A company's president believes that the time-cost tradeoff function for an innovation is C=200-60t+2t2. The company's president also believes that the present value of profit R=400-30t. What would be the optimal duration of the project?
Profit (Z) = R - C
Z = (400 - 3t) - (200 - 60t + 2t2)
Z = 400 - 30t - 200 + 60t - 2t2
Z = 200 + 30t - 2t2
Duration is optimized when dZ/dt = 0.
dZ/dt = 30 - 4t = 0
4t = 30
t = 7.5
A company's president believes that the time-cost tradeoff function for an innovation is C=200-60t+2t2. The company's...
The total cost C for a manufacturer during a given time period is a function of the number N of items produced during that period. To determine a formula for the total cost, we need to know the manufacturer's fixed costs (covering things such as plant maintenance and insurance), as well as the cost for each unit produced, which is called the variable cost. To find the total cost, we multiply the variable cost by the number of items produced...
4) A company's Cost function is: C=8x2-50x +103, Revenue function is: R=4x2+3. (Profit=R-C) Find the Profit equation: a. b. Find the break-even points: ( _) U c. Find the Profit intercept: (_ d. Find the max profit (Vertex): ( e. Sketch a Graph f. Domain: g. Range: h. Find the intercepts if the company wants a Profit of $200. L.), 8) Cost = x2+2x+1, Revenue = -5x2+6x-10 Profit 9) Cost = 7x2–7x+7, Revenue = 4x2+7x+7 Profit 10) Solve the Quadratic...
Engineering Management
rash C Duration (day) Cost (SR) Cost Slope (Skany) 300 500 Normal Activity by Duration .com (day) on A - 7 3600 BA55500 CB96350 DB 19 4700 Е в 10 | 2050 FC 8 1200 G F 5 7200 Γ Η Τ Ε Ι 9450 I D, G, H 4500 Cost (SK) 3900 6500 7200 4900 2200 1450 7200 10000 4600 ABD OTO D ESTU It is required to crash the project duration from its original duration to...
You may need to use the appropriate appendix table or technology to answer this question The president of Doerman Distributors, Inc., believes that 35% of the firm's orders come from first-time customers. A random sample of 200 orders will be used to estimate the proportion of first-time customers. (a) Assume that the president is correct and p 0.35. What is the sampling distribution of p for n 200? (Round your answer for o to four decimal places.) , approximating the...
Thank you!!
(2 points) An oil company discovered an oil reserve of 130 million barrels. For time t > 0, in years, the company's extraction plan is a linear declining function of time as follows: where q(t) is the rate of extraction of oil in millions of barrels per year at time t and b 0.05 and a -14. (a) How long does it take to exhaust the entire reserve? time years (b) The oil price is a constant 30...
1. A monopoly’s total cost function is TC = 200 + 8Q + 4Q2. The inverse demand function is P = 400 – 10Q. What will be the monopoly’s profit if it charges a single price to all customers? Group of answer choices a.$2,150 b.$3,420 c.$3,640 d.$2,544 $1,980 2. A Cournot oligopoly has four firms in the industry. The market price elasticity of demand is –2.5 and the marginal cost of production is $200. What is the profit-maximizing price, rounded...
#1. A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000. What are the cost and schedule variances for the project? What are the SPI and CPI? What is your assessment of the project from a cost and schedule perspective? #2. A project has just completed the 87th item in its plan. It was scheduled to have spent $168,000 at...
Assume the network and data that follow: ACTIVITY NORMAL TIME (WEEKS) NORMAL COST CRASH TIME (WEEKS) CRASH COST IMMEDIATE PREDECESSORS A 3 $ 60 2 $ 80 — B 5 70 4 110 A C 9 50 6 80 A D 7 100 6 130 A E 8 90 6 100 B F 5 30 3 50 D G 6 110 5 190 C, E, F b. Indicate the critical path when normal activity times are used. A-B-E-G A-C-F-G A-D-E-G...
Suppose that Jessica faces the following total cost function: C(y) = 2y2 + y + 200 Note that 200 denotes the fixed cost component. Use this information in answering this part of the submission question. (a) Find the Marginal cost function, Average Cost function, Average Variable cost function and the Average fixed cost function. Once you obtain these, sketch them on the grid below. (b) Derive the short run supply function for Jessica. Suppose p = 61. How much y...
Suppose that Jessica faces the following total cost function: C(y) = 2y2 + y + 200 Note that 200 denotes the fixed cost component. Use this information in answering this part of the submission question. (a) Find the Marginal cost function, Average Cost function, Average Variable cost function and the Average fixed cost function. Once you obtain these, sketch them on the grid below. (c) Derive the long run supply function for Jessica. Suppose p = 61. How much output...