Question

PRINCE2 Is the initiation plan included in the project plan of the PID? Also when describing...

PRINCE2

Is the initiation plan included in the project plan of the PID? Also when describing a high level timeline of the project is the initiation stage plan included?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project Initiation Document (PID) is a significant tool used in project management. It plays a role of a foundation stone or base in any project. The initiation plan is not included in the project plan of the PID.

To satisfy various project needs, PRINCE2 has three planning levels. These levels are the project plan, the stage plan and the team plan. In stage plan distinction can be made for initiation stage and management stages for implementing project. In-fact project plan is prepared in the initiation stage and after approval from project board it becomes the part of PID.

The initiation stage plan is prepared at the end of the initiation stage. Therefore, even while describing a high level timeline of the project the initiation stage plan is included at the Stage plan level.

Add a comment
Know the answer?
Add Answer to:
PRINCE2 Is the initiation plan included in the project plan of the PID? Also when describing...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT