1. 1 Complete the following MRP matrix for item A. Then answer
the questions that follow.
When are planned orders scheduled to be released? (Hint: it's
the last row of the matrix).
| Item: A LLC: 1 | Period | |||||||
| Lot size: Mult 50 LT: 2 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements | 10 | 15 | 25 | 75 | 60 | 85 | 45 | 60 |
| Scheduled Receipts | ||||||||
| Projected on Hand | 50 | ||||||||
| Net Requirements | ||||||||
| Planned Order Receipts | ||||||||
| Planned Order Releases | ||||||||
A. Periods 2 through 6
B. Periods 2, 4 and 6
C. Periods 1 through 6
D. Periods 4 through 8
1.2
Complete the following MRP matrix for item A. Then answer the
questions that follow.
What is the Projected on Hand at the end of period 5?
| Item: A LLC: 1 | Period | |||||||
| Lot size: Mult 50 LT: 2 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements | 10 | 15 | 25 | 75 | 60 | 85 | 45 | 60 |
| Scheduled Receipts | ||||||||
| Projected on Hand | 50 | ||||||||
| Net Requirements | ||||||||
| Planned Order Receipts | ||||||||
| Planned Order Releases | ||||||||
A. 0
B. 15
C. 25
D. 30
Answer: The below MRP sheet is filled as below
| tem: A LLC: 1 | Period | |||||||
| Lot size: Mult 50 LT: 2 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Gross Requirements | 10 | 15 | 25 | 75 | 60 | 85 | 45 | 60 |
| Scheduled Receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Projected on Hand | 50 | 40 | 25 | 0 | 25 | 15 | 30 | 35 | 25 |
| Net Requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Planned Order Receipts | 0 | 0 | 0 | 100 | 50 | 100 | 50 | 50 |
| Planned Order Releases | 0 | 100 | 50 | 100 | 50 | 50 | 0 | 0 |
Answer 1.1 : Correct Option – A : Period 2 through 6.
Refer the above MRP chart filled for the same. It shows that planned order to be released for each period starts from period 2 to period 6 for meeting the customer demand in each period.
Answer 1.2: Correct Option – B : 15 nos.
Refer the above MRP chart filled for the same. It shows that the on hand inventory at end of period 5 is 15 nos. only. 50 nos, are planned receipts, 25 nos were previous inventory, so this make total = 75 nos. Demand for the 5th week is 60 nos. hence inventory left at the end of week 5 = 75 – 60 =15 nos.
1. 1 Complete the following MRP matrix for item A. Then answer the questions that follow....
Material Requirements Planning (MRP) Given the product tree diagram and develop a material requirements plan for item D. A 400 unit-delivery of product P is due at the beginning of week 7. Use the worksheet Product Structure Tree Inventory Information P Order Currently Scheduled Lead Item On-Hand Recpt (wk) Time Qty LAL P 100 L4L A A FIxed Q 450 Fixed Q = 600 L4L 0 C 90 100 (wk 2) 80 (wk 2) 2 50 2 C D(2 Beg...
Given the following MRP matrix for Item Z, prepare a material requirements plan for component P. Lot-for-lot ordering will be used for component P. ITEM: Z Lot Size: Q=100 LT: 1 Project on Hand : 200 Period 1 2 3 4 5 6 7 Gross Requirements 600 300 270 200 Schedule Receipts 250 150 Project on Hand 200 Net Requirements Planned Order Receipts Planned Order Releases ps fr unit 1 is 100 and i do not have the tree
Given the data provided for product structure, component AC101, and the planned orders of parent AB 500 below, use the matrix for AC101 at the bottom to compute gross requirements, projected on hand, net requirements and planned orders. Suggestion: Start by filling out the MRP matrix for AC101 with the data given. AB500 LT=2 AC101 (2) LT=3 Notes: O signifies usage. FOQ = Fixed order quantity. Item On Hand MPS Scheduled Receipts 600: Week 6 Lot Size / Order Policy...
Fill in the blanks
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER 0 4 50 5 70 75 40 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 75 50 70 Period Gross requirements Item J Scheduled receipts...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 75 50 70 On hand 40 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J OH = 40...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) 1 0 34 WEEK NUMBER 2 3 4 47 ITEM J Gross requirements On hand Net requirements Planned order receipt Planned order release 5 71 - 4 Item J LT = 1 Q = L4L Period Gross...
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.) WEEK NUMBER ITEM J 0 1 2 3 4 5 Gross requirements 73 55 74 On hand 43 Net requirements Planned order receipt Planned order release Period 1 2 3 4 5 Item J LT = 1...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
Download HW 15 (Excel download) and perform the necessary MRP calculations. Then enter selected values below. What is the Parent's Net Requirements for Period 5? What is the Parent's Net Requirements for Period 8? What is the Parent's Planned Order Receipts for Period 6? What is Part 1's Net Requirements for Period 8? What is the Part 1's Net Requirements for Period 5? What is the Part 1's Planned Order Release for Period 5? What is Part 2's Gross Requirements...
Download HW 15 (Excel download) and perform the necessary MRP calculations. Then enter selected values below. What is the Parent's Net Requirements for Period 5? What is the Parent's Net Requirements for Period 8? What is the Parent's Planned Order Receipts for Period 6? What is Part 1's Net Requirements for Period 8? What is the Part 1's Net Requirements for Period 5? What is the Part 1's Planned Order Release for Period 5? What is Part 2's Gross Requirements...