Question

You realize that the approved cost baseline must change because of the approval of a major...

You realize that the approved cost baseline must change because of the approval of a major scope change on your project. Your NEXT step should be to:

a. Estimate the magnitude of the scope change

b. Issue a budget update

c. Document lessons learned

d. Execute the approved scope change

0 0
Add a comment Improve this question Transcribed image text
Answer #1

d) Execute the approved scope change is the next step.

Please give positive rating,

Thanks

Add a comment
Know the answer?
Add Answer to:
You realize that the approved cost baseline must change because of the approval of a major...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During these project objectives, you will work with project scope and handling changes to prevent catastrophic...

    During these project objectives, you will work with project scope and handling changes to prevent catastrophic failure to the project. The project scope is usually defines as the use-case documentation is created and approved. The project manager should finally get signatures from the other managers when everyone agrees on the final draft of the project. The final draft is the scope and it will typically not change unless there is a change request. At the bottom of the project use-case...

  • 4. You are the project finance manager on a project that is coming in over budget...

    4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...

  • QUESTION 9 Activity based costing allocates overhead (indirect costs) to fixed costs based upon four different...

    QUESTION 9 Activity based costing allocates overhead (indirect costs) to fixed costs based upon four different types of drivers. Which of the following is one of the cost drivers that serves as a basis of cost allocation? ​ a. direct equipment costs b. number of labor hours c. number of units produced d. quantity of materials used QUESTION 13 Which of these is NOT one of the items that can provide useful assistance to a project team to define the...

  • Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically...

    Sample Questions (Midterm Exam) Chapter 5 Initiating and Planning Systems Development Projects 1) Who is typically responsible for performing the PIP process? A) Managers B) Users C) Systems analyst D) The basiness unit 2) What is an example of a project assumption? A) Size B) Potential problems C) Soope D) Complexity Answer: B Difficulty: Difficult AACSB: Information Technology LO: 5.1 Deseribe the steps involved in the project initiation and planning process Classification: Concept 3) What is the tem that describes...

  • As a project goes through the execution phase, project control is critical to ensure that a...

    As a project goes through the execution phase, project control is critical to ensure that a project stays within the constraints of time, cost, and scope. A project manager will use different monitoring techniques to help keep the project within these constraints. If a project incurs changes, becomes delayed, or costs become higher, a project manager will execute change control to document and determine how to handle the change. Once a project is completed, the project team should complete a...

  • !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a...

    !!!Only Project 2 need to be answered!!! Project Report 1 Once the business case has been approved, you need to make a project plan showing each task. Assume you are a project manager to lead your team to acquire an additional delivery van for the company. Please find the details below. The current month is January. Activity (What is to be done?) Objective (Why will we do it?) Resources (Where will it be done?) Procedures (How will it be done?)...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • HEA 285 Wellness Project Guide Sheet The wellness project focuses on the process of changing personal behavior. Th...

    HEA 285 Wellness Project Guide Sheet The wellness project focuses on the process of changing personal behavior. The primary focus is the PROCESS of behavior ou e comfortable working with and sharing with your instructor. Please see your this project. Objective: The purpose of the wellness projet is to 1. Demo nstrate knowledge of lifestyle behaviors that promote wellness & reduce the risk of illness, injury. and disease 2. Demonstrate responsible decision making skillsfor the enhancement of individual Steps to...

  • Step 1: Design and create the tables You must create additional tables to hold Project and...

    Step 1: Design and create the tables You must create additional tables to hold Project and Activity Data. A project represents the construction of a facility with a limited scope of work and financial funding. A Project can be composed of many activities which indicate the different phases in the construction cycle. Example Project Name: Bobba Fett’s Bounty Chase Ride An activity represents the work that must be done to complete the project. Example Activity Name: For Example activity name...

  • The Cost of Capital: Cost of New Common Stock If a firm plans to issue new...

    The Cost of Capital: Cost of New Common Stock If a firm plans to issue new stock, flotation costs (investment bankers' fees) should not be ignored. There are two approaches to use to account for flotation costs. The first approach is add the sum of flotation costs for the debt, preferred, and common stock and add them to the initial investment cost. Because the investment cost is increased, the project's expected return is reduced so it may not meet the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT