Question

The Sylva Machine Shop was implementing lean throughout their shop floor and needed to determine the...

The Sylva Machine Shop was implementing lean throughout their shop floor and needed to determine the number of containers at several of their work centers. In one such work center, the demand was 200 parts per hour, and the containers they used for this part held 50 parts. It normally takes 6 hours for a full container to make a circuit through the work cell and back to its input side, and they desired to carry 12% safety stock in the system.

  1. How many containers should the lean system be using?
  2. Calculate the maximum system inventory for this part.
  3. If the required safety stock was changed to zero, how many containers should the lean system be using, all else being constant?
  4. Based on the required safety stock of zero and the number of containers computed in part c, calculate the maximum inventory for this part.
  5. Based on the required safety stock of zero and the number of containers computed in part a, what would be the new required round-trip time, all else being constant?
  6. If the demand from the original data was changed to 250 parts per hour, how many containers should the lean system be using, all else being constant?
  7. If the required round-trip time from the original data was changed to 5 hours, how many containers should the lean system be using, all else being constant?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

In kanban system, kanban cards are placed on kanban board that act as a visual control and signaling system. The kanban system monitor the work in progress and does not pull the work and make it active without proper resources that is required to do that work. The aim of Kanban is to promote transparency in the workflow within the organization in order to make the employees and management aware of the process they are involved in and what is their role within the organization. In this way employees and management could improve their effort to make the entire process effective for the organization.

Add a comment
Know the answer?
Add Answer to:
The Sylva Machine Shop was implementing lean throughout their shop floor and needed to determine the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly...

    Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system. Based on the required safety stock of zero and the number of...

  • Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area,...

    Boehm Compressors uses a lean production assembly line to make its compressors. In one assembly area, the demand is 100 parts per eight-hour day. It uses a container that holds eight parts. It typically takes about six hours to round-trip a container from one work center to the next and back again. It also desires to hold 15% safety stock of this part in the system. If it reduced the number of containers by one, how would this impact the...

  • A manufacturing assembly line has a demand for specific part of 1,200 parts per eight-hour day....

    A manufacturing assembly line has a demand for specific part of 1,200 parts per eight-hour day. It wants to design a lean system using containers. It takes about four hours to round-trip a container from one work center to the next and back again. It also wants to hold 10% safety stock of this part in its system. a) Design a container system. State each container's size and how many are needed. b) Calculate the maximum system inventory for this...

  • Suppose a Lean work center is being operated with a container size of 25 units and...

    Suppose a Lean work center is being operated with a container size of 25 units and a demand rate of 100 units per hour. Also assume it takes 180 minutes lead time to fulfill a downstream container request. Assuming a safety stock factor of 5 percent, how many containers should be required? Select one: O a. none of these O b. 756.0 containers O c. 12.6 containers O d. 1,080.0 containers O e. 18.0 containers

  • Explain how the production schedule is developed and communicated to the shop-floor in a Just-in-Time (JIT)...

    Explain how the production schedule is developed and communicated to the shop-floor in a Just-in-Time (JIT) manufacturing system. Q. B8 (a) (10 marks) Define kanban as it is understood in JIT systems and explain the role and operation of a conveyance or C kanban in the production system. (b) (6 marks) (c) Data for a particular part that is controlled by a two-card kanban system on a JIT feeder line is as follows: daily demand: 500 units average waiting and...

  • Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day,...

    Copenhagen Industries uses a kanban system to manage production of their subassembly. In a 10-hour day, they use 1,500 units and use containers that can hold 50 units each. It takes 45 minutes to fill and move a container of parts to the right place on the subassembly line that is currently rated at a 15% safety factor. If the required safety stock was changed to zero and 3 containers were being used in the system, calculate the maximum inventory....

  • QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased...

    QUESTION 23 Current challenges in operations Management include all of the following EXCEPT: lean operations increased communication cost. rapid product development. sustainability mass customization how many hours would the plant have to work to produce 1000 parts? QUESTION 24 A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were increased 20 between 9 and 10 hours between 2 and 6 hours less than 2 hours between 6 and 8 hours between 8 and 9 hours...

  • 03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a...

    03-Consider the product structure tree shown below: D(2) C(3) A(2) E(3) B(2) E(3) A(3) With a beginning inventory of zero for all components and finished items, how many assembly E's are needed to produce 25 product X's? A) 125 B) 375 C) 400 D) 250 Q4-Livernonions Industries uses a Kanban system to manage production of the BR-549 subassembly. In an eight-hour day, they use 900 units and use containers that can hold 30 units each. It takes 120 minutes to...

  • Please read the opening vignette about Community Medical Center in Missoula. How have they used lean...

    Please read the opening vignette about Community Medical Center in Missoula. How have they used lean management approaches to efficiently utilize resources (human resources and processes), eliminate waste, incorporate Total Quality Management, and also motivated the Respect for People I have uploaded the figures from 10.1 to 10.6 to give you more details. Please use them when explaining the question. Thank you! Orthopedic surgeon Doug Woolley was frustrated. A bottleneck in the recovery room at the Community Medical Center in...

  • Please read the opening vignette about Community Medical Center in Missoula. How have they used lean...

    Please read the opening vignette about Community Medical Center in Missoula. How have they used lean management approaches to efficiently utilize resources (human resources and processes), eliminate waste, incorporate Total Quality Management, and also motivated the Respect for People I have uploaded the figures from 10.1 to 10.6 to give you more details. Please use them when explaining the question. Thank you! Orthopedic surgeon Doug Woolley was frustrated. A bottleneck in the recovery room at the Community Medical Center in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT