Question

Lavoie company planned to use 18,500 pounds of material costing $2.50 per pound to make 4000...

Lavoie company planned to use 18,500 pounds of material costing $2.50 per pound to make 4000 units of its product. In actually making 4,000, the company used 18,800 pounds that cost $2.54 per pound. Calculate the direct material proce variance
0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Lavoie company planned to use 18,500 pounds of material costing $2.50 per pound to make 4000...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The...

    Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound to produce 2,000 units. What is the direct materials quantity variance? Multiple Choice 0 $3,050 unfavorable. 0 $460 unfavorable. 0 $3,460 unfavorable. 0 $3,000 unfavorable. 0 $410 unfavorable. Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound...

  • 36 $ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds at $2.50 per pound Direct lab...

    36 $ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds at $2.50 per pound Direct labor 5 hours at $7.50 per hour Actual results: Units produced 8,100 units Direct material purchased 26,600 pounds at $2.70 Direct material used 24,000 pounds at $2.70 Direct labor 41,100 hours at $7.30 (8 04:26:11 $ 71,820 64,800 300,030 Print Assume that the company computes variances at the earliest point in time. The direct-material price variance is: Multiple...

  • A company has established 6 pounds of Material J at $3 per pound as the standard...

    A company has established 6 pounds of Material J at $3 per pound as the standard for the material in its Product Z. The company has just produced 1,000 units of this product, using 6,200 pounds of Material J that cost $17,680. The direct materials quantity variance is: $600 unfavorable. $920 unfavorable. $920 favorable. $600 favorable. $320 favorable.

  • Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.50 per...

    Cost standards for one unit of product no. C77: Direct material 3 pounds at $2.50 per pound $7.50 Direct labor 5 hours at $7.50 per hour 37.50 Actual results: Units produced Direct materials purchased 7,800 units 26,000 pounds at $2.70 23,100 pounds at $2.70 $70,200 Direct materials used 62,370 Direct labor 40,100 hours at $7.30 292,730 The direct-labor rate variance is: O$7,800F. O$7.950F $8,020F. O$8,000U None of these.

  • $ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds...

    $ 7.50 37.50 Cost standards for one unit of product no. 077: Direct material 3 pounds at $2.50 per pound Direct labor 5 hours at $7.50 per hour Actual results: Units produced 7,800 units Direct material purchased 26,000 pounds at $2.70 Direct material used 23,100 pounds at $2.70 Direct labor 40,100 hours at $7.30 $ 70,200 62,370 292,730 Assume that the company computes variances at the earliest point in time. The direct-labor rate variance is: Multiple Choice 0 $7,800F. 0...

  • During June, Danby Company’s material purchases amounted to 8,000 pounds at a price of $6.20 per...

    During June, Danby Company’s material purchases amounted to 8,000 pounds at a price of $6.20 per pound. Actual costs incurred in the production of 2,500 units were as follows: Direct labor: $ 121,506 ($15.40 per hour) Direct material: $ 32,798 ($6.20 per pound) The standards for one unit of Danby Company’s product are as follows: Direct Labor: Direct Material: Quantity, 3 hours per unit Quantity, 2 pounds per unit Rate, $15.00 per hour Price, $5.90 per pound     Required: Fill...

  • At the beginning of 19X4, Beal Company adopted the following standards: Direct material (3 pounds &$2.50...

    At the beginning of 19X4, Beal Company adopted the following standards: Direct material (3 pounds &$2.50 per pound) 750 3750 Direct labor (5 hours $7.50 per hour) Factory overhead: Variable ($3.00 per dircet labor hour) Fixed ($4.00 per direct labor hour) 15.00 20.00 Standard cost per unit Normal volume per month is 40,000 direct labor hours Beal's January 19X4 budget was based on normal volume. During January. Beal produced 7,800 units with records indicating the following: Direct material purchased Direct...

  • The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ $4...

    The Litton Company has established standards as follows: Direct material: 3 pounds per unit @ $4 per pound $12 per unit Direct labor: 2 hours per unit @ $8 per hour = $16 per unit Variable manufacturing overhead: 2 hours per unit@ $5 per hour $10 per unit Actual production figures for the past year are given below The company records the materials price variance when materials are purchased Units produced.. 600 units 2,000 pounds si1,400 S9,240 S5,720 Direct material...

  • Better Products Inc. planned to use $37 of material per unit but actually used $33 of material per unit, and planned to...

    Better Products Inc. planned to use $37 of material per unit but actually used $33 of material per unit, and planned to make 1,520 units but actually made 1,390 units. The flexible - budget variance for materials is O A. $6,080 unfavorable B. $6,080 favorable O C. $5,560 unfavorable O D. $5,560 favorable

  • Key Company produces a single product. The company’s standard cost per unit is based on 2.50...

    Key Company produces a single product. The company’s standard cost per unit is based on 2.50 pounds of material at a cost of $11.00 per pound. During the most recent operating period, Key used 16,080 pounds of materials at a total cost of $192,960 and produced 6,700 units of output. Use this information to address the following requirements: 1. Calculate the total budget variance for materials that Key Company would have found in its responsibility report. Indicate whether the variance...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT