in 2018, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2020. Information related to
the contract is as follows:
| 2018 | 2019 | 2020 | |||||||
| Cost incurred during the year | $ | 2,100,000 | $ | 2,450,000 | $ | 2,695,000 | |||
| Estimated costs to complete as of year-end | 4,900,000 | 2,450,000 | 0 | ||||||
| Billings during the year | 2,200,000 | 2,350,000 | 5,450,000 | ||||||
| Cash collections during the year | 1,900,000 | 2,300,000 | 5,800,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
2-a. In the journal below, complete the
necessary journal entries for the year 2018 (credit "Various
accounts" for construction costs incurred).
2-b. In the journal below, complete the necessary
journal entries for the year 2019 (credit "Various accounts" for
construction costs incurred).
2-c. In the journal below, complete the necessary
journal entries for the year 2020 (credit "Various accounts" for
construction costs incurred).



in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 3,600,000 $ 4,050,000 $ 1,485,000 Estimated costs to complete as of year-end 5,400,000 1,350,000 0 Billings during the year 3,000,000 4,650,000 2,350,000 Cash collections during the year 2,800,000 4,600,000 2,600,000 Westgate Construction uses the completed contract method...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,291,000 $ 3,555,000 $ 2,259,400 Estimated costs to complete as of year-end 5,609,000 2,054,000 0 Billings during the year 2,110,000 3,736,000 4,154,000 Cash collections during the year 1,855,000 3,500,000 4,645,000 Westgate...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a
contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2023. Information related to
the contract is as follows:
2021
2022
2023
Cost incurred during the year
$
2,975,000
$
3,825,000
$
1,870,000
Estimated costs to complete as of year-end
5,525,000
1,700,000
0
Billings during the year
2,500,000
4,300,000
3,200,000
Cash collections during the year
2,300,000
4,100,000
3,600,000
Assume that Westgate Construction’s contract with Santa...