Question

4. You are the project finance manager on a project that is coming in over budget...

4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except

  1. A description of how cost changes should be managed and controlled is found in the cost management plan.
  2. Approved cost changes are reflected in the cost baseline.
  3. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that must be realized for the remaining work of the project to meet the BAC goal.
  4. The equation, EAC = BAC/cumulative CPI, is used to forecast an estimate at completion assuming future project performance will be the same as past performance.
0 1
Add a comment Improve this question Transcribed image text
Answer #1

Answer

following statements are true regarding the Control Costs process except

C) The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that must be realized for the remaining work of the project to meet the BAC goal.

(The correct formula used to determine the cost performance that must be realized for the remaining work of the project to meet the BAC goal, is EAC = AC + [BAC - EV / (Cumulative CPI x Cumulative SPI))

Add a comment
Know the answer?
Add Answer to:
4. You are the project finance manager on a project that is coming in over budget...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • 1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project...

    1 In regard to Project Work, which activity refers to “reviewing the progress and capturing project performance data with reference to the project plan, developing performance measures, and communicating performance information?” a. controlling b. monitoring c. executing d. managing 3 Which of the following formulas represents the schedule performance index (SPI)? a. EV/PV b. EV PV c. EV AC d. EV/AC 4 If your sponsor asks for an estimate as to how much more money your team needs to complete...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • 2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate....

    2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Your project exceeded costs in the past caused by an underestimation of resource costs in the...

    Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at 51.000.000, what should be your new EAC (estimate at completion)? A) $1.800.000 B) $2.000.000 C) $2.200.000 D) $2.400.000

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

  • Using the below information answer only part e bolded. Given the following information for a one-year...

    Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...

  • You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned...

    You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT