorable
(Standard hours for actual output-Actual hours worked)*Standard Rate per hour=$ 70000(F)
Let Actual hours worked per unit of output = “X”
Therefore Standard hours per unit of output =1.2 X
Therefore 1.2X=3 i.e X=2.5 hours i.e Actual Hours worked per unit of output=2.5 hours
Let Actual units of output = “Y”
(3Y-2.5Y) $ 28/labor hour=70000
0.5 Y=2500 i.e Y=5000 units
Given the Direct Labor Rate Variance=$ 25000 U
(Standard Rate per hour-Actual Rate Per hour)Actual hours=$ 25000(U)
Actual hours= 2.5 hours per unit*5000 units=12500 hours
($ 28 per hour-Actual rate per hour) 12500 hours=-25000
Therefore $ 28+$ 2= Actual rate per hour i.e Actual labor rate per hour=$ 30 per hour
2. Joe Malay received the following report on the Division's operation for the month of August:...