Question

Given the following MRP matrix for Item Z, prepare a material requirements plan for component P....

Given the following MRP matrix for Item Z, prepare a material requirements plan for component P. Lot-for-lot ordering will be used for component P.

ITEM: Z       

Lot Size: Q=100

LT: 1

Project on Hand : 200

Period

1

2

3

4

5

6

7

Gross Requirements

600

300

270

200

Schedule Receipts

250

150

Project on Hand              200

Net Requirements

Planned Order Receipts

Planned Order Releases

ps fr unit 1 is 100 and i do not have the tree

0 0
Add a comment Improve this question Transcribed image text
Answer #1

I assume that for each unit of Z, 100 unit of p is required with L4L method and 1 week of lead time.

Below is the required MRP schedule -

Z
LT = 1
Q = 100
On Hand 1 2 3 4 5 6 7
Gross Requirement 0 0 600 0 300 270 200
Scheduled Receipts 0 250 0 0 150 0 0
Projected on Hand 200 200 450 50 50 0 30 30
Net Requirements 0 0 150 0 100 270 170
Planned Order Receipts 0 0 200 0 100 300 200
Planned Order Releases 0 200 0 100 300 200 0
P
LT = 1
Q = L4L
On Hand 1 2 3 4 5 6 7
Gross Requirement 0 20000 0 10000 30000 20000 0
Scheduled Receipts 0 0 0 0 0 0 0
Projected on Hand 0 0 0 0 0 0 0 0
Net Requirements 0 20000 0 10000 30000 20000 0
Planned Order Receipts 0 20000 0 10000 30000 20000 0
Planned Order Releases 20000 0 10000 30000 20000 0 0
Add a comment
Know the answer?
Add Answer to:
Given the following MRP matrix for Item Z, prepare a material requirements plan for component P....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for...

    Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...

  • 1. 1 Complete the following MRP matrix for item A. Then answer the questions that follow....

    1. 1 Complete the following MRP matrix for item A. Then answer the questions that follow. When are planned orders scheduled to be released? (Hint: it's the last row of the matrix). Item:  A                    LLC: 1 Period Lot size:  Mult 50       LT:   2 1 2 3 4 5 6 7 8 Gross Requirements 10 15 25 75 60 85 45 60 Scheduled Receipts Projected on Hand         | 50 Net Requirements Planned Order Receipts Planned Order Releases A. Periods 2 through 6 B....

  • Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item a...

    Problem 12-18 Develop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2. (Leave no cells...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...

  • Given the data provided for product structure, component AC101, and the planned orders of parent AB...

    Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...

  • In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order...

    In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...

  • Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct...

    Fill in the blanks In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...

  • Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and...

    Extra Credit MRP Exercise (15 Points) Given: Indented Bill of Material Master Production Schedule (MPS) and Material Requirements Planning (MRP) Tables Bill of Material (QPA) A =Finished Good LT=1 B (1 LT-3 C(2) LT=2 D(1) LT 2 LT-2 F (2) LT-2 G (1) LT=1 Answer the following questions: 1). Fill in MPS/MRP tables provided 2). For Part Number B: What is the first period in which there is a net requirement ?:_AND, What is the net requirement Quantity (in the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT