You want to determine the control lines for a "P" chart for quality control purposes. If the total number of defects from all samples is 2,500, the number of samples is 100, and the sample size is 50, which of the following would be the standard deviation used in developing the control lines?

a. .0707

b. .4900

c. .2499

d. .1556

e. .02499

Please show all steps and where all numbers come from if they aren't already given.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. A. 0707

P-BAR = TOTAL NUMBER OF DEFECTS / (SAMPLE SIZE * NUMBER OF SAMPLES)

STDEV = SQRT((PBAR * (1 - PBAR)) / SAMPLE SIZE

TOTAL DEFECTS = 2500
SAMPLE SIZE = 50
NUMBER OF SAMPLES = 100


PBAR = 2500 / (50 * 100) = 0.5
STDEV = SQRT((0.5 (1 - 0.5)) / 50 = 0.0707

Add a comment
Know the answer?
Add Answer to:
You want to determine the control lines for a "P" chart for quality control purposes. If...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2 You want to determine the control lines for a “P” chart for quality control...

    Question 2 You want to determine the control lines for a “P” chart for quality control purposes. If the total number of defects from all samples is 560, the number of samples is 70 and the sample size is 80, what would be the standard deviation used in developing the control lines? question 3 Assume a fixed cost for a process of $120,000. The variable cost to produce each unit of product is $35 and the selling price for the...

  • 1 pts D Question 11 You want to determine the control lines for a p-chart for...

    1 pts D Question 11 You want to determine the control lines for a p-chart for quality control purposes. If the total number of defects from all samples is 250, the number of samples is 100, and the sample size is 50, which of the following would be the standard deviation used in developing the control lines? O 0.1556 0.2499 0 0.0707 O 0.0308 O 0.02499

  • (0) Des the prcess producing the cookies appear to be in control? What ctions would you...

    (0) Des the prcess producing the cookies appear to be in control? What ctions would you ssk based on the inspection results 4 (10 points) The quality of a cookie production job has been examined, and the results are shown below. The same definition of defect used in Problem 3 is also used here. Cookie No 1O 9918 27918 92799 0 Size (in) Number of defects 0 0 2 (a) Using an appropriate control chart, to construct the control limits...

  • Binomial Distributions Given your statistical knowledge, you have been asked to assist the quality control manager of a...

    Binomial Distributions Given your statistical knowledge, you have been asked to assist the quality control manager of a local manufacturer in establishing and seeing that the factory conforms to standards set by management. The facility manufactures a new electronic toy. The factory can produce 1000 toys per day. Management has indicated that initially they will be satisfied if the defect rate is 3% or less. Since you can’t quality-test every toy produced, you suggest that a random sample of 40...

  • A gear has been designed to have a diameter of 3 inches. The standard deviation of the process is 0.3 inch. A control chart is shown. Each chart has horizontal lines drawn at the mean, μ, μ 2o, and a...

    A gear has been designed to have a diameter of 3 inches. The standard deviation of the process is 0.3 inch. A control chart is shown. Each chart has horizontal lines drawn at the mean, μ, μ 2o, and at μ 3G. Determine if the process shown is in control or out of control. Explain Is the process in control or out of control? Select all that apply A. Out of control, because a point lies more than three standard...

  • 1 - Almost all processes, regardless on whether they are goods or services, exhibit some type...

    1 - Almost all processes, regardless on whether they are goods or services, exhibit some type of variation in their output. For example, a box of cereal may say that it contains 16 ounces, but in reality, it may be a little bit more, or a little bit less. The machine pouring the cereal into the box may not be adjusted properly, and it may only put 15.8 ounces in each box, on the average. This would be considered an...

  • 43. Statistically, a population is defined as aQID 422 1) Subset of size n from all possible obje...

    43. Statistically, a population is defined as aQID 422 1) Subset of size n from all possible objects of interest 2) Subset of a random sample. 3) Set or collection of all possible objects of interest 4) Random selection of objects from all possible objects of interest 44. The purpose of multi-voting is to QID 595 1) Generate a list of potential failure modes. 2) Identify the greatest number of defects. 3) Come to a concensus on the relative importance...

  • You are considering relaxing your control requirements that determine what is acceptable quality; you have been...

    You are considering relaxing your control requirements that determine what is acceptable quality; you have been using a 99.0% confidence interval but want to begin using a 97.5% confidence interval. Your team has collected the following data from 4 samples of 7 observations each. The calculated standard deviation is 13.981. Sample 1 Sample 2 Sample 3 Sample 4 Obs 1 392.2 415.1 413.6 402.2 Obs 2 392.3 408.1 394.9 418.3 Obs 3 405.4 428.6 410.1 419.9 Obs 4 410.3 398.2...

  • What is a control chart? What are its main features and how is it used? I...

    What is a control chart? What are its main features and how is it used? I included the definition of a control chart so there isn't any confusion. Please include an explantion in your own words. Control Chart Assuming production engineers have gotten everything to work such that the process conforms to specifications (the average of the process is close to the target value and the variability [standard deviation] is very small), after that they have to ensure that the...

  • Tom is the quality control manager for the company XYZ. XYZ recently received some complaints about...

    Tom is the quality control manager for the company XYZ. XYZ recently received some complaints about its product D's quality and the general manager Steve requested Tom to investigate it. To gain a better understanding of the production process, Tom decided to use p-chart to monitor and identify the assignable cause variations. For the next 10 working days, Tom collected 10 samples (each of the size 300 units) and found the following number of defects, 4, 6, 0, 1, 3,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT