Question

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 3,600,000 $ 4,050,000 $ 1,485,000
Estimated costs to complete as of year-end 5,400,000 1,350,000 0
Billings during the year 3,000,000 4,650,000 2,350,000
Cash collections during the year 2,800,000 4,600,000 2,600,000

Westgate Construction uses the completed contract method of accounting for long-term construction contracts.

Required:

1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
2-a. In the journal below, complete the necessary journal entries for the year 2018 (credit "Various accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary journal entries for the year 2019 (credit "Various accounts" for construction costs incurred).
2-c. In the journal below, complete the necessary journal entries for the year 2020 (credit "Various accounts" for construction costs incurred).

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Calculate The Amount Of Revenue And Gross Profit (Loss) To Be Recognized In Each Of The Three Years.

Year

Gross Profit

2018

0

2019

0

2020

($10000000-3600000-4050000-1485000)

$865000

Under Completed Contract Method Profit Only Recognized On Completion Of Contract

Journal Entries for the Year 2018

Date

Account Title

Debit

Credit

Construction In Progress

$3600000

            Various Accounts

$3600000

(To Record Current Year Construction Costs)

Accounts Receivable

$3000000

      Billing On Construction Contract

$3000000

(To Record Progress Billings)

Cash

$2800000

     Accounts Receivable

$2800000

(To Record Cash Collections)

Journal Entries for the Year 2019

Date

Account Title

Debit

Credit

Construction In Progress

$4050000

            Various Accounts

$4050000

(To Record Current Year Construction Costs)

Accounts Receivable

$4650000

      Billing On Construction Contract

$4650000

(To Record Progress Billings)

Cash

$4600000

     Accounts Receivable

$4600000

(To Record Cash Collections)

                Journal Entries for the Year 2020

Date

Account Title

Debit

Credit

Construction In Progress

$1485000

            Various Accounts

$1485000

(To Record Current Year Construction Costs)

Accounts Receivable

$2350000

      Billing On Construction Contract

$2350000

(To Record Progress Billings)

Cash

$2600000

     Accounts Receivable

$2600000

(To Record Cash Collections)

Construction In Progress

$865000

Cost Of Construction

$9135000

              Revenue From Contracts

$10000000

Add a comment
Know the answer?
Add Answer to:
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa ...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,400,000 5,600,000 2,000,000 1,800,000 2022 $3,600,000 2,000,000 4,000,000 3,600,000 2023 $2,200,000 0 4,000,000 4,600,000 Assume that Westgate Construction's contract with Santa Clara County does...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 1,900,000 3,946,000 4,154,000 Cash collections during the year 1,700,000 3,500,000 4,800,000 Assume that Westgate Construction’s contract with Santa...

  • In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT