Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at 51.000.000, what should be your new EAC (estimate at completion)? A) $1.800.000 B) $2.000.000 C) $2.200.000 D) $2.400.000
Ans:
Given PV = $ 1,200,000 , EV = $ 1,000,000 , AC = $ 1,200,000
BAC-EV = $ 1,000,000
Need to calculate,
EAC = BAC / CPI
BAC - EV = $ 1,000,000
BAC = 1,000,000 + EV
BAC = $ 2,000,000
CPI = EV / AC
= $ 1,000,000 / $ 1,200,000
= 1 / 1.2
EAC = 2,000,000 * 1.2
= $ 2,400,000
Option D , $ 2,400,000
Your project exceeded costs in the past caused by an underestimation of resource costs in the...
4. You are the project finance manager on a project that is coming in over budget and requires a cost change through the cost change control system. You know all of the following statements are true regarding the Control Costs process except A description of how cost changes should be managed and controlled is found in the cost management plan. Approved cost changes are reflected in the cost baseline. The equation, (BAC-AC)/(BAC-EV) is used to determine the cost performance that...
A project was budgeted at $106915. The project is now being executed. The following figures have been determined: PV:$36282 EV:$62637 AC:$50020 Assume that the cost variance was caused by the purchase of computer hardware last month, but that you do not expect any more variances from your original spending plan going forward. To the nearest dollar, what estimate at completion (EAC) do you predict?
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
I have this case study to solve. i want to ask which
type of case study in this like problem, evaluation or decision? if
its decision then what are the criterias and all?
Stardust Petroleum Sendirian Berhad: how to inculcate the pro-active safety culture? Farzana Quoquab, Nomahaza Mahadi, Taram Satiraksa Wan Abdullah and Jihad Mohammad Coming together is a beginning; keeping together is progress; working together is success. - Henry Ford The beginning Stardust was established in 2013 as a...