13.10 An imaging lab is launching a project to relocate to a newly constructed space, which will require relocation of numerous workstations as well as six imaging cameras. Table EX 13.10 displays the duration (in weeks) and precedence relationships among this project's activities.
a. Construct an activity on node network for this project.
b. Determine the critical path and the project completion time.
c. Calculate ES, LS, EF, LF, and slack time for each activity.
Table EX 13.10
|
Activity |
Description |
Duration |
Predecessor |
|
A |
Prep new space for equipment |
1 |
|
|
B |
Assess relocation of existing telephones and need for new numbers |
2 |
A |
|
C |
Identify printer locations and routing order with RIS/IT |
8 |
A |
|
D |
Assess existing office workstation furniture |
1 |
B |
|
E |
Order new furniture based on assessment |
10 |
C,D |
|
F |
Relocate office workstations |
1 |
E |
|
G |
Relocate computers |
1 |
F |
|
H |
Relocate telephones |
1 |
F |
|
I |
Complete staged move of imaging equipment |
3 |
A |
Answer a:

Answer b:
| Paths | duration |
| ABDEFG | 16 |
| ABDEFH | 16 |
| ACEFG | 21 |
| ACEFH | 21 |
| AI | 4 |
ACEFG and ACEFH are critical paths with longest duration
Answer c:
| Activities | Duration | ES, Early start=Max of early finish of last activities | EF, Early finish = early start + duration | LF, Late finish= Min of late start of after activities | LS, Late start= late finish - duration |
Slack= LF-EF, Slack is 0 for critical activity |
| A | 1 | 0 | 1 | 1 | 0 | 0 |
| B | 2 | 1 | 3 | 8 | 6 | 5 |
| C | 8 | 1 | 9 | 9 | 1 | 0 |
| D | 1 | 3 | 4 | 9 | 8 | 5 |
| E | 10 | 9 | 19 | 19 | 9 | 0 |
| F | 1 | 19 | 20 | 20 | 19 | 0 |
| G | 1 | 20 | 21 | 21 | 20 | 0 |
| H | 1 | 20 | 21 | 21 | 20 | 0 |
| I | 3 | 1 | 4 | 21 | 18 | 17 |
13.10 An imaging lab is launching a project to relocate to a newly constructed space, which...
2.
Can the project be completed before construction can begin,
which is scheduled 40 weeks later?
a.
Yes, because the project duration time is 39 weeks.
b.
No, because the project duration time is 41 weeks.
c.
No, because the project duration time is 42 weeks.
d.
Yes, because the project duration time is 40 weeks.
3.
Which activities can be delayed without delaying the projection
completion time?
a.
B, D and F
b.
B, D and G
c.
A,...