Problem 5-10 (Algo)
The following represents a project that should be scheduled
using CPM:
| IMMEDIATE PREDECESSORS | TIMES (DAYS) | |||
| ACTIVITY | a | m | b | |
| A | — | 1 | 4 | 7 |
| B | — | 1 | 3 | 5 |
| C | A | 2 | 5 | 11 |
| D | A | 1 | 8 | 9 |
| E | B | 1 | 2 | 3 |
| F | C,D | 1 | 6 | 11 |
| G | D,E | 1 | 2 | 3 |
| H | F,G | 2 | 3 | 3 |
b. What is the critical path?
a. A-D-F-H
b. B-E-G-H
c.A-D-G-H
d.A-C-F-H
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
d. What is the probability of completing this project within 22 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
| Activity | Optimistic time-a | Expected completion time-m | Pessimistic time-b | Expected time= (a+4*m+ b)/6 | Variance, (sigma)^2= (b-a/6)^2 |
| A | 1 | 4 | 7 | 4.00 | 1.00 |
| B | 1 | 3 | 5 | 3.00 | 0.44 |
| C | 2 | 5 | 11 | 5.50 | 2.25 |
| D | 1 | 8 | 9 | 7.00 | 1.78 |
| E | 1 | 2 | 3 | 2.00 | 0.11 |
| F | 1 | 6 | 11 | 6.00 | 2.78 |
| G | 1 | 2 | 3 | 2.00 | 0.11 |
| H | 2 | 3 | 3 | 2.83 | 0.03 |
PATHS
| Path | Duration | Variance |
| ADFH | 19.833 | 5.583 |
| BEGH | 9.833 | 0.667 |
| ADGH | 15.833 | 5.056 |
| ACFH | 18.333 | 1.889 |
Answer b: The critical path is the longest path i.e ADFH
Answer c: the expected project completion time through critical path is 19.833
Answer d: the probability of completing this project within 22 days is 0.8204
| step 1 | we will find the variance of the tasks which lie on critical path | 5.58 | |||
| step 2 | mean project time (u) of critical path is= | 19.83 | |||
| step 3 | Required completion time is | 22 | |||
| step 4 | standard deviation= sqrt(variance)= | 2.363 | |||
| step 5 | because Z= (given completion time- u)/standard deviation | 0.917 | |||
| step 6 | P(z)= using NORM.S.DIST(z,true) | 0.8204 | |||
Please ask, if you have any doubts through the comment section. Do rate the answer
Problem 5-10 (Algo) The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS...
The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 2 6 13 C A 1 1 4 D A 2 3 4 E B 2 4 6 F C,D 1 5 9 G D,E 1 2 9 H F,G 3 6 9 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Do not round...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A — 1 3 5 B — 1 2 3 C A 1 2 3 D A 2 3 4 E B 3 4 11 F C, D 3 4 5 G D, E 1 4 6 H F, G 2 4 5 b. What is the critical path? A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time?...
The following represents a project that should be scheduled using CPM: TIMES (DAYS) IMMEDIATE b ACTIVITY PREDECESSORS m a 1 4 7 3 5 10 B 2 5 4 6 11 D B 1 2 3 E C,D D,E F,G 3 5 7 F G 1 2 6 2 5 b. What is the critical path? A-D-F-H A-D-G-H B-E-G-H A-C-F-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS TIMES (DAYS) ACTIVITY a m b A — 1 4 7 B — 3 5 10 C A 2 5 8 D A 4 6 11 E B 1 2 3 F C,D 3 5 7 G D,E 1 2 6 H F,G 2 5 6 b. What is the critical path? B-E-G-H A-D-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round...
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b А 7 B 2 3 7 с A 3 5 7 D А 5 6 10 E B 1 2 6 F CD 1 3 6 DE 1 3 14 H F G 5 14 b. What is the critical path? A-D-G-H B-E-G-H A-D-F-H A-C-F-H c. What is the expected project completion time? (Round your answer to 3 decimal...
The following represents a project that should be scheduled using CPM: Intermediate Times(Days) Activity Predecessors a m b A ----- 1 2 6 B ----- 1 2 9 C A 2 2 11 D A 1 8 9 E B 1 2 3 F C,D 3 4 11 G D,E 1 3 11 H F,G 2 3 11 What is the critical path? What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time...
Problem 5-7 (Algo) The following activities are part of a project to be scheduled using CPM ACTIVITY IMMEDIATE PREDECESSOR TIME (HEEKS) A 9 B A. 3 C A. 7 D C E BD 4 F 3 E F G a. What is the critical path? A-C-D-E-G O A-B-D-F-G A-B-E-G A-C-D-F-G b. How many weeks will it take to complete the project? Number of weeks <Prey 3 of 8 Next>
I need help with the following problem. Schedule the following activities using CPM. ACTIVITY Immediate Predecessors Time in Weeks A ---- 2 B A 5 C A 4 D B 3 E C, D 6 F D 3 G F 3 H E, G 4 Draw the network diagram below using the square activity I have provided. Just select the object, then copy it and paste how many you need and then arrange them in the order you need and...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 3 B A 9 C A 5 D C 2 E B D 7 F D 6 G E F 4 b. What is the critical path? A-B-D-F-G A-B-E-G A-C-D-F-G A-C-D-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-B-D-F-G A-C-D-E-G A-C-D-F-G A-B-E-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B week(s)